Operations Update

16 Feb 2012 11:00

RNS Number : 5473X
Jubilee Platinum PLC
16 February 2012
 



AIM: JLP

JSE: JBL

Registration number: 4459850

ISIN GB0031852162 16 February 2012

Jubilee Platinum PLC

("Jubilee" or the "Company")

Update

Jubilee, the AIM and JSE quoted mine to metal specialist is pleased to report an update on its Middelburg ferroalloy smelting operation (70% owned by Jubilee Smelting and Refining (Pty) Ltd.) and development on its Leinster nickel tailings project (the "Nickel Tailings Project" or "Project") in Western Australia.

HIGHLIGHTS

·; Middelburg smelter achieved record 774 tonnes ferroalloy production in January 2012, with continued ramp up of its new furnace;

 

·; Jubilee Smelting and Refining (Pty) Ltd ("JSR") received its environmental permitting to implement both the ConRoast smelting process as well as the refining of the produced PGM (platinum group metal) alloy at its Middelburg Smelting facility; and

 

·; Jubilee's Australian subsidiary, Braemore Nickel (Pty) Ltd ("Braemore") concluded a drilling program on the Leinster nickel sulphide tailings to obtain fresh samples for testwork at Mintek South Africa, in order to refine the scoping flowsheet on the Nickel Tailings Project.

Leon Coetzer, CEO of Jubilee Platinum commented: "We are pleased with the continued improved performance at our Middelburg smelting operation. We have met our set throughput targets for January and will continue to ramp up production through this quarter as we target full production. We have continued acquiring PGM containing feed material as we migrate our smelter capacity from ferroalloy smelting to PGM smelting. 

"With regard to our Australian nickel tailings project, we are pleased to have reached this stage on the project and look forward to the outcome of the confirmation testwork at Mintek with a view towards the potential development of the tailings".

Middelburg Smelter

JSR ramped up production from its new 5MW AC furnace with a record total 774 tonnes of ferroalloy output for January for the smelter operation.

 JSR remains focussed, in the short term, on ramping up the new furnace to its planned combined ferroalloy production of 1,100 tonnes per month in order to maximise cash flow. The extended ramp-up of the furnace was due mainly to initial refractory lining concerns and the nature of the stainless steel material, which prevented running the furnace at full capacity. This has now been resolved.

The Department of Economic Development, Environment and Tourism issued JSR with an Atmospheric Emission Licence in respect of its current and submitted new planned operations. JSR's smelter operation is now fully permitted for the implementation of the ConRoast process and associated refining of the PGM containing alloy. This, together with maximising cash flow from the ferroalloy smelting process, significantly advances JSR's medium term mission for the implementation of the complete ConRoast platinum smelting process and further strengthens its position in negotiations in sourcing PGM-rich chromite tailings.

Nickel Tailings Project

Braemore drilled and obtained fresh samples in January this year from the tailings in Western Australia ("Tailings") for further testwork. The samples have been despatched to Mintek, South Africa's national mineral research organisation, which has been contracted to carry out the testwork. This testwork is towards completion of an Engineering Study and Economic Evaluation (ESEE) of the Project, currently being carried out by Bateman Engineering Projects of South Africa ("Bateman").

Bateman's technical-economic review of the Project recommended testwork comprising pre concentration of the Tailings using a combination of classification and flotation methods in order to refine the Project scoping flowsheet and demonstrate from the ESEE the potential of the Project to meet the criteria stipulated in the Tailings Supply Agreement ("TSA Criteria"). Should the testwork and the ESEE demonstrate the potential to meet the TSA Criteria, the Company would anticipate progressing to a Definitive Feasibility Study on the Project thereafter.

