Pin to quick picksCleantech Lithium Regulatory News (CTL)

Share Price Information for Cleantech Lithium (CTL)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 20.50
Bid: 20.00
Ask: 21.00
Change: 2.50 (13.89%)
Spread: 1.00 (5.00%)
Open: 18.00
High: 20.50
Low: 18.00
Prev. Close: 18.00
CTL Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Direct Lithium Extraction (DLE) Progress Update

8 Nov 2023 07:00

RNS Number : 7095S
CleanTech Lithium PLC
08 November 2023
 

8 November 2023

 

CleanTech Lithium PLC ("CleanTech Lithium" or "CTL" or the "Company")

Direct Lithium Extraction (DLE) Progress Update

 

CleanTech Lithium PLC (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF), an exploration and development company advancing sustainable lithium projects in Chile for the clean energy transition, provides a progress update on Direct Lithium Extraction (DLE) with the final components for the DLE Pilot Plant arriving and being installed in Copiapó, Chile.

The Company is progressing the Pre-Feasibility Study (PFS) at its major Laguna Verde project which will incorporate the results from extensive test work over six months using the lab scale multivalve DLE system. In addition, the DLE Pilot Plant and downstream process plant to produce battery grade lithium carbonate will enable the Company to advance discussions with potential strategic partners who can support the development and financing of the Company's projects.

Highlights:

- Delivery of final components of the DLE Pilot Plant at CTL's warehouse facilities in Copiapó means the pilot plant can be fully assembled and testing starts.

- Technicians from Sunresin are scheduled to visit at the end of November 2023 for the final testing and commissioning phase.

- The DLE Pilot Plant is designed to produce up to 1 tonne per month of lithium carbonate equivalent (LCE) in concentrated lithium eluate which will be processed to battery grade lithium carbonate at an existing third party facility.

- Samples of the product will be made available to potential strategic partners and offtakers, such as major auto and battery manufacturers, for testing and product qualification.

- Recently, a team from CTL's senior leadership visited several DLE operations in China. The visit demonstrated how rapidly DLE technology is advancing.

- CEO Aldo Boitano, Non-Executive Director, Maha Daoudi and DLE Process Manager, Rodrigo Rivas, visited DLE operations and manufacturers spanning the DLE supply chain to see first hand the commercial application of the technology in China.

Aldo Boitano, Chief Executive Officer, CleanTech Lithium said: "The recent visit to China has shown me the great opportunity DLE offers to produce lithium with an ESG led approach. It is clear in my mind that DLE is the way forward for lithium production if we are to meet EV production targets.

The companies we visited in China are forging ahead with lithium extraction from brine with no evaporation ponds and this has provided further certainty in our projects as we progress with the PFS for Laguna Verde. This important phase of CTL's growth will help with the discussions we are planning to have with strategic partners in 2024.

The next six months is going to be a busy period for CTL, with the combination of the PFS and the analysis of results from the DLE Pilot Plant making this an exciting period in the Company's journey."

Maha Daoudi, Independent Non-Executive Director, CleanTech Lithium said: "It has been fantastic to return to China and see the pace of technological advancement. With the support of a local specialist consultant with whom I have worked before for many years, we have been able to meet the Chairmen and CEOs of some of the world's leading DLE developers to discuss how we can apply their technical expertise to CTL's projects. It has been overall a very constructive visit and gives positive perspectives for the development of CTL's projects. "

 

DLE Pilot Plant

The pilot plant is designed for process optimisation and to produce a purified concentrated eluate that will feed the downstream process to deliver 1 tonne per month of LCE for product qualification by potential offtakers and strategic partners.

The US$2 million plant has been fabricated in Belgium by Puritech, a wholly-owned subsidiary of the Company's DLE partner, Sunresin, who are the leading provider of operational DLE facilities in the world.

The final shipment for the DLE Pilot Plant has arrived in Chile and will be transported to CTL's warehouse facility in Copiapó where it will be assembled. Technicians from Sunresin are scheduled to visit at the end of November 2023 for the final testing and commissioning phase.

The DLE pilot plant will process feed brine to produce an eluate in which lithium has been selectively extracted and concentrated, while other elements in the brine are greatly reduced (see figure 1). The eluate will then undergo several stages of concentration and impurity removal before carbonation into battery grade lithium.

