Watch the latest episode of focusIR Fireside Chats: Why Edinburgh Investment Trust Is Backing Turnaround Stocks for 2026 Growth. View here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksORM.L Regulatory News (ORM)

  • There is currently no data for ORM

Barruecopardo Tungsten Project Update

14 Dec 2018 07:00

RNS Number : 4551K
Ormonde Mining PLC
14 December 2018
 

14 December 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project: Construction and Commissioning Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

The development schedule has progressed in line with previous guidance of first production of tungsten concentrates from the beginning of February 2019. Key progress includes:

 

· Crush and Screen Plant commissioning nearing completion;

· Process Plant:

o Installation of equipment and supporting structures almost complete;

o Pipework and low voltage electrical installations very advanced;

o Commissioning of some circuits has commenced.

· Water Management System:

o Water treatment plant commissioning complete;

o Dewatering of the historic pit is ongoing with over 100,000 cubic metres pumped from the pit to the water dams (approximately 10% of the historic pit water content).

· Open pit mining contract awarded and mobilisation of mining equipment underway;

· Key operations staff recruited, and first tranche of plant operators recruited and in training;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"With substantial progress made on construction activities during the quarter, the Project has now entered a transition period as construction activities begin to wind down and mine commissioning activities ramp up significantly. It is particularly pleasing to have recently completed the recruitment of the first wave of plant operators, and to see the commencement of process plant commissioning.

 

"I would like to praise the hard work and professionalism of the site team and contractors as they continue to progress the Project through this busy commissioning period. The Project schedule remains in line with previous guidance, with the production of first tungsten concentrates targeted for early February 2019."

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction and Commissioning:

Significant advancements have been seen in both construction and commissioning during the quarter. Construction of the turnkey crush and screen plant was completed in September, with "cold" commissioning completed during October and "hot" commissioning currently ongoing.

 

At the process plant, recruitment and training of plant operators together with significant advancements in plant construction have allowed the commencement of process plant commissioning, in line with previous guidance.

 

Water treatment plant commissioning has been completed and the plant has been handed over to the site team. Dewatering of the historic open pit is in progress (pit dewatering is not required to be completed for a number of months), with 100,750 cubic metres of the historic pit waters (approximately 10% of the total contained historic pit waters) pumped out for treatment and use in the process plant. At the end of November, around 185,000 cubic metres of water was held within the water dams.

 

In addition, mains power has been connected and the site laboratory is operational. Training of key personnel in the process plant has been ongoing, and the first tranche of the main plant workforce recruitment has completed, with around 20 plant operators and maintenance personnel already employed. With construction teams winding down and operating teams being ramped up during this transition phase, total people on site currently number 180, with 39 of these being from the local area.

 

The current commissioning plan sees first production of tungsten from early February 2019, in line with existing guidance.

 

The open pit mining contract has been awarded to one of the largest open pit mining contractors in Spain, with worldwide operations. Mobilisation of their mining equipment to site is ongoing.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have been flat over the period since September, with a current range of US$275-290 per metric tonne unit. Thin trading on the one hand and tight supply on the other appear to be keeping the market in its current range, while it seeks direction against broader financial and commodity market uncertainties. The Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term as Barruecopardo enters production.

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDDXLFFVLFZFBZ
Date   Source Headline
10th May 20077:01 amRNSSalamanca Drilling Update
28th Feb 20077:01 amRNSSalamanca Drilling Results
19th Feb 20077:01 amRNSLa Zarza drilling results
30th Jan 20077:01 amRNSLa Zarza Project Update
26th Jan 200712:41 pmRNSHolding in Company
23rd Jan 20077:01 amRNSSalamanca Tungsten Update
11th Jan 200711:42 amRNSDirectorate Change
9th Jan 20077:01 amRNSTungsten Update
5th Jan 200711:38 amRNSHolding in Company
20th Nov 20067:01 amRNSDrilling Update
27th Oct 20064:20 pmRNSGrant of Options
23rd Oct 20064:03 pmRNSHolding in Company
18th Oct 20065:29 pmRNSIEX Notice
13th Oct 200611:29 amRNSHolding in Company
9th Oct 20062:40 pmRNSBrochure of Particulars
9th Oct 20067:00 amRNSTungsten Project Update
28th Sep 20067:54 amRNSInterim Results
26th Sep 20067:01 amRNSDrilling Update
4th Sep 20067:01 amRNSLa Zarza Copper-Gold Project
1st Sep 20065:03 pmRNSHolding in Company
1st Sep 20064:50 pmRNSHolding in Company
15th Aug 200612:46 pmRNSInterest in Share Capital
9th Aug 20065:24 pmRNSAdditional Listing
16th Jun 20065:07 pmRNSHolding in Company
16th Jun 200612:58 pmRNSResult of AGM and EGM
25th May 20068:41 amRNSDocument Availability
24th May 20064:38 pmRNSHolding in Company
12th May 20064:00 pmRNSPlacing Raising StgGBP3.04 m
8th May 200612:12 pmRNSHolding in Company
8th May 20067:01 amRNSPreliminary Results
2nd May 20067:01 amRNSSalamanca Update
24th Apr 20067:01 amRNSResource Update
28th Feb 20067:02 amRNSTungsten Project Option
16th Feb 20067:01 amRNSDrilling Report
26th Jan 20067:01 amRNSSalamanca Gold Project Update
16th Jan 20067:00 amRNSDrilling Results and Update
6th Jan 20064:02 pmRNSHolding in Company
9th Dec 20054:42 pmRNSRe: Holding in Company
8th Dec 20057:00 amRNSAwards Granted
14th Nov 20057:01 amRNSLa Zarza Testwork Update
12th Oct 20057:00 amRNSDirectorate Change
26th Sep 20057:01 amRNSInterim Results
1st Sep 20057:00 amRNSDirectorate Change
15th Aug 20057:30 amRNSDrilling Report
13th Jul 20057:30 amRNSDrilling Report
27th Jun 20051:36 pmRNSIEX Notice
23rd Jun 20051:05 pmRNSAdditional Listing
2nd Jun 20057:01 amRNSDrilling Update
27th May 200511:46 amRNSDirectorate Change
10th May 20059:30 amRNSDrilling Report-Replacement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.