Drilling Programme Commences at Laguna Verde

8 Jan 2024 07:00

RNS Number : 8646Y
CleanTech Lithium PLC
08 January 2024
 

8th January 2024

 

CleanTech Lithium PLC ("CleanTech Lithium" or "CTL" or the "Company")

New Resource Drilling Programme Commences at Laguna Verde

CleanTech Lithium PLC (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF) commences new drilling programme at the Laguna Verde project and outlines planned activity.

Highlights:

· Drill rig mobilisation and establishment of drillers camp and support services now completed with the drilling of the first of five planned wells, LV07 (see figure 1), having started on 4 January 2024

· Drill programme to target upgrade of existing JORC resource and to convert resources into reserves

· Generation of a reserve estimate of lithium carbonate equivalent (LCE) is to be included in the Project's pre-feasibility study and ultimately the project´s production plan

· CTL has engaged leading hydrogeology and resource estimation consultant Montgomery & Associates for the resource drill programme and JORC reserve report

· The programme will include reinjection testing to further define the brine extraction and reinjection model, as the Company continues to be a leader in advancing a direct lithium extraction (DLE) based sustainable lithium production model in Chile.

 

Aldo Boitano, Chief Executive Officer, CleanTech Lithium said: "We are excited to start off the new year with another active drilling programme at our flagship project, Laguna Verde. The aim of this drilling programme is to upgrade the current JORC resource, converting resources into reserves. This provides a key input into the pre-feasibility study and will inform the environmental impact assessment, all of which will support CTL's conversations with potential strategic partners.

We are working with a leading international consultant, Montgomery & Associates, to deliver the resource drill programme which will include reinjection testing. The reinjection of spent brine is key to minimizing aquifer depletion. Furthermore, we are expecting results from our DLE test work and first eluate production from our pilot plant in the coming weeks. We are looking forward to a busy and highly productive 2024."

Figure 1: LV07 drill rig in place with work tent - early January 2024

Resource Drill Programme

At Laguna Verde a resource drill programme is planned to convert existing Measured and Indicated resources of 1.1 million tonnes LCE into Reserves. The existing JORC compliant total resource estimate of 1.8 million tonnes of lithium carbonate equivalent (LCE) is based on six wells completed in 2022 and 2023. A further five wells are planned to be completed in the first half of 2024, as shown in figure 2, which will contribute to a new JORC compliant reserve report targeted for completion in July 2024. The Company has engaged Montgomery & Associates, a leading hydrogeological consultant, for the 2024 programme.

Figure 2: Drill Plan Map Showing Previous and Planned Well Locations

The drill programme will comprise four diamond drill holes and one wide diameter reverse circulation well (LV09) which will be used for planned extraction and reinjection tests. The data generated from this testing will be used in the key hydrogeological models for the project, being the water balance model for the basin and the groundwater flow model, that are used in reserve estimation, feasibility studies, the Environmental Impact Assessment (EIA), and ultimately the project's plan for production.

The drilling contractor has mobilised equipment, installed the drillers camp and completed access roads for the planned new wells.

Figure 3: Mobilisation of Equipment and Drillers Camp - late December 2023

Drilling of the first planned well, LV07, started on 4 January. LV07 will be targeting a depth of up to 700m based on the results of the gravity survey in 2023, which is the deepest target depth drilled at the project to date. Two drill rigs will be used to accelerate the programme. Results from the drilling and hydrogeological evaluations will be reported to the market on an ongoing basis during 1H 2024. 

Direct Lithium Extraction Process Test-work Update

The Company is nearing completion of important DLE test work which will be reported to the market. Trials using the brine from the Company's projects have been ongoing, utilising CTL's lab-scale DLE carousel unit in Copiapó as well as at the facilities of the Company´s DLE process partners. These trials provide information on key operating parameters that will be applied as the Company ramps up the production of DLE eluate from its pilot plant, with first eluate production expected in the coming weeks.

 

**ENDS**

For further information contact:

 

 

 

 

CleanTech Lithium PLC

 

Aldo Boitano/Gordon Stein

Jersey office: +44 (0) 1534 668 321

Chile office: +562-32239222

 

Or via Celicourt

 

Celicourt Communications

+44 (0) 20 7770 6424

 

Felicity Winkles/Philip Dennis/Ali AlQahtani

cleantech@celicourt.uk

 

 

Dr. Reuter Investor Relations

Dr. Eva Reuter

 

Harbor Access - North America

Jonathan Paterson/Lisa Micali

 

Porter Novelli - Chile

Ernesto Escobar

 

Beaumont Cornish Limited

(Nominated Adviser)

Roland Cornish/Asia Szusciak

 

+49 69 1532 5857

 

 

+1 475 477 9401

 

 

+569 95348744

Ernesto@publicoporternovelli.cl

 

 

+44 (0) 207 628 3396

 

 

Fox-Davies Capital Limited

(Joint Broker)

Daniel Fox-Davies

Canaccord Genuity Limited

(Joint Broker)

James Asensio

 

+44 (0) 20 3884 8450

 

daniel@fox-davies.com

+44 (0) 207 523 4680

 

 

 

 

 

 

Beaumont Cornish Limited ("Beaumont Cornish") is the Company's Nominated Adviser and is authorised and regulated by the FCA. Beaumont Cornish's responsibilities as the Company's Nominated Adviser, including a responsibility to advise and guide the Company on its responsibilities under the AIM Rules for Companies and AIM Rules for Nominated Advisers, are owed solely to the London Stock Exchange. Beaumont Cornish is not acting for and will not be responsible to any other persons for providing protections afforded to customers of Beaumont Cornish nor for advising them in relation to the proposed arrangements described in this announcement or any matter referred to in it.

