PROGRESS REPORT

5 Apr 2011 07:00

RNS Number : 2784E
Patagonia Gold PLC
05 April 2011
 



PATAGONIA GOLD PLC

 

  5th April 2011

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final preparations for the commissioning of the Lomada Trial Heap leach project are nearing completion. Irrigation for conditioning of the ore pad is scheduled to commence on the 10th April with handover of the commissioned process facility by the construction company, INFA, scheduled for the 25th April.

 

·; Initial results from the recently completed extension and infill drilling campaign on the Lomada deposit are highly encouraging, including drill hole LLD10-17 intersecting 18 metres at 10.95 grams per tonne gold . A Resource and Scoping study upgrade is in progress with completion anticipated in Q2.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,500 ounces of gold for the first 6 metre loading.

 

Work on the Lomada project commenced in late September 2010. All sections of works are now complete with the exception of the processing facility, the commissioning of which will commence next week, with handover by the construction company, INFA, scheduled for the 25th April.

 

All staff and operators have been hired and are currently undergoing training in the safe use and operation of the facilities and equipment on site. Power generators, fuel and water storage together with other ancillary items have been installed and are in operation. Sufficient reagents and consumables have been purchased for the anticipated life of the Lomada project.

 

Full operation of the Lomada project will commence soon after the commissioning of the processing plant with the first production of gold expected in early May.

 

Updated images of the Lomada project can be viewedon the website, www.patagoniagold.com 

 

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational.

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category. Results received to date are highly encouraging and include:

 

Hole No.

From

To

Interval

Grade

metres

metres

metres

Au g/t

LLD-10-01

93.00

99.00

6.00

11.22

including

95.00

97.00

2.00

20.30

LLD-10-03

71.00

85.00

14.00

5.67

LLD-10-14

54.00

74.00

20.00

6.86

including

60.00

67.00

7.00

14.52

LLD-10-15

97.00

112.00

15.00

3.91

including

100.00

105.00

5.00

7.62

LLD-10-17

61.00

79.00

18.00

10.95

including

73.00

78.00

5.00

27.14

LLD-10-24

98.00

107.00

9.00

4.37

 

Table 1: Lomada Project table of significant Intercepts 2010/11 DDH extension and infill.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC (CAM) of Lakewood, Colorado, to prepare a NI 43-101 report for the upgrade of the resource at Lomada, scheduled for completion in Q2, 2011.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 Scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSUFMLFFSESL
Date   Source Headline
4th Mar 201010:00 amRNSDrilling Report
11th Jan 20103:54 pmRNSExercise of Options
10th Dec 20094:03 pmRNSExercise of Options
1st Dec 20097:00 amRNSDrilling Results
30th Nov 20097:00 amRNSSanta Cruz Legislation Update
10th Nov 20097:00 amRNSDrilling Report
15th Oct 20092:40 pmRNSChange of Name of Nominated Adviser
8th Oct 20097:00 amRNSUpdated Resource Estimate
18th Sep 20097:00 amRNSHalf Yearly Report
24th Jul 20094:05 pmRNSHoldings in Company
24th Jun 200911:03 amRNSGrant of options
23rd Jun 20097:00 amRNSDrilling Report
9th Jun 20094:29 pmRNSResult of AGM
9th Jun 20097:00 amRNSDrilling Report
11th May 20097:00 amRNSDrilling Update
28th Apr 20097:00 amRNSFinal Results
8th Apr 20097:00 amRNSProgress Report
12th Mar 200912:47 pmRNSHolding(s) in Company
4th Mar 200910:51 amRNSPlacing and Subscription
23rd Feb 20097:00 amRNSDrilling Report
4th Feb 20097:00 amRNSPROGRESS REPORT
20th Jan 200910:07 amRNSRe-pricing of Options
13th Jan 20097:00 amRNSDrilling Report
3rd Dec 20087:00 amRNSDrilling Update
20th Nov 20088:21 amRNSLOMADA-SCOPING STUDY RESULTS - REPLACEMENT
20th Nov 20087:00 amRNSLOMADA-SCOPING STUDY RESULTS
4th Nov 20081:02 pmRNSResult of GM
4th Nov 20087:00 amRNSRESOURCE STATEMENT
22nd Oct 20082:32 pmRNSPlacing
30th Sep 200812:56 pmRNSNotice of General Meeting
29th Sep 20087:00 amRNSInterim Results
1st Aug 20082:08 pmRNSHolding(s) in Company
15th Jul 200811:07 amRNSPlacing
18th Jun 20083:35 pmRNSPosting of Annual Report & Ac
4th Jun 20089:42 amRNSGrant of options
3rd Jun 20084:08 pmRNSResult of AGM
3rd Jun 20087:00 amRNSDrilling Report
9th May 20087:00 amRNSLetter of Intent
1st May 20087:01 amRNSFinal Results
23rd Apr 20087:00 amRNSDrilling Update
18th Mar 20087:00 amRNSDrilling Report
4th Feb 20087:00 amRNSAdditional Listing
28th Jan 20087:00 amRNSDrilling Update
9th Jan 200810:02 amRNSPlacing
26th Nov 20077:00 amRNSDrilling Update
30th Oct 20077:01 amRNSAppointment of Broker
4th Oct 20077:00 amRNSResource Statement
27th Sep 20077:01 amRNSInterim Results
16th Aug 20073:49 pmRNSWebsite Information
6th Aug 20075:12 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.