Watch the latest episode of focusIR Fireside Chats: Why Edinburgh Investment Trust Is Backing Turnaround Stocks for 2026 Growth. View here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksORM.L Regulatory News (ORM)

  • There is currently no data for ORM

Barruecopardo Tungsten Project Update

14 Dec 2018 07:00

RNS Number : 4551K
Ormonde Mining PLC
14 December 2018
 

14 December 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project: Construction and Commissioning Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

The development schedule has progressed in line with previous guidance of first production of tungsten concentrates from the beginning of February 2019. Key progress includes:

 

· Crush and Screen Plant commissioning nearing completion;

· Process Plant:

o Installation of equipment and supporting structures almost complete;

o Pipework and low voltage electrical installations very advanced;

o Commissioning of some circuits has commenced.

· Water Management System:

o Water treatment plant commissioning complete;

o Dewatering of the historic pit is ongoing with over 100,000 cubic metres pumped from the pit to the water dams (approximately 10% of the historic pit water content).

· Open pit mining contract awarded and mobilisation of mining equipment underway;

· Key operations staff recruited, and first tranche of plant operators recruited and in training;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"With substantial progress made on construction activities during the quarter, the Project has now entered a transition period as construction activities begin to wind down and mine commissioning activities ramp up significantly. It is particularly pleasing to have recently completed the recruitment of the first wave of plant operators, and to see the commencement of process plant commissioning.

 

"I would like to praise the hard work and professionalism of the site team and contractors as they continue to progress the Project through this busy commissioning period. The Project schedule remains in line with previous guidance, with the production of first tungsten concentrates targeted for early February 2019."

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction and Commissioning:

Significant advancements have been seen in both construction and commissioning during the quarter. Construction of the turnkey crush and screen plant was completed in September, with "cold" commissioning completed during October and "hot" commissioning currently ongoing.

 

At the process plant, recruitment and training of plant operators together with significant advancements in plant construction have allowed the commencement of process plant commissioning, in line with previous guidance.

 

Water treatment plant commissioning has been completed and the plant has been handed over to the site team. Dewatering of the historic open pit is in progress (pit dewatering is not required to be completed for a number of months), with 100,750 cubic metres of the historic pit waters (approximately 10% of the total contained historic pit waters) pumped out for treatment and use in the process plant. At the end of November, around 185,000 cubic metres of water was held within the water dams.

 

In addition, mains power has been connected and the site laboratory is operational. Training of key personnel in the process plant has been ongoing, and the first tranche of the main plant workforce recruitment has completed, with around 20 plant operators and maintenance personnel already employed. With construction teams winding down and operating teams being ramped up during this transition phase, total people on site currently number 180, with 39 of these being from the local area.

 

The current commissioning plan sees first production of tungsten from early February 2019, in line with existing guidance.

 

The open pit mining contract has been awarded to one of the largest open pit mining contractors in Spain, with worldwide operations. Mobilisation of their mining equipment to site is ongoing.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have been flat over the period since September, with a current range of US$275-290 per metric tonne unit. Thin trading on the one hand and tight supply on the other appear to be keeping the market in its current range, while it seeks direction against broader financial and commodity market uncertainties. The Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term as Barruecopardo enters production.

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDDXLFFVLFZFBZ
Date   Source Headline
20th Aug 20091:01 pmRNSAGM Result
20th Jul 20093:09 pmRNSIssue of Equity
13th Jul 20097:00 amRNSLa Zarza Exploration Deal
30th Jun 200910:33 amRNSAnnual Report and Accounts
26th May 20097:00 amRNSPreliminary Results 2008
6th May 20092:01 pmRNSShareholder Notification
21st Apr 20097:00 amRNSTungsten Testwork
12th Jan 20097:00 amRNSDrilling Report
28th Oct 20087:00 amRNSDrilling Report
6th Oct 20087:00 amRNSDrilling Report
23rd Sep 20085:32 pmRNSShareholder Notification
22nd Sep 20087:00 amRNSInterim Results
22nd Jul 20087:00 amRNSIEX Notice
21st Jul 20085:16 pmRNSShareholder Notification
15th Jul 200811:15 amRNSIssue of Equity
17th Jun 20087:00 amRNSDrilling Report
12th Jun 20081:03 pmRNSResult of AGM
12th Jun 20087:00 amRNSOperational Update
13th May 20086:00 amRNSFinal Results
16th Apr 20087:00 amRNSBoard Appointment
1st Apr 20087:00 amRNSDrilling Report
26th Feb 20087:00 amRNSDrilling Update
6th Feb 20087:01 amRNSLa Zarza Feasibility Study
24th Jan 20087:01 amRNSTungsten Resource Update
10th Jan 20087:00 amRNSIEX Notice
4th Jan 20085:16 pmRNSAdditional Listing
6th Dec 20077:00 amRNSDrilling Report
5th Dec 20074:00 pmRNSDirectorate Change
4th Dec 20074:10 pmRNSHolding in Company
30th Nov 200712:30 pmRNSHolding in Company
30th Nov 20077:00 amRNSIEX Notice
28th Nov 20072:29 pmRNSHolding in Company
27th Nov 20077:00 amRNSEquity Fundraising
13th Nov 20077:01 amRNSTungsten Update
8th Nov 20077:01 amRNSDrilling Update
1st Nov 20077:01 amRNSDrilling Report
28th Sep 20074:27 pmRNSBrochure of Particulars
27th Sep 20077:02 amRNSTungsten Drilling Results
24th Sep 20077:01 amRNSInterim Results
17th Aug 20072:26 pmRNSAIM Rule 26
7th Aug 20077:01 amRNSDrilling Report
30th Jul 200710:20 amRNSHolding in Company
26th Jul 20073:25 pmRNSResults of AGM
17th Jul 200710:28 amRNSPlacing
12th Jul 20077:00 amRNSLa Zarza Update
26th Jun 20073:12 pmRNSDocument Availability
6th Jun 20077:00 amRNSIEX Notice
30th May 20075:38 pmRNSAdditional Listing
16th May 20077:01 amRNSPreliminary Results
15th May 20074:16 pmRNSHolding in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.