Mbeya Power Project MOU and PPA Update

18 Dec 2017 07:00

RNS Number : 6086Z
Kibo Mining Plc
18 December 2017
 

Kibo Mining Plc (Incorporated in Ireland) (Registration Number: 451931)

(External registration number: 2011/007371/10) Share code on the JSE Limited: KBO

Share code on the AIM: KIBO ISIN: IE00B97C0C31

('Kibo' or 'the Company')

 

Dated: 18 December 2017

 

Kibo Mining Plc ('Kibo' or the 'Company')

Mbeya Coal to Power Project MOU and PPA Update

 

Kibo Mining Plc (AIM:KIBO; AltX:KBO), the multi-asset African focused energy and resource company, is pleased to announce that the newly formed Tanzania Ministry for Energy ('The Ministry') has committed to an indicative timeline for the completion of the MOU for the fast-tracking of the Mbeya Coal to Power Project ('MCPP').

 

Overview

· Positive briefing between Kibo, General Electric ('GE'), the Tanzania Electric Supply Company ('TANESCO') and the Deputy Minister for Energy ('The Deputy Minister') on 14 December 2017 and subsequent follow-up meeting between Kibo and the Deputy Minister

· Discussed strategic importance of the MCPP within the successful and expeditious execution of the Tanzanian energy strategy and establishing targeted deliverables towards its implementation

· MCPP viewed as the most advanced Independent Power Producer ('IPP') coal power project in the Tanzanian generation projects pipeline and expected to make a significant contribution towards achieving the 2020 targets and beyond, through further development of MCPP Phases II and III

· Full support for the MCPP: focus on signing MOU with TANESCO within the next 10 to 12 working days; and agreeing a final Power Purchase Agreement ('PPA') during Q1 2018

· Confirmation that priority generation projects are being fast-tracked as the Tanzanian Government targets the delivery of 5GW installed generation capacity by 2020, with a further 7GW to be added in the following five years (EWURA, 2016, p 47)1

 

Kibo's CEO, Louis Coetzee, said: "Our focus on positioning Kibo as a strategic regional electricity supplier gained further momentum as we continue to strengthen our relationships with TANESCO, the Ministry of Energy, and General Electric for assisting in the structure and implementation of the country's new energy policy and the resultant fast-tracking and development of the MCPP. We were delighted with the commitment to sign a MOU within 10 to 12 working days and the prospect to finalize the PPA in Q1 2018, which will allow us to materially advance the project level financing talks we have been conducting. I understand that there has been frustration with the delays we have been experiencing, however we believe these latest very positive outcomes reiterate the strong commitment from all the MCPP stakeholders to see the MCPP come to fruition in the shortest possible time, given the complex procedural and bureaucratic environment of the current development phase of the MCPP."

 

Over the course of the past three months a series of meetings have been held with the Ministry for Energy in Dar es Salaam between representatives of Kibo, TANESCO, the Minister for Energy and the Deputy Minister to discuss the progress made with regard to previously agreed milestones and deliverables towards the completion of the MCPP. The latest meeting, held on 14 December 2017, also had General Electric ('GE'), one of Kibo's strategic partners, in attendance and confirmed the Ministry's strategy to fast-track all priority generation projects as it focused on delivering 5GW installed generation capacity by 2020, with a further 7GW to be added in the following five years. The bulk of the first 5GW is to be developed as base load capacity, with coal fired power forming the backbone of all base load power facilities.

 

Accordingly, the Ministry confirmed the strategic importance of the MCPP in the successful and expeditious execution of its energy strategy. The MCPP is considered as one of the most advanced IPP coal power projects in the Tanzanian generation projects pipeline and it is expected to make a significant contribution towards achieving the 2020 target and beyond, through further development of MCPP Phases II and III.

 

To take advantage of the current favourable funding window of opportunity created by Kibo through the use of innovative strategic partnerships, the Ministry reiterated its full support for the MCPP and acknowledged the urgency to complete the PPA process for the MCPP in the shortest possible time. To this end, and following the recent approval of the MOU by the Board of TANESCO, the Ministry provided a firm undertaking to complete the remaining administrative process and signing of the MOU within the next 10 to 12 working days. The Ministry also confirmed its intention to fast-track the PPA negotiations and agree a final PPA during Q1 2018.

 

**ENDS**

 

For further information please visit www.kibomining.com or contact:

 

Louis Coetzee

louisc@kibomining.com

Kibo Mining Plc

Chief Executive Officer

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate Adviser and Designated Adviser on JSE

Jon Belliss

+44 (0) 207 382 8300

 

Beaufort Securities Limited

Broker

Andrew Thomson

+61 8 9480 2500

RFC Ambrian Limited

NOMAD on AIM

Isabel de Salis / Priit Piip

+44 (0) 207 236 1177

St Brides Partners Ltd

Investor and Media Relations Adviser

 

This announcement contains inside information as stipulated under the Market Abuse Regulations

(EU) no. 596/2014 ("MAR").

 

Notes to editors:

 

The Mbeya Coal to Power Project ('MCPP'), comprises the development of the Mbeya Coal Mine, a 1.5Mt p/a mining operation and the Mbeya Power Plant, a 300 MW mine-mouth thermal power station.