 

Notes

 

About CleanTech Lithium

CleanTech Lithium (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF) is an exploration and development company advancing sustainable lithium projects in Chile for the clean energy transition. Committed to net-zero, CleanTech Lithium's mission is to produce material quantities of battery grade using sustainable Direct Lithium Extraction technology, powered by renewable energy, the Company plan to be the leading supplier of 'green' lithium to the EV and battery manufacturing market.

CleanTech Lithium has four lithium projects - Laguna Verde, Francisco Basin, Llamara and Salar de Atacama - located in the lithium triangle, the world's centre for battery grade lithium production. The two major projects: Laguna Verde and Francisco Basin are situated within basins controlled by the Company, which affords significant potential development and operational advantages. All four projects have direct access to existing infrastructure and renewable power.

CleanTech Lithium is committed to using renewable power for processing and reducing the environmental impact of its lithium production by utilising Direct Lithium Extraction. Direct Lithium Extraction is a transformative technology which removes lithium from brine, with higher recoveries and purities. The method offers short development lead times, low upfront capex, with no extensive site construction and no evaporation pond development so there is no water depletion from the aquifer. www.ctlithium.com

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
DRLUNOURSOUARAR
Date   Source Headline
30th Apr 20267:00 amRNS-RUpdated Investor Presentation
22nd Apr 20267:00 amRNSUpdate to Legal Claim in Chile
16th Apr 20267:00 amRNS-RTrials to Further Validate PFS Process Design
14th Apr 20267:00 amRNSReplacement: Positive PFS Results RNS
9th Apr 20267:00 amRNSAppointment of Australian Resident Independent NED
31st Mar 20267:00 amRNSPositive Pre-Feasibility Study & Reserves Declared
23rd Mar 20267:00 amRNSVAT refund of over £1 million received
17th Mar 20263:08 pmRNSIssue of Equity, TVR and Blocklisting Application
16th Mar 20268:00 amRNSHolding(s) in Company
10th Mar 20265:53 pmRNSLV CEOL Terms Agreed with Chilean Government
12th Feb 20267:00 amRNSUpdate to CEOL Process and CFO Position
27th Jan 20263:30 pmRNSHolding(s) in Company
6th Jan 20267:00 amRNSAppointment of Project Financial Advisor
5th Jan 20267:00 amRNSCEOL Application for Laguna Verde Submitted
31st Dec 20257:00 amRNS-REnd-of-Year Message from CEO
22nd Dec 20254:23 pmRNSResult of AGM
19th Dec 20257:00 amRNSLaguna Verde New CEOL Streamlined Process Opened
15th Dec 20257:00 amRNSLaguna Verde Indigenous Consultations Concluded
1st Dec 20257:00 amRNSLegal action against subsidiary of CleanTech
28th Nov 20257:00 amRNSNotice of AGM and Electronic Communications
10th Nov 20257:00 amRNSLaguna Verde Resource Increase
3rd Nov 20257:00 amRNSIssue of Equity & Partial Redemption of Loan Notes
23rd Oct 20255:22 pmRNSHolding(s) in Company
20th Oct 20257:00 amRNSUpdate to Certain Laguna Verde Licence Payments
10th Oct 20257:00 amRNS-RInvestor Presentation via Investor Meet Company
6th Oct 20257:00 amRNSAppointment of Jersey Resident Independent NED
1st Oct 20257:00 amRNS-RShareholder Meet and Greet in London
29th Sep 20257:00 amRNSInterim Results for six-months ending 30 June 2025
8th Sep 20257:00 amRNSIssue of Equity and TVR
29th Aug 202512:19 pmRNSResult of GM, Issue of Equity and TVR
29th Aug 20257:00 amRNSResults of Retail Offer
26th Aug 20257:01 amRNSRetail Offer to Shareholders
26th Aug 20257:00 amRNSResults of Broker Option
14th Aug 20255:03 pmRNSGrant of Options
13th Aug 20254:51 pmRNSNotice of General Meeting and Posting of Circular
11th Aug 20258:24 amRNSResults of Placing, Issue of Equity and TVR
11th Aug 20257:00 amRNSAdditional Licences, Fundraising & Board Changes
1st Aug 20257:00 amRNSExtension to Loan Notes Maturity Date
7th Jul 20257:00 amRNSProcess Test-work Progress Update
30th Jun 20257:05 amRNSUpdate to CEOL Appeal
30th Jun 20257:00 amRNSExtension to Loan Notes Maturity Date
12th Jun 202511:00 amRNSFinal Results
30th Apr 20257:00 amRNSUpdate to CEOL Application
23rd Apr 20257:00 amRNSUpdate to CEOL Process
17th Apr 20257:00 amRNS-RCollaboration with DuPont Water Solutions
10th Apr 20257:00 amRNSAppointment of CEO and Director
4th Apr 20257:00 amRNSCEOL Application Process Update
24th Mar 202512:47 pmRNSResult of GM Admission of Retail Offer Shares TVR
10th Mar 20257:00 amRNSResults of Retail Offer & Update on Broker Option
4th Mar 20254:45 pmRNSNotice of General Meeting and Posting of Circular

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.