The latest Investing Matters Podcast episode featuring Jeremy Skillington, CEO of Poolbeg Pharma has just been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAndrada Mining. Regulatory News (ATM)

Share Price Information for Andrada Mining. (ATM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 5.00
Bid: 4.90
Ask: 5.10
Change: -0.05 (-0.99%)
Spread: 0.20 (4.082%)
Open: 5.05
High: 5.05
Low: 5.00
Prev. Close: 5.05
ATM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Uis Phase 1 Expansion Commissioning Complete

7 Nov 2022 07:00

RNS Number : 4508F
AfriTin Mining Ltd
07 November 2022
 

7 November 2022

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 (MAR) as in force in the United Kingdom pursuant to the European Union (Withdrawal) Act 2018. Upon the publication of this announcement via Regulatory Information Service (RIS), this inside information is now considered to be in the public domain.

AfriTin Mining Limited

 ("AfriTin" or the "Company")

Uis Phase 1 Expansion Commissioning Complete

AfriTin Mining Limited (AIM: ATM), an African technology metals mining company with a portfolio of mining and exploration assets in Namibia, is pleased to provide an update of its Phase 1 Expansion Project at the Uis Mine ("Uis").

Highlights:

· Commissioning of the Uis Phase 1 Expansion Project complete;

· Production projected to ramp up from 780 to 1200 tpa of tin concentrate over the next three months; and

· The potential by-product production of lithium and tantalum is expected to benefit from the plant throughput expansion due to its co-occurrence within the ore.

Anthony Viljoen (CEO) commented:

"We are extremely pleased to announce the completion of commissioning for our Uis Phase 1 Expansion Project. The beneficiation plant is performing well, and the production ramp-up from pre-expansion levels is going according to plan. The potential production of lithium and tantalum by-products is also expected to benefit from the expansion of the throughput capacity of the plant, since these minerals will be extracted from the existing processing streams.

Our team has once again demonstrated the ability to deliver value accretive projects. Our development strategy is centred on driving costs down whilst expanding our mineral resource base, production volumes and product portfolio of tin, lithium and tantalum with the concomitant increase in revenue streams. We remain committed to our goal of becoming a tier-one producer of technology metals."

Project Overview

The Uis Phase 1 Expansion Project ("the Project") targets an increase in production at Uis from approximately 780 tonnes per annum ("tpa") to 1200 tpa tin concentrate (470 tpa and 720 tpa tin contained in concentrate respectively). The Project scope consists of a modular expansion of the current processing plant, leveraging existing bulk infrastructure services. Specifically, it involves the expansion of the crushing and screening circuits ("the dry plant") and construction of a fines ore stockpile prior to the concentrator. The expansion of the dry plant will allow the operation to increase the feed rate of ore to the plant by approximately 50%, while the new stockpile provides buffer capacity before the concentrator ("the wet plant") to increase plant utilisation. In addition, the Project addresses potential throughput constraints in the concentrator due to the increased feed rate, as well as upgrades to the concentrate cleaning circuit to enhance tin recovery, and upgrades to the process control and instrumentation to improve plant operability and utilisation.

Plant Commissioning

The Project commenced in September 2021 with the ordering of long lead items. Project construction was completed in mid-September 2022 and commissioned one month later. A C4 commissioning certificate has been received from Consulmet, an independent mineral processing consultancy that acted as commissioning manager. C4 commissioning refers to the hot commissioning of processing circuits and involves stages including feeding ore material into the process plant, validating process flows and instrumentation readings, and the achievement of instantaneous design throughput. A C4 certificate indicates that the entire system is complete and fully operational.

Current daily production has now matched pre-expansion levels, as planned, and the plant will be ramped up over the next three months to achieve continuous design throughput.

Uis Development Strategy

The Company is developing its business aspirations in Namibia through expansion of its mineral resource base, expansion of both production volume and product portfolio, and a strategic focus on supplying metals to the technology and renewable energy sectors.

The Uis Mine is AfriTin's flagship project and underpins its development strategy. The ore mined at Uis contains additional commodities in addition to tin, including lithium and tantalum. An infill exploration programme is currently in progress, aiming to improve the geological confidence of the present lithium and tantalum mineral resource estimate.

The existing plant processing circuits extract a high-quality tin concentrate. The Company has initiated a further expansion of the current plant to produce a saleable tantalum concentrate. In addition, successful bench scale tests for the production of a lithium concentrate will be followed by the construction of a lithium pilot plant at the mine site.

The increased plant throughput resulting from the Project is also expected to benefit the ultimate production of lithium and tantalum by-products, since these minerals are present in the same ore stream as tin. AfriTin is investigating the suitability of sensor-based ore sorting which has the potential to further expand the throughput of ore at Uis by a factor of two to three times.

The Company will provide an update on its Uis development programme in due course.

 

* The Company's Financial Year runs from March to February. All reference to quarters applies to the financial year reporting period, unless stated otherwise.