Figure 1: CleanTech Lithium's simplified DLE processing flowsheet

China Visit by Senior Management

CEO, Aldo Boitano, Non-Executive Director Maha Daoudi and DLE Processes Manager, Rodrigo Rivas, recently visited China where they met with several DLE operators and developers. Ms Daoudi has significant experience in China from her time at world leading trading company, Trafigura, where she helped develop strategic partnerships and significant offtake agreements over a number of years. A key objective of the trip was to share learnings and developments of CTL's projects, meet the leadership teams of DLE companies and see the facilities of existing operators.

Figure 2: Sunresin's senior leadership team welcoming CleanTech Lithium to their facilities

Figure 3: Lanshen's senior leadership team welcoming CleanTech Lithium to their facilities

CTL visited Sunresin New Materials Co. Ltd. and Lanshen Technology which included seeing facilities similar to the Company's DLE pilot plant being assembled in Copiapó. This included a trip to Geermu, Golmud to see a resin manufacturing process which is used for their three operating DLE plants.

Figure 4: Lanshen's demonstration plant for extracting lithium from brine with Minmetals Salt Lake Co. Ltd.

Source: Lanshen New Material Technology Co.Ltd.

Figure 5: Jiuwu's senior leadership team welcoming CleanTech Lithium to discuss DLE development and attend a site visit

A further productive meeting was held with Jiangsu Jiuwu Hitech Co.,Ltd, a leading specialist in membrane technologies, including a visit to a working DLE pilot plant.

Figure 6: CEO, Aldo Boitano from CleanTech Lithium on a visit to a DLE pilot plant

A meeting was held with Yongzheng, experts in the manufacturing and exporting of lithium batteries. The Company is currently constructing a 5,000 tpa battery-grade lithium hydroxide project where it is using a technology that maximises lithium recovery rates.

DLE, as demonstrated in China, is a proven method of producing lithium from brines faster and with much higher recovery rates compared to traditional production that require pre-treatment and evaporation ponds. DLE is based on a commercially proven adsorption technology and has been used in multiple industries over many decades and is now being applied to brine-based lithium projects.

 

 

 

**ENDS**

For further information contact:

 

 

 

 

CleanTech Lithium PLC

 

Aldo Boitano/Gordon Stein

Jersey office: +44 (0) 1534 668 321

Chile office: +562-32239222

 

Or via Celicourt

 

Celicourt Communications

+44 (0) 20 7770 6424

 

Felicity Winkles/Philip Dennis/Ali AlQahtani

cleantech@celicourt.uk

 

 

Dr. Reuter Investor Relations

Dr. Eva Reuter

 

Harbor Access - North America

Jonathan Paterson/Lisa Micali

 

Porter Novelli - Chile

Ernesto Escobar

 

Beaumont Cornish Limited

(Nominated Adviser)

Roland Cornish/Asia Szusciak

 

+49 69 1532 5857

 

 

+1 475 477 9401

 

 

+569 95348744

Ernesto@publicoporternovelli.cl

 

 

+44 (0) 207 628 3396

 

 

Fox-Davies Capital Limited

(Joint Broker)

Daniel Fox-Davies

Canaccord Genuity Limited

(Joint Broker)

James Asensio

 

+44 (0) 20 3884 8450

 

daniel@fox-davies.com

+44 (0) 207 523 4680

 

 

 

 

 

 

 

Notes

 

About CleanTech Lithium

CleanTech Lithium (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF) is an exploration and development company advancing sustainable lithium projects in Chile for the clean energy transition. Committed to net-zero, CleanTech Lithium's mission is to produce material quantities of battery grade using sustainable Direct Lithium Extraction technology, powered by renewable energy, the Company plan to be the leading supplier of 'green' lithium to the EV and battery manufacturing market.

CleanTech Lithium has four lithium projects - Laguna Verde, Francisco Basin, Llamara and Salar de Atacama - located in the lithium triangle, the world's centre for battery grade lithium production. The two major projects: Laguna Verde and Francisco Basin are situated within basins controlled by the Company, which affords significant potential development and operational advantages. All four projects have direct access to existing infrastructure and renewable power.

