Mbeya Power Project MOU and PPA Update

18 Dec 2017 07:00

RNS Number : 6086Z
Kibo Mining Plc
18 December 2017
 

Kibo Mining Plc (Incorporated in Ireland) (Registration Number: 451931)

(External registration number: 2011/007371/10) Share code on the JSE Limited: KBO

Share code on the AIM: KIBO ISIN: IE00B97C0C31

('Kibo' or 'the Company')

 

Dated: 18 December 2017

 

Kibo Mining Plc ('Kibo' or the 'Company')

Mbeya Coal to Power Project MOU and PPA Update

 

Kibo Mining Plc (AIM:KIBO; AltX:KBO), the multi-asset African focused energy and resource company, is pleased to announce that the newly formed Tanzania Ministry for Energy ('The Ministry') has committed to an indicative timeline for the completion of the MOU for the fast-tracking of the Mbeya Coal to Power Project ('MCPP').

 

Overview

· Positive briefing between Kibo, General Electric ('GE'), the Tanzania Electric Supply Company ('TANESCO') and the Deputy Minister for Energy ('The Deputy Minister') on 14 December 2017 and subsequent follow-up meeting between Kibo and the Deputy Minister

· Discussed strategic importance of the MCPP within the successful and expeditious execution of the Tanzanian energy strategy and establishing targeted deliverables towards its implementation

· MCPP viewed as the most advanced Independent Power Producer ('IPP') coal power project in the Tanzanian generation projects pipeline and expected to make a significant contribution towards achieving the 2020 targets and beyond, through further development of MCPP Phases II and III

· Full support for the MCPP: focus on signing MOU with TANESCO within the next 10 to 12 working days; and agreeing a final Power Purchase Agreement ('PPA') during Q1 2018

· Confirmation that priority generation projects are being fast-tracked as the Tanzanian Government targets the delivery of 5GW installed generation capacity by 2020, with a further 7GW to be added in the following five years (EWURA, 2016, p 47)1

 

Kibo's CEO, Louis Coetzee, said: "Our focus on positioning Kibo as a strategic regional electricity supplier gained further momentum as we continue to strengthen our relationships with TANESCO, the Ministry of Energy, and General Electric for assisting in the structure and implementation of the country's new energy policy and the resultant fast-tracking and development of the MCPP. We were delighted with the commitment to sign a MOU within 10 to 12 working days and the prospect to finalize the PPA in Q1 2018, which will allow us to materially advance the project level financing talks we have been conducting. I understand that there has been frustration with the delays we have been experiencing, however we believe these latest very positive outcomes reiterate the strong commitment from all the MCPP stakeholders to see the MCPP come to fruition in the shortest possible time, given the complex procedural and bureaucratic environment of the current development phase of the MCPP."

 

Over the course of the past three months a series of meetings have been held with the Ministry for Energy in Dar es Salaam between representatives of Kibo, TANESCO, the Minister for Energy and the Deputy Minister to discuss the progress made with regard to previously agreed milestones and deliverables towards the completion of the MCPP. The latest meeting, held on 14 December 2017, also had General Electric ('GE'), one of Kibo's strategic partners, in attendance and confirmed the Ministry's strategy to fast-track all priority generation projects as it focused on delivering 5GW installed generation capacity by 2020, with a further 7GW to be added in the following five years. The bulk of the first 5GW is to be developed as base load capacity, with coal fired power forming the backbone of all base load power facilities.

 

Accordingly, the Ministry confirmed the strategic importance of the MCPP in the successful and expeditious execution of its energy strategy. The MCPP is considered as one of the most advanced IPP coal power projects in the Tanzanian generation projects pipeline and it is expected to make a significant contribution towards achieving the 2020 target and beyond, through further development of MCPP Phases II and III.

 

To take advantage of the current favourable funding window of opportunity created by Kibo through the use of innovative strategic partnerships, the Ministry reiterated its full support for the MCPP and acknowledged the urgency to complete the PPA process for the MCPP in the shortest possible time. To this end, and following the recent approval of the MOU by the Board of TANESCO, the Ministry provided a firm undertaking to complete the remaining administrative process and signing of the MOU within the next 10 to 12 working days. The Ministry also confirmed its intention to fast-track the PPA negotiations and agree a final PPA during Q1 2018.

 

**ENDS**

 

For further information please visit www.kibomining.com or contact:

 

Louis Coetzee

louisc@kibomining.com

Kibo Mining Plc

Chief Executive Officer

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate Adviser and Designated Adviser on JSE

Jon Belliss

+44 (0) 207 382 8300

 

Beaufort Securities Limited

Broker

Andrew Thomson

+61 8 9480 2500

RFC Ambrian Limited

NOMAD on AIM

Isabel de Salis / Priit Piip

+44 (0) 207 236 1177

St Brides Partners Ltd

Investor and Media Relations Adviser

 

This announcement contains inside information as stipulated under the Market Abuse Regulations

(EU) no. 596/2014 ("MAR").

 

Notes to editors:

 

The Mbeya Coal to Power Project ('MCPP'), comprises the development of the Mbeya Coal Mine, a 1.5Mt p/a mining operation and the Mbeya Power Plant, a 300 MW mine-mouth thermal power station.