AfriTin Mining Limited

+27 (11) 268 6555

Anthony Viljoen, CEO

Nominated Adviser 

+44 (0) 207 220 1666

WH Ireland Limited

Katy Mitchell

Corporate Advisor and Joint Broker

H&P Advisory Limited

Andrew Chubb

Jay Ashfield

Nilesh Patel

+44 (0) 20 7907 8500

Stifel Nicolaus Europe Limited

Ashton Clanfield

Callum Stewart

+44 (0) 20 7710 7600

Tavistock Financial PR (United Kingdom)

+44 (0) 207 920 3150

Emily Moss

Catherine Drummond

Adam Baynes

 

About AfriTin Mining Limited

Notes to Editors

AfriTin Mining Limited is a London-listed technology metals mining company with a vision to create a portfolio of globally significant, conflict-free, producing and exploration assets. The Company's flagship asset is the Uis Tin Mine in Namibia, formerly the world's largest hard-rock open cast tin mine.

AfriTin is managed by an experienced board of directors and management team with a current strategy to ramp-up production at the Uis Mine in Namibia to more than 10,000 tonnes of tin concentrate and 350,000 tonnes of lithium concentrate in a Phase 2 expansion, having reached Phase 1 commercial production in 2020. The Company strives to capitalise on the solid supply/demand fundamentals of tin and lithium by developing a critical mass of resource inventory, achieving production in the near term and further scaling production by consolidating assets in Africa.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCBKABQPBDDADK
Date   Source Headline
27th Mar 20249:38 amRNSOperational update - replacement
27th Mar 20247:00 amRNSOperational update for the period ended 29/02/24
19th Mar 20247:36 amRNSFunding Agreement
12th Mar 20247:00 amRNSProduction and Strategic Process Update
22nd Dec 20237:00 amRNSQ3 Ops Update for the period ended 30 Nov 2023
5th Dec 20237:00 amRNSSpodumene Concentrate Produced from Lithium Ridge
29th Nov 20237:00 amRNSUNAUDITED INTERIM RESULTS 6 MONTHS ENDED 31/08/23
28th Nov 20236:40 pmRNSHolding(s) in Company - Replacement
28th Nov 20235:03 pmRNSHolding(s) in Company
27th Nov 20237:00 amRNSLithium Development Update
16th Nov 20237:00 amRNSUSD 25 million received from OMF
15th Nov 20237:00 amRNSRenewal of off-take agreements
27th Oct 202312:08 pmRNSRelease of the 2023 Sustainability Report
12th Oct 20237:00 amRNSUpdate on Brandberg West
3rd Oct 20232:08 pmRNSExercise of Share Options
29th Sep 20237:00 amRNSExercise of Share Options
18th Sep 20237:00 amRNSFinal Results for Initial ML133 Drill Programme
14th Sep 20237:00 amRNSQ2 Ops Update for the period ended 31 August 2023
6th Sep 20237:00 amRNSInitial Drill Results on ML133 (“Lithium Ridge”)
5th Sep 20237:00 amRNSDevelopment Bank of Namibia financing concluded
29th Aug 20237:00 amRNSExploration Update on ML133 (Lithium Ridge)
24th Aug 20238:30 amRNSAudited Financial Results
15th Aug 20234:46 pmRNSOrion US$25m Funding Package Update - Replacement
15th Aug 20237:00 amRNSOrion US$25 Million Funding Package Update
18th Jul 20237:00 amRNSFunding update and commissioning of pilot plant
6th Jul 20237:00 amRNSDrill programme results for Spodumene Hill Project
26th Jun 20237:00 amRNSOperational update for period ended 31 May 2023
5th Jun 20237:00 amRNSShares to Trade on OTCQB & Update on Financing
22nd May 20237:00 amRNSFirst Bulk Lithium Production and Funding Update
18th May 20237:00 amRNSNotice of Investor Presentations
11th May 20237:05 amRNSIssue of Share Options
11th May 20237:00 amRNSAppointment of Barclays as Strategic Advisor
10th May 20237:00 amRNSAppointment of Directors
30th Mar 20235:26 pmRNSV1V2 final 2022 exploration drilling results
20th Mar 20237:00 amRNSQuarterly FY 2023 production and Company update
20th Feb 20237:00 amRNSDirector/PDMR Shareholding
6th Feb 20237:00 amRNSSignificant Lithium Resource Upgrade
2nd Feb 20237:00 amRNSLithium And Tantalum Infill Drilling Update
1st Feb 20238:33 amRNSHolding(s) in Company
31st Jan 20237:00 amRNSLithium and tantalum infill drill programme update
27th Jan 20237:00 amRNSConfirmation of Change in Website Address
26th Jan 20237:00 amRNSPublication of the Inaugural Sustainability Report
25th Jan 20233:54 pmRNSExercise of warrants and issue of equity
23rd Jan 20237:00 amRNSUis Mine Mineral Resource Expansion
10th Jan 20234:51 pmRNSConfirmation of Name Change
5th Jan 20235:06 pmRNSResult of EGM and Change of Name
22nd Dec 20227:00 amRNSQuarterly Production Update
7th Dec 20227:00 amRNSLithium and Tantalum Product Development Update
6th Dec 20227:00 amRNSNotice of EGM and Proposed Change of Name
5th Dec 20227:00 amRNSLithium and Tantalum Infill Drill Programme Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.