PROGRESS REPORT

5 Apr 2011 07:00

RNS Number : 2784E
Patagonia Gold PLC
05 April 2011
 



PATAGONIA GOLD PLC

 

  5th April 2011

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final preparations for the commissioning of the Lomada Trial Heap leach project are nearing completion. Irrigation for conditioning of the ore pad is scheduled to commence on the 10th April with handover of the commissioned process facility by the construction company, INFA, scheduled for the 25th April.

 

·; Initial results from the recently completed extension and infill drilling campaign on the Lomada deposit are highly encouraging, including drill hole LLD10-17 intersecting 18 metres at 10.95 grams per tonne gold . A Resource and Scoping study upgrade is in progress with completion anticipated in Q2.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,500 ounces of gold for the first 6 metre loading.

 

Work on the Lomada project commenced in late September 2010. All sections of works are now complete with the exception of the processing facility, the commissioning of which will commence next week, with handover by the construction company, INFA, scheduled for the 25th April.

 

All staff and operators have been hired and are currently undergoing training in the safe use and operation of the facilities and equipment on site. Power generators, fuel and water storage together with other ancillary items have been installed and are in operation. Sufficient reagents and consumables have been purchased for the anticipated life of the Lomada project.

 

Full operation of the Lomada project will commence soon after the commissioning of the processing plant with the first production of gold expected in early May.

 

Updated images of the Lomada project can be viewedon the website, www.patagoniagold.com 

 

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational.

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category. Results received to date are highly encouraging and include:

 

Hole No.

From

To

Interval

Grade

metres

metres

metres

Au g/t

LLD-10-01

93.00

99.00

6.00

11.22

including

95.00

97.00

2.00

20.30

LLD-10-03

71.00

85.00

14.00

5.67

LLD-10-14

54.00

74.00

20.00

6.86

including

60.00

67.00

7.00

14.52

LLD-10-15

97.00

112.00

15.00

3.91

including

100.00

105.00

5.00

7.62

LLD-10-17

61.00

79.00

18.00

10.95

including

73.00

78.00

5.00

27.14

LLD-10-24

98.00

107.00

9.00

4.37

 

Table 1: Lomada Project table of significant Intercepts 2010/11 DDH extension and infill.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC (CAM) of Lakewood, Colorado, to prepare a NI 43-101 report for the upgrade of the resource at Lomada, scheduled for completion in Q2, 2011.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 Scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSUFMLFFSESL
Date   Source Headline
3rd Nov 20177:00 amRNSProduction Guidance and Resource Update
11th Oct 20177:24 amRNSCalcatreu Option Extension
27th Sep 20177:00 amRNSHalf Yearly Financial Statements
19th Sep 20171:18 pmRNSInterim Results Announcement Date Replacement
19th Sep 20177:00 amRNSInterim Results Announcement Date
31st Aug 20171:00 pmRNSCap-Oeste and Exploration Update
10th Jul 20177:00 amRNSOperations Update for Cap-Oeste
1st Jun 20177:00 amRNSCompletion of the Disposal of COSE
5th May 20177:00 amRNSOperations Update
2nd May 20177:00 amRNSChange of Registered Office Address
27th Apr 201712:40 pmRNSResult of AGM
25th Apr 20177:00 amRNSDisposal of COSE and Option
19th Apr 20173:20 pmRNSHolding(s) in Company
28th Mar 20177:00 amRNSFinal Results for the Year Ended 31 December 2016
23rd Dec 20167:00 amRNSCap-Oeste Project Operations Update
7th Nov 20167:00 amRNSUruguay Exploration Update
31st Oct 20167:00 amRNSCap-Oeste Project Operations Update - REPEAT
28th Oct 20165:39 pmRNSCap-Oeste Project Operations Update
29th Sep 20167:00 amRNSHalf Yearly Financial Statements
28th Sep 20167:00 amRNSInterim Results Announcement Date
30th Aug 20167:00 amRNSCap-Oeste Project and Lomada Operations Update
1st Jul 201612:00 pmRNSBoard Changes / Issue of shares to Directors
1st Jul 20167:00 amRNSChange of Broker
16th Jun 20162:05 pmRNSSecond Price Monitoring Extn
16th Jun 20162:00 pmRNSPrice Monitoring Extension
25th May 20169:00 amRNSHolding(s) in Company
20th May 20167:00 amRNSFurther Subscription
10th May 20163:20 pmRNSResult of Open Offer and General Meeting
10th May 20163:14 pmRNSResult of AGM
22nd Apr 20167:00 amRNSSubscription and Open Offer
15th Apr 20167:00 amRNSFinal Results
26th Feb 20167:00 amRNSUpdate on Lomada and Cap-Oeste
2nd Feb 20167:00 amRNSTrilogy Earn-In Agreement
6th Jan 20167:00 amRNSFurther re: Trilogy earn-in agreement
23rd Dec 20157:00 amRNSRemoval of tax on gold exports
21st Dec 20157:00 amRNSEconomic & fiscal policy changes in Argentina
24th Nov 20157:00 amRNSLomada Production Update
9th Nov 20157:00 amRNSProposed Earn-In Agreement
26th Oct 20154:40 pmRNSSecond Price Monitoring Extn
26th Oct 20154:35 pmRNSPrice Monitoring Extension
30th Sep 20157:00 amRNSHalf Yearly Report
21st Aug 20157:00 amRNSChange of Registered Office
19th Jun 20157:00 amRNSAdditional Listing/Directors' Shareholdings
10th Jun 20153:52 pmRNSResult of AGM
10th Jun 201510:30 amRNSDirectorate Change
1st Jun 20157:00 amRNSDirectorate Change
15th May 20157:00 amRNSPosting of Annual Report and Notice of AGM
12th May 20152:21 pmRNSCap-Oeste infill drilling update
21st Apr 20157:00 amRNSAppointment of CEO
9th Apr 20157:00 amRNSFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.