CleanTech Lithium is committed to using renewable power for processing and reducing the environmental impact of its lithium production by utilising Direct Lithium Extraction. Direct Lithium Extraction is a transformative technology which removes lithium from brine, with higher recoveries and purities. The method offers short development lead times, low upfront capex, with no extensive site construction and no evaporation pond development so there is no water depletion from the aquifer. www.ctlithium.com

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDFFFFFLILDIIV
Date   Source Headline
22nd Apr 20247:00 amRNSAcquisition of Laguna Verde licences
12th Apr 20247:00 amRNSDirectorate Change
9th Apr 20247:00 amRNSDirector's Share Dealing
3rd Apr 20247:00 amRNSCEOL Applications
27th Mar 20248:25 amRNSComment on Chilean Government's Announcement
20th Mar 20247:00 amRNSPilot Plant Producing First Lithium Chloride
29th Feb 20247:00 amRNSLaguna Verde Project PFS Update
19th Feb 20244:10 pmRNSInvestor Webinar (Replacement)
19th Feb 20241:15 pmRNSInvestor Webinar
30th Jan 20247:00 amRNSDLE Process Test Work - Adsorbent Selection
25th Jan 20247:00 amRNSHost International Academics - University Atacama
22nd Jan 20247:00 amRNSDrilling Update at Laguna Verde
8th Jan 20247:00 amRNSDrilling Programme Commences at Laguna Verde
29th Dec 202311:13 amRNSTotal Voting Rights
20th Dec 20232:29 pmRNSHolding(s) in Company
14th Dec 202312:39 pmRNSResult of GM, PDMR Shareholdings & TVR
14th Dec 20239:00 amRNSCTL Awarded Green Achievement Grand Prix Award
12th Dec 20237:00 amRNSAgreement for Co-Developed Mining Model
4th Dec 202312:07 pmRNSTotal Voting Rights
23rd Nov 20237:00 amRNSOpen Offer, Posting of Circular & GM Notice
22nd Nov 20237:14 amRNSResults of Placing
21st Nov 20234:45 pmRNSProposed Fundraising
8th Nov 20237:00 amRNSDirect Lithium Extraction (DLE) Progress Update
26th Oct 20238:00 amRNSStrategic Partnership - The University of Atacama
4th Oct 20239:30 amRNSInvestor Webinar and New Company Presentation
29th Sep 20237:00 amRNSUpdate on Exploration Stage Projects
26th Sep 20237:00 amRNSFrancisco Basin Scoping Study
7th Sep 20237:00 amRNSApplication of Operating Contracts in Chile
4th Sep 20237:00 amRNSDirect Lithium Extraction (DLE) Pilot Plant Update
24th Aug 20237:00 amRNSUpgraded JORC resource- Francisco Basin Li Project
17th Jul 20237:00 amRNSUpgraded JORC Resource - Laguna Verde Li Project
23rd Jun 202311:44 amRNSPDMR Dealing
21st Jun 20237:00 amRNSAppointment of Australian NED and Board Changes
6th Jun 20237:00 amRNS3 Projects - Operations Update
1st Jun 202310:43 amRNSDTC Eligibility for OTCQX Trading in the U.S.
31st May 202312:36 pmRNSCommencement of trading on OTCQX® Best Market
31st May 202312:02 pmRNSResult of AGM
30th May 20237:00 amRNSOperations Update
26th May 20237:00 amRNSInvestor Events Schedule
9th May 20237:00 amRNSNotice of AGM
5th May 20237:00 amRNSFinal Results
24th Apr 20237:00 amRNSFurther Comment: Chile’s National Li Strategy
21st Apr 202312:01 pmRNSReaction to Comments by Chile's President Boric
12th Apr 20237:00 amRNSInvestor Events Schedule
31st Mar 202312:54 pmRNSGrant of Options, Exercise of Options and TVR
31st Mar 20239:05 amRNSSecond Price Monitoring Extn
31st Mar 20239:00 amRNSPrice Monitoring Extension
31st Mar 20237:00 amRNSOperations and Corporate Update
28th Mar 20237:00 amRNSBoard changes to advance next phase of development
24th Feb 20237:00 amRNSProposed Listing on Australian Securities Exchange

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.