Barruecopardo Tungsten Project Update

14 Dec 2018 07:00

RNS Number : 4551K
Ormonde Mining PLC
14 December 2018
 

14 December 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project: Construction and Commissioning Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

The development schedule has progressed in line with previous guidance of first production of tungsten concentrates from the beginning of February 2019. Key progress includes:

 

· Crush and Screen Plant commissioning nearing completion;

· Process Plant:

o Installation of equipment and supporting structures almost complete;

o Pipework and low voltage electrical installations very advanced;

o Commissioning of some circuits has commenced.

· Water Management System:

o Water treatment plant commissioning complete;

o Dewatering of the historic pit is ongoing with over 100,000 cubic metres pumped from the pit to the water dams (approximately 10% of the historic pit water content).

· Open pit mining contract awarded and mobilisation of mining equipment underway;

· Key operations staff recruited, and first tranche of plant operators recruited and in training;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"With substantial progress made on construction activities during the quarter, the Project has now entered a transition period as construction activities begin to wind down and mine commissioning activities ramp up significantly. It is particularly pleasing to have recently completed the recruitment of the first wave of plant operators, and to see the commencement of process plant commissioning.

 

"I would like to praise the hard work and professionalism of the site team and contractors as they continue to progress the Project through this busy commissioning period. The Project schedule remains in line with previous guidance, with the production of first tungsten concentrates targeted for early February 2019."

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction and Commissioning:

Significant advancements have been seen in both construction and commissioning during the quarter. Construction of the turnkey crush and screen plant was completed in September, with "cold" commissioning completed during October and "hot" commissioning currently ongoing.

 

At the process plant, recruitment and training of plant operators together with significant advancements in plant construction have allowed the commencement of process plant commissioning, in line with previous guidance.

 

Water treatment plant commissioning has been completed and the plant has been handed over to the site team. Dewatering of the historic open pit is in progress (pit dewatering is not required to be completed for a number of months), with 100,750 cubic metres of the historic pit waters (approximately 10% of the total contained historic pit waters) pumped out for treatment and use in the process plant. At the end of November, around 185,000 cubic metres of water was held within the water dams.

 

In addition, mains power has been connected and the site laboratory is operational. Training of key personnel in the process plant has been ongoing, and the first tranche of the main plant workforce recruitment has completed, with around 20 plant operators and maintenance personnel already employed. With construction teams winding down and operating teams being ramped up during this transition phase, total people on site currently number 180, with 39 of these being from the local area.

 

The current commissioning plan sees first production of tungsten from early February 2019, in line with existing guidance.

 

The open pit mining contract has been awarded to one of the largest open pit mining contractors in Spain, with worldwide operations. Mobilisation of their mining equipment to site is ongoing.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have been flat over the period since September, with a current range of US$275-290 per metric tonne unit. Thin trading on the one hand and tight supply on the other appear to be keeping the market in its current range, while it seeks direction against broader financial and commodity market uncertainties. The Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term as Barruecopardo enters production.

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDDXLFFVLFZFBZ
Date   Source Headline
31st Jan 20143:27 pmRNSAlmonty Ind. - Financing & No Offer for Ormonde
31st Jan 20142:45 pmRNSResponse to Announcement
29th Jan 201411:00 amRNSAppointment of Bond Advisors
29th Jan 20149:39 amRNSForm 38.5 Ormonde Mining Plc
27th Jan 201410:35 amRNSForm 38.5 Ormonde Mining Plc
24th Jan 201410:57 amRNSForm 38.5 Ormonde Mining Plc
23rd Jan 20149:58 amRNSForm 38.5 Ormonde Mining Plc
22nd Jan 201411:58 amRNSForm 38.5 Ormonde Mining Plc
21st Jan 201411:13 amRNSForm 38.5 Ormonde Mining Plc
20th Jan 20143:08 pmRNSForm 38.5 Ormonde Mining Plc
16th Jan 201410:36 amRNSForm 38.5 Ormonde Mining Plc
14th Jan 20149:51 amRNSForm 38.5 Ormonde Mining Plc
13th Jan 201410:44 amRNSForm 38.5 Ormonde Mining Plc
10th Jan 201410:54 amRNSForm 38.5 Ormonde Mining Plc
8th Jan 20147:00 amRNSBarruecopardo Permitting Update
7th Jan 20149:38 amRNSForm 38.5 Ormonde Mining Plc
6th Jan 201412:37 pmRNSForm 38.5 Ormonde Mining Plc
3rd Jan 201412:06 pmRNSForm 38.5 Ormonde Mining Plc
24th Dec 20139:41 amRNSForm 38.5 Ormonde Mining Plc
23rd Dec 20139:25 amRNSForm 38.5 Ormonde Mining Plc
20th Dec 201310:13 amRNSForm 38.5 Ormonde Mining Plc
19th Dec 201310:21 amRNSForm 38.5 Ormonde Mining Plc
18th Dec 201311:07 amRNSOrmonde welcomes Irish Takeover Panel Statement
13th Dec 201311:03 amRNSForm 38.5 Ormonde Mining Plc
11th Dec 201310:00 amRNSForm 38.5 Ormonde Mining Plc
10th Dec 201310:23 amRNSForm 38.5 Ormonde Mining
9th Dec 201312:32 pmRNSForm 38.5 Ormonde Mining Plc
5th Dec 20139:49 amRNSForm 38.5 Ormonde Mining
4th Dec 20139:51 amRNSForm 38.5 Ormonde Mining Plc
29th Nov 201310:10 amRNSForm 38.5 Ormonde Mining Plc
28th Nov 201310:06 amRNSForm 38.5 Ormonde Mining Plc
27th Nov 20138:43 amRNSForm 38.5 Ormonde Mining Plc
26th Nov 20138:29 amRNSForm 38.5 Ormonde Mining Plc
25th Nov 20138:14 amRNSForm 38.5 Ormonde Mining Plc
22nd Nov 201312:12 pmRNSForm 38.5 Ormode Mining Plc
21st Nov 201311:31 amRNSForm 38.5 Ormonde Mining Plc
20th Nov 201311:13 amRNSForm 38.5 Ormonde Mining Plc
19th Nov 201310:30 amRNSForm 38.5 Ormonde Mining Plc
18th Nov 201310:08 amRNSForm 38.5 Ormonde Mining Plc
15th Nov 201310:32 amRNSForm 38.5 Ormonde Mining Plc
14th Nov 20133:23 pmRNSForm 8.3 - Ormonde Mining plc
14th Nov 201310:06 amRNSForm 38.5 Ormonde Mining Plc
13th Nov 20133:27 pmRNSForm 8.3 - Ormonde Mining plc
13th Nov 201310:18 amRNSForm 38.5 Ormonde Mining Plc
12th Nov 20131:18 pmRNSForm 8.3 - Ormonde Mining plc
11th Nov 20133:00 pmRNSForm 8.3 - Ormonde Mining plc
8th Nov 20133:17 pmRNSForm 8.3 - Ormonde Mining plc
6th Nov 20133:19 pmRNSForm 8.3 - Ormonde Mining plc
6th Nov 20139:47 amRNSForm 38.5 Ormonde Mining Plc
4th Nov 20132:57 pmRNSForm 8.3 - Ormonde Mining plc

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.