Barruecopardo Tungsten Project Update

14 Dec 2018 07:00

RNS Number : 4551K
Ormonde Mining PLC
14 December 2018
 

14 December 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project: Construction and Commissioning Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

The development schedule has progressed in line with previous guidance of first production of tungsten concentrates from the beginning of February 2019. Key progress includes:

 

· Crush and Screen Plant commissioning nearing completion;

· Process Plant:

o Installation of equipment and supporting structures almost complete;

o Pipework and low voltage electrical installations very advanced;

o Commissioning of some circuits has commenced.

· Water Management System:

o Water treatment plant commissioning complete;

o Dewatering of the historic pit is ongoing with over 100,000 cubic metres pumped from the pit to the water dams (approximately 10% of the historic pit water content).

· Open pit mining contract awarded and mobilisation of mining equipment underway;

· Key operations staff recruited, and first tranche of plant operators recruited and in training;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"With substantial progress made on construction activities during the quarter, the Project has now entered a transition period as construction activities begin to wind down and mine commissioning activities ramp up significantly. It is particularly pleasing to have recently completed the recruitment of the first wave of plant operators, and to see the commencement of process plant commissioning.

 

"I would like to praise the hard work and professionalism of the site team and contractors as they continue to progress the Project through this busy commissioning period. The Project schedule remains in line with previous guidance, with the production of first tungsten concentrates targeted for early February 2019."

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction and Commissioning:

Significant advancements have been seen in both construction and commissioning during the quarter. Construction of the turnkey crush and screen plant was completed in September, with "cold" commissioning completed during October and "hot" commissioning currently ongoing.

 

At the process plant, recruitment and training of plant operators together with significant advancements in plant construction have allowed the commencement of process plant commissioning, in line with previous guidance.

 

Water treatment plant commissioning has been completed and the plant has been handed over to the site team. Dewatering of the historic open pit is in progress (pit dewatering is not required to be completed for a number of months), with 100,750 cubic metres of the historic pit waters (approximately 10% of the total contained historic pit waters) pumped out for treatment and use in the process plant. At the end of November, around 185,000 cubic metres of water was held within the water dams.

 

In addition, mains power has been connected and the site laboratory is operational. Training of key personnel in the process plant has been ongoing, and the first tranche of the main plant workforce recruitment has completed, with around 20 plant operators and maintenance personnel already employed. With construction teams winding down and operating teams being ramped up during this transition phase, total people on site currently number 180, with 39 of these being from the local area.

 

The current commissioning plan sees first production of tungsten from early February 2019, in line with existing guidance.

 

The open pit mining contract has been awarded to one of the largest open pit mining contractors in Spain, with worldwide operations. Mobilisation of their mining equipment to site is ongoing.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have been flat over the period since September, with a current range of US$275-290 per metric tonne unit. Thin trading on the one hand and tight supply on the other appear to be keeping the market in its current range, while it seeks direction against broader financial and commodity market uncertainties. The Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term as Barruecopardo enters production.

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDDXLFFVLFZFBZ
Date   Source Headline
23rd Jun 20117:00 amRNSDrilling Update
20th Jun 20112:01 pmRNSAnnual Financial Report
24th May 20117:00 amRNSFinal Results
16th May 20117:00 amRNSNotification of Interest
12th May 20117:00 amRNSNotification of Interest
11th May 20112:44 pmRNSIssue of Equity
10th May 20117:00 amRNSEnterprise Securities Market Notice
9th May 201112:50 pmRNSNotification of Interest
9th May 20117:00 amRNSEngineering Firm Appointed
4th May 20117:00 amRNSPlacing
14th Apr 20117:00 amRNSBarruecopardo Drilling Results
4th Apr 20117:00 amRNSAcquisition
14th Mar 20117:00 amRNSSalamanca-Zamora Gold Exploration Update
14th Mar 20117:00 amRNSJoint Venture with Ormonde Mining plc
2nd Mar 20117:00 amRNSTungsten Update
13th Jan 20117:00 amRNSTungsten Permitting
13th Dec 20101:06 pmRNSHolding in Company
13th Dec 201010:36 amRNSHolding in Company
10th Dec 20102:34 pmRNSNotification of Interest
11th Nov 20107:00 amRNSTungsten Progress
13th Oct 20107:00 amRNSOrmonde Presentation
11th Oct 20109:53 amRNSHolding(s) in Company
6th Oct 20107:00 amRNSEnterprise Securities Market Notice
5th Oct 20102:09 pmRNSGranting of Options
30th Sep 20107:00 amRNSIssue of Equity
28th Sep 20107:00 amRNSHalf Yearly Report
27th Sep 20104:41 pmRNSSecond Price Monitoring Extn
27th Sep 20104:35 pmRNSPrice Monitoring Extension
16th Sep 20107:00 amRNSScott Wilson Study
9th Sep 20107:00 amRNSLa Zarza Update
7th Sep 20102:56 pmRNSShareholder Notification
27th Aug 201012:02 pmRNSNotification of Major Interest
26th Aug 20103:17 pmRNSNotification of Major Interest
3rd Aug 20107:01 amRNSSalamanca Gold Report
3rd Aug 20107:00 amRNSAppointment of Joint AIM Broker
28th Jul 20107:00 amRNSTungsten Review
19th Jul 201012:01 pmRNSNotification of Major Interest
16th Jul 20101:40 pmRNSEnterprise Securities Market Notice - Replacement
16th Jul 20101:20 pmRNSEnterprise Securities Market Notice
2nd Jul 20107:00 amRNSResignation of Director
30th Jun 20107:00 amRNSIssue of Equity
28th May 20102:56 pmRNSAGM Result
27th May 20107:00 amRNSMajor Tungsten Upgrade
6th May 201010:14 amRNSAnnual Financial Report
27th Apr 20107:00 amRNSFinal Results
12th Apr 20107:00 amRNSTharsis Option Agreement
19th Feb 20107:00 amRNSLa Zarza Update
27th Oct 20097:00 amRNSAntofagasta Joint Venture
28th Sep 20097:00 amRNSInterim Results
22nd Sep 200911:17 amRNSShareholder Notification

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.