 

The Mbeya Coal Mine has a defined 120.8 Mt NI 43 101 thermal coal resource. A Definitive Feasibility Study has been conducted on the project which underpins its value with an indicated IRR of 69.2%. The 300 MW mouth-of-mine thermal power station has long term scalability to 1000MW, with a full Power Feasibility Study that has been completed, highlighting an annual power output target of 1,8 GW based on annual average coal consumption of 1.5 Mt. An Integrated Bankable Feasibility Study report for the entire project indicated total potential revenues of US$ 7.5-8.5 billion over an initial 25-year mine life, post tax equity IRR between 21-22%, debt pay-back period of 11-12 years and a construction period of 36 months.

 

To assist in the execution this critical power project of the MCPP, Kibo has assembled a team of international team of advisors and partners including Engineering Procurement and Construction ('EPC') contractors and financial teams that are assisting in the development of. These include ABSA/Barclays as Financial Advisor, China based EPC contractor SEPCO III, General Electric, Tractebel Engineering (Power), Minxcon Consulting (Mining) and legal advisors Norton Rose Fulbright.

 

Johannesburg

18 December 2017

Corporate and Designated Adviser

River Group

 


1 EWURA (2016) POWER SYSTEM MASTER PLAN 2016 UPDATE. Dar Es Salaam. Available at: http://www.ewura.go.tz/wp-content/uploads/2017/01/Power-System-Master-Plan-Dec.-2016.pdf.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDFFUSMAFWSEEE
Date   Source Headline
10th Nov 20148:00 amRNSCommencement of Accelerated PFS for RCPP
28th Oct 20148:00 amRNSRukwa DMFS Project Update
14th Oct 20148:00 amRNSCommencement of DFS on Imweru
10th Oct 20148:11 amRNSClarification re CEO shareholding
9th Oct 20147:00 amRNSFirst Financial Indicators for RCPP
8th Oct 20149:15 amRNSKibo Mining raises £855,725 in Share Placing
29th Sep 20148:00 amRNSRCPP Update
25th Sep 20144:00 pmRNSInterim Results
18th Sep 20148:00 amRNSRCPP Update
9th Sep 20148:00 amRNSPreliminary Evaluation confirms Mining Viability
2nd Sep 20148:30 amRNSImweru Exploration Results
21st Aug 20148:31 amRNSProgress with DFS at RCPP
31st Jul 20148:00 amRNSResult of AGM & Completion of Placing
29th Jul 20148:00 amRNSRCPP to commence DMFS
15th Jul 20144:40 pmRNSSecond Price Monitoring Extn
15th Jul 20144:35 pmRNSPrice Monitoring Extension
14th Jul 20148:30 amRNSKibo Mining Plc Share Placing
7th Jul 20149:17 amRNSPosting of 2013 Annual Report
30th Jun 20143:56 pmRNSAnnual Financial Statements & Notice of AGM
27th Jun 201412:40 pmRNSFinal Results
27th May 20149:00 amRNS1st Quarter Results
2nd Apr 20141:00 pmRNSUK Investor Show & Registered Company Address
31st Mar 20149:00 amRNSKibo Mining raises £750,000 in Share Placing
17th Mar 20148:00 amRNSTechnical Report - Haneti
24th Feb 20148:00 amRNSTechnical Report Confirms Imweru Upside Potential
14th Feb 20149:30 amRNSAppointment of Director
23rd Jan 20149:00 amRNSShareholder Update: Financial Year 2013/14
14th Jan 20147:00 amRNSPositive Phase 1 Drilling Results From Imweru
20th Dec 20137:00 amRNSDistribution of Shareholding by Major Shareholder
19th Dec 20137:00 amRNSHaneti Nickel and Imweru Gold Projects Update
13th Dec 20137:30 amRNSHaneti Exploration Project Update
5th Dec 20133:48 pmRNSKibo Re-acquires 100% interest in Haneti
4th Dec 20137:30 amRNSIMWERU GOLD PROJECT COMPLETED AHEAD OF SCHEDULE
19th Nov 20137:30 amRNSUpdate on Exploration Activities
28th Oct 20137:30 amRNSKibo Commences 3,000 metre Drill Programme
8th Oct 20137:00 amRNSManagement Team and Financial Advisor Appointed
1st Oct 20137:00 amRNSKibo Issues of Shares for Cash
30th Sep 20139:45 amRNSHalf Year Results Announcement
16th Sep 20137:00 amRNSRecent Encouraging Stream Sampling Results
11th Sep 20137:00 amRNSRaises further £500,000 in Secondary Placement
9th Sep 20137:30 amRNSHaneti Joint Venture Project Update
30th Aug 201310:52 amRNSKibo raises £1,105,000 in Share Placing
13th Aug 20137:30 amRNSKibo Announces new Consolidated Lake Victoria Gold
1st Aug 20137:00 amRNSChange in UK Broking Arrangements
31st Jul 20134:45 pmRNSRESULTS OF THE ANNUAL GENERAL MEETING
31st Jul 20137:00 amRNSHaneti Project Interim Update
18th Jul 20137:00 amRNSMOU Signed with Korean East West Power
11th Jul 20137:00 amRNSHaneti Interim Project Update
8th Jul 201310:00 amRNSAnnual Report, AGM Date and Director Resignations
1st Jul 20137:00 amRNS15 months results for the period ended 31 Dec 2012

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.