Contacts

Jubilee Platinum plc

Colin Bird/Leon Coetzer

Tel +44 (0) 20 7584 2155 / Tel +27 (0)11 465 1913

Andrew Sarosi

Tel +44 (0) 1752 221937

finnCap Ltd

Matthew Robinson/Rose Herbert - corporate finance

Joanna Weaving - corporate broking

Tel +44 (0) 20 7600 1658 

Shore Capital Stockbrokers Limited (Joint Broker)

Jerry Keen/ Edward Mansfield

Tel: +44 (0) 20 7 408 4090

Sasfin Capital

Leonard Eiser /Sharon Owens

Tel +27 (0) 11 809 7500

Bishopsgate Communications Ltd

Nick Rome/Shabnam Bashir

Tel +44 (0) 20 7562 3350

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLDMGMZGVDGZZM
Date   Source Headline
6th Mar 20137:00 amRNSMajor Interest in Shares
27th Feb 20137:00 amRNSIssue of Equity
25th Feb 20132:55 pmRNSClarification
25th Feb 20137:00 amRNSTransactional Agreements to acquire PLA
19th Feb 201312:15 pmRNSUpdate regarding proposed merger with PLA
8th Feb 201312:26 pmRNSNotification of major interest in shares
5th Feb 20131:15 pmRNSProposed PLA Merger Update
29th Jan 201312:00 pmRNSProposed PLA Merger Update
25th Jan 20137:00 amRNSIssue of Equity
16th Jan 201312:45 pmRNSUpdate to the Proposed Transaction with PLA
10th Jan 20139:30 amRNSUpdate on Sale of Energy
17th Dec 20123:18 pmRNSResult of AGM
14th Dec 20124:18 pmRNSProposed Merger with Platinum Australia
14th Dec 20127:00 amRNSOperations Update
23rd Nov 20127:00 amRNSNotice of AGM and Posting of Report and Accounts
21st Nov 20127:00 amRNSProcessing Agreements Update
23rd Oct 20124:03 pmRNSTR-1: Notification of major interest in shares
23rd Oct 20124:00 pmRNSTR-1: Notification of major interest in shares
19th Oct 20127:00 amRNSTotal Voting Rights
17th Oct 20127:00 amRNSOperations Update
15th Oct 20127:00 amRNSIssue of Equity
9th Oct 201212:00 pmRNSToll processing tailings agreement
27th Sep 20124:51 pmRNSFinal Results
27th Sep 201211:30 amRNSOperations Update
24th Aug 20127:00 amRNSJubilee executes farm-in agreement with IPR
8th Aug 20125:17 pmRNSOperations Update
9th Jul 20127:00 amRNSFarm-in agreement
13th Jun 20127:00 amRNSJubilee Awarded Rights to Chromite Tailings
11th Jun 20121:30 pmRNSResult of General Meeting
22nd May 20128:00 amRNSUpdate
18th May 20127:00 amRNSNotice of General Meeting
29th Mar 20127:00 amRNSInterim Report
27th Mar 20127:00 amRNSTrading Statement
16th Feb 201211:00 amRNSOperations Update
28th Dec 20112:27 pmRNSResults of AGM
7th Dec 20118:00 amRNSNotice of AGM and Posting of Report and Accounts
20th Oct 201112:30 pmRNSShareholdings in Company
19th Oct 201111:30 amRNSHolding(s) in Company
13th Oct 20111:45 pmRNSIssue of Equity
4th Oct 20117:00 amRNSTjate's Quartzhill farm
30th Sep 201112:00 pmRNSFinal Results
29th Sep 20118:51 amRNSTrading Update
5th Aug 20117:00 amRNSOperations Update
8th Jul 20111:45 pmRNSWithdrawal of Cautionary Announcement
24th Jun 20117:00 amRNSAppointment of UK Joint Broker
20th Jun 201110:00 amRNSCompany Update
17th Jun 20112:30 pmRNSWithdrawal of Cautionary Announcement
20th May 201111:00 amRNSJubilee in Preliminary Discussions and Cautionary
21st Apr 20112:30 pmRNSCorrection - Directors Dealings
21st Apr 20117:00 amRNSDirectors Dealings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.