 

The Mbeya Coal Mine has a defined 120.8 Mt NI 43 101 thermal coal resource. A Definitive Feasibility Study has been conducted on the project which underpins its value with an indicated IRR of 69.2%. The 300 MW mouth-of-mine thermal power station has long term scalability to 1000MW, with a full Power Feasibility Study that has been completed, highlighting an annual power output target of 1,8 GW based on annual average coal consumption of 1.5 Mt. An Integrated Bankable Feasibility Study report for the entire project indicated total potential revenues of US$ 7.5-8.5 billion over an initial 25-year mine life, post tax equity IRR between 21-22%, debt pay-back period of 11-12 years and a construction period of 36 months.

 

To assist in the execution this critical power project of the MCPP, Kibo has assembled a team of international team of advisors and partners including Engineering Procurement and Construction ('EPC') contractors and financial teams that are assisting in the development of. These include ABSA/Barclays as Financial Advisor, China based EPC contractor SEPCO III, General Electric, Tractebel Engineering (Power), Minxcon Consulting (Mining) and legal advisors Norton Rose Fulbright.

 

Johannesburg

18 December 2017

Corporate and Designated Adviser

River Group

 


1 EWURA (2016) POWER SYSTEM MASTER PLAN 2016 UPDATE. Dar Es Salaam. Available at: http://www.ewura.go.tz/wp-content/uploads/2017/01/Power-System-Master-Plan-Dec.-2016.pdf.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDFFUSMAFWSEEE
Date   Source Headline
23rd Dec 20257:00 amRNSUpdate on Acquisition of Carbon Resilience Pte Ltd
23rd Dec 20257:00 amRNSUpdate on Acquisition of Carbon Resilience Pte Ltd
24th Oct 20254:04 pmRNSHolding(s) in Company
16th Oct 20252:00 pmRNSReceipt of First Tranche of Convertible Loan Note
8th Oct 20251:07 pmRNSReplacement: Conditional Acqn of Carbon Resilience
8th Oct 20257:30 amRNSCarbon Resilience Acquisition , CLN & AFS Update
8th Oct 20257:26 amRNSConditional Acquisition of Carbon Resilience Pte
2nd May 20257:00 amRNS2024 Audited Accounts Publication Date
14th Apr 20257:30 amRNSSuspension - Kibo Energy Plc
14th Apr 20257:00 amRNSProject Acquisition Update
7th Mar 20257:00 amRNSHolding(s) in Company
7th Jan 20253:46 pmRNSApplication for Admission of Shares to AIM & TVR
24th Dec 20247:30 amRNSRestoration - Kibo Energy plc
24th Dec 20247:00 amRNSUnaudited Interim Results - 30 June 2024
23rd Dec 20243:25 pmRNS-RDematerialisation of Shares
23rd Dec 202412:00 pmRNSResults for the Year Ended 31 December 2023
3rd Dec 20247:00 amRNSTerm Sheet Termination, Funding & Loan Agreement
11th Oct 202412:22 pmRNSResult of Meeting
1st Oct 20248:00 amRNSSale of 19.52% Shareholding in MAST
26th Sep 20247:00 amRNSNotice of Extraordinary General Meeting
19th Sep 20241:45 pmRNSSale of Disposal of Kibo Mining (Cyprus) Signed
16th Sep 202412:10 pmRNSReverse Takeover & Disposal of Company’s Assets
12th Sep 20247:00 amRNSKibo Subsidiary Announces Business Update
30th Aug 20247:00 amRNSKibo Subsidiary MED Unaudited Interim Results
20th Aug 20247:00 amRNSKibo Subsidiary Announces Business Update
7th Aug 20247:00 amRNSKibo Subsidiary Business Update
5th Aug 20245:08 pmRNSUpdate to Placing Shares Issue of Equity & TVR
25th Jul 20241:50 pmRNSResults of Extraordinary General Meeting
23rd Jul 20247:00 amRNSTR-1: Notification of major holdings
18th Jul 20249:50 amRNSAppointment of Director
10th Jul 20247:00 amRNSNotice of Extraordinary General Meeting
5th Jul 20247:00 amRNSUpdate to Placing and Board Changes
1st Jul 20247:30 amRNSSuspension - Kibo Energy plc
1st Jul 20247:00 amRNSKibo Subsidiary Announces Business Update
27th Jun 202411:20 amRNSUpdate to Placing and Admission of Placing Shares
25th Jun 20247:00 amRNSPublication of AFS & Admission of Placing Shares
20th Jun 20247:00 amRNSUpdated Corporate Restructuring and Repositioning
13th Jun 20247:00 amRNSKibo Subsidiary Announces Business Update
12th Jun 20243:30 pmRNSUpdate to Corporate Restructuring
7th Jun 20242:07 pmRNSBroker Update
7th Jun 20247:00 amRNSCorporate Restructuring and Repositioning
30th May 20242:00 pmRNSKibo Subsidiary Announces AGM Results
23rd May 20243:55 pmRNSKibo Subsidiary Announces Business Update
21st May 20247:00 amRNSKibo Subsidiary Announces Business Update
9th May 202410:45 amRNSKibo Subsidiary MAST Major Shareholdings
8th May 20247:00 amRNSKibo Subsidiary Notice of Annual General Meeting
7th May 20247:00 amRNSKibo Subsidiary Business Update & Financing
30th Apr 20247:00 amRNSKibo Subsidiary MED Accounts’ Publication
26th Apr 20247:00 amRNSKibo Subsidiary Announces Business Update
23rd Apr 20242:30 pmRNSKibo Subsidiary Announces Major Shareholdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.