14 December 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project: Construction and Commissioning Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

The development schedule has progressed in line with previous guidance of first production of tungsten concentrates from the beginning of February 2019. Key progress includes:

 

· Crush and Screen Plant commissioning nearing completion;

· Process Plant:

o Installation of equipment and supporting structures almost complete;

o Pipework and low voltage electrical installations very advanced;

o Commissioning of some circuits has commenced.

· Water Management System:

o Water treatment plant commissioning complete;

o Dewatering of the historic pit is ongoing with over 100,000 cubic metres pumped from the pit to the water dams (approximately 10% of the historic pit water content).

· Open pit mining contract awarded and mobilisation of mining equipment underway;

· Key operations staff recruited, and first tranche of plant operators recruited and in training;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"With substantial progress made on construction activities during the quarter, the Project has now entered a transition period as construction activities begin to wind down and mine commissioning activities ramp up significantly. It is particularly pleasing to have recently completed the recruitment of the first wave of plant operators, and to see the commencement of process plant commissioning.

 

"I would like to praise the hard work and professionalism of the site team and contractors as they continue to progress the Project through this busy commissioning period. The Project schedule remains in line with previous guidance, with the production of first tungsten concentrates targeted for early February 2019."

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction and Commissioning:

Significant advancements have been seen in both construction and commissioning during the quarter. Construction of the turnkey crush and screen plant was completed in September, with "cold" commissioning completed during October and "hot" commissioning currently ongoing.

 

At the process plant, recruitment and training of plant operators together with significant advancements in plant construction have allowed the commencement of process plant commissioning, in line with previous guidance.

 

Water treatment plant commissioning has been completed and the plant has been handed over to the site team. Dewatering of the historic open pit is in progress (pit dewatering is not required to be completed for a number of months), with 100,750 cubic metres of the historic pit waters (approximately 10% of the total contained historic pit waters) pumped out for treatment and use in the process plant. At the end of November, around 185,000 cubic metres of water was held within the water dams.

 

In addition, mains power has been connected and the site laboratory is operational. Training of key personnel in the process plant has been ongoing, and the first tranche of the main plant workforce recruitment has completed, with around 20 plant operators and maintenance personnel already employed. With construction teams winding down and operating teams being ramped up during this transition phase, total people on site currently number 180, with 39 of these being from the local area.

 

The current commissioning plan sees first production of tungsten from early February 2019, in line with existing guidance.

 

The open pit mining contract has been awarded to one of the largest open pit mining contractors in Spain, with worldwide operations. Mobilisation of their mining equipment to site is ongoing.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have been flat over the period since September, with a current range of US$275-290 per metric tonne unit. Thin trading on the one hand and tight supply on the other appear to be keeping the market in its current range, while it seeks direction against broader financial and commodity market uncertainties. The Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term as Barruecopardo enters production.

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDDXLFFVLFZFBZ
Date   Source Headline
15th Apr 201510:49 amRNSForm 38.5a Ormonde Mining Plc
14th Apr 201510:15 amRNSForm 38.5a Ormonde Mining Plc
13th Apr 20157:00 amRNSBarruecopardo Project Financing Update
31st Mar 201510:16 amRNSForm 38.5a Ormonde Mining Plc
27th Mar 201510:55 amRNSForm 35.8a Ormonde Mining Plc
25th Mar 201510:22 amRNSForm 38.5a Ormonde Mining Plc
24th Mar 201510:30 amRNSForm 38.5a Ormonde Mining Plc
23rd Mar 201510:05 amRNSForm 38.5a Ormonde Mining Plc
20th Mar 201511:27 amRNSForm 38.5a Ormonde Mining Plc
19th Mar 201510:24 amRNSForm 38.5a Ormonde Mining Plc
18th Mar 201511:39 amRNSForm 38.5a Ormonde Mining Plc
16th Mar 20151:57 pmRNSHolding(s) in Company
16th Mar 20151:55 pmRNSHolding(s) in Company
16th Mar 201511:09 amRNSForm 38.5(a) Ormonde Mining Plc
13th Mar 201511:41 amRNSForm 38.5(a) Ormonde Mining Plc
12th Mar 201512:37 pmRNSForm 8.3 - Ormonde Mining plc
12th Mar 201510:42 amBUSForm 38.5 (b) - Ormonde Mining Plc
12th Mar 201510:25 amRNSRule 2.10 Announcement
12th Mar 201510:17 amRNSForm 38.5a Ormonde Mining Plc
11th Mar 201512:21 pmRNSRule 2.10 Announcement
11th Mar 201511:09 amRNSApproach from Almonty Industries
11th Mar 20157:27 amRNSStatement on Approach to Ormonde Mining Plc
2nd Mar 20152:58 pmRNSHolding(s) in Company
18th Feb 20157:00 amRNSBarruecopardo - Financing and Operations Update
16th Jan 20151:33 pmRNSHolding(s) in Company
17th Dec 20145:37 pmRNSHolding(s) in Company
27th Nov 20145:35 pmRNSHolding(s) in Company
26th Nov 20145:03 pmRNSHolding(s) in Company
21st Nov 20147:00 amRNSBarruecopardo - Granting of Mining Concession
6th Oct 20144:35 pmRNSHolding(s) in Company
30th Sep 20145:47 pmRNSHolding(s) in Company
29th Sep 20147:00 amRNSHalf Yearly Report
21st Jul 20147:00 amRNSEnterprise Securities Market Notice
16th Jul 201411:59 amRNSResult of AGM
15th Jul 20147:00 amRNSBarruecopardo Permitting Update
20th Jun 20142:41 pmRNSAnnual Financial Report
11th Jun 20147:00 amRNSFinal Results 2013
8th May 20142:03 pmRNSHolding(s) in Company
8th May 20142:01 pmRNSHolding(s) in Company
6th May 20147:01 amRNSEnterprise Securities Market Notice
2nd May 201410:46 amRNSResult of EGM
29th Apr 20147:00 amRNSBarruecopardo Update
15th Apr 20145:44 pmRNSHolding(s) in Company
11th Apr 20147:00 amRNSEnterprise Securities Market Notice
8th Apr 20145:28 pmRNSNotice of EGM
4th Apr 20142:00 pmRNSPlacing Raising
24th Mar 20147:00 amRNSOfftake Agreement
3rd Mar 20147:00 amRNSFairport Engineering Appointment
11th Feb 20145:54 pmRNSHolding(s) in Company
3rd Feb 20147:00 amRNSBarruecopardo Permitting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.