Uis Phase 1 Expansion Commissioning Complete

7 Nov 2022 07:00

RNS Number : 4508F
AfriTin Mining Ltd
07 November 2022
 

7 November 2022

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 (MAR) as in force in the United Kingdom pursuant to the European Union (Withdrawal) Act 2018. Upon the publication of this announcement via Regulatory Information Service (RIS), this inside information is now considered to be in the public domain.

AfriTin Mining Limited

 ("AfriTin" or the "Company")

Uis Phase 1 Expansion Commissioning Complete

AfriTin Mining Limited (AIM: ATM), an African technology metals mining company with a portfolio of mining and exploration assets in Namibia, is pleased to provide an update of its Phase 1 Expansion Project at the Uis Mine ("Uis").

Highlights:

· Commissioning of the Uis Phase 1 Expansion Project complete;

· Production projected to ramp up from 780 to 1200 tpa of tin concentrate over the next three months; and

· The potential by-product production of lithium and tantalum is expected to benefit from the plant throughput expansion due to its co-occurrence within the ore.

Anthony Viljoen (CEO) commented:

"We are extremely pleased to announce the completion of commissioning for our Uis Phase 1 Expansion Project. The beneficiation plant is performing well, and the production ramp-up from pre-expansion levels is going according to plan. The potential production of lithium and tantalum by-products is also expected to benefit from the expansion of the throughput capacity of the plant, since these minerals will be extracted from the existing processing streams.

Our team has once again demonstrated the ability to deliver value accretive projects. Our development strategy is centred on driving costs down whilst expanding our mineral resource base, production volumes and product portfolio of tin, lithium and tantalum with the concomitant increase in revenue streams. We remain committed to our goal of becoming a tier-one producer of technology metals."

Project Overview

The Uis Phase 1 Expansion Project ("the Project") targets an increase in production at Uis from approximately 780 tonnes per annum ("tpa") to 1200 tpa tin concentrate (470 tpa and 720 tpa tin contained in concentrate respectively). The Project scope consists of a modular expansion of the current processing plant, leveraging existing bulk infrastructure services. Specifically, it involves the expansion of the crushing and screening circuits ("the dry plant") and construction of a fines ore stockpile prior to the concentrator. The expansion of the dry plant will allow the operation to increase the feed rate of ore to the plant by approximately 50%, while the new stockpile provides buffer capacity before the concentrator ("the wet plant") to increase plant utilisation. In addition, the Project addresses potential throughput constraints in the concentrator due to the increased feed rate, as well as upgrades to the concentrate cleaning circuit to enhance tin recovery, and upgrades to the process control and instrumentation to improve plant operability and utilisation.

Plant Commissioning

The Project commenced in September 2021 with the ordering of long lead items. Project construction was completed in mid-September 2022 and commissioned one month later. A C4 commissioning certificate has been received from Consulmet, an independent mineral processing consultancy that acted as commissioning manager. C4 commissioning refers to the hot commissioning of processing circuits and involves stages including feeding ore material into the process plant, validating process flows and instrumentation readings, and the achievement of instantaneous design throughput. A C4 certificate indicates that the entire system is complete and fully operational.

Current daily production has now matched pre-expansion levels, as planned, and the plant will be ramped up over the next three months to achieve continuous design throughput.

Uis Development Strategy

The Company is developing its business aspirations in Namibia through expansion of its mineral resource base, expansion of both production volume and product portfolio, and a strategic focus on supplying metals to the technology and renewable energy sectors.

The Uis Mine is AfriTin's flagship project and underpins its development strategy. The ore mined at Uis contains additional commodities in addition to tin, including lithium and tantalum. An infill exploration programme is currently in progress, aiming to improve the geological confidence of the present lithium and tantalum mineral resource estimate.

The existing plant processing circuits extract a high-quality tin concentrate. The Company has initiated a further expansion of the current plant to produce a saleable tantalum concentrate. In addition, successful bench scale tests for the production of a lithium concentrate will be followed by the construction of a lithium pilot plant at the mine site.

The increased plant throughput resulting from the Project is also expected to benefit the ultimate production of lithium and tantalum by-products, since these minerals are present in the same ore stream as tin. AfriTin is investigating the suitability of sensor-based ore sorting which has the potential to further expand the throughput of ore at Uis by a factor of two to three times.

The Company will provide an update on its Uis development programme in due course.

 

* The Company's Financial Year runs from March to February. All reference to quarters applies to the financial year reporting period, unless stated otherwise.

AfriTin Mining Limited

+27 (11) 268 6555

Anthony Viljoen, CEO

Nominated Adviser 

+44 (0) 207 220 1666

WH Ireland Limited

Katy Mitchell

Corporate Advisor and Joint Broker

H&P Advisory Limited

Andrew Chubb

Jay Ashfield

Nilesh Patel

+44 (0) 20 7907 8500

Stifel Nicolaus Europe Limited

Ashton Clanfield

Callum Stewart

+44 (0) 20 7710 7600

Tavistock Financial PR (United Kingdom)

+44 (0) 207 920 3150

Emily Moss

Catherine Drummond

Adam Baynes

 

About AfriTin Mining Limited

Notes to Editors

AfriTin Mining Limited is a London-listed technology metals mining company with a vision to create a portfolio of globally significant, conflict-free, producing and exploration assets. The Company's flagship asset is the Uis Tin Mine in Namibia, formerly the world's largest hard-rock open cast tin mine.

AfriTin is managed by an experienced board of directors and management team with a current strategy to ramp-up production at the Uis Mine in Namibia to more than 10,000 tonnes of tin concentrate and 350,000 tonnes of lithium concentrate in a Phase 2 expansion, having reached Phase 1 commercial production in 2020. The Company strives to capitalise on the solid supply/demand fundamentals of tin and lithium by developing a critical mass of resource inventory, achieving production in the near term and further scaling production by consolidating assets in Africa.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCBKABQPBDDADK
Date   Source Headline
27th May 20267:00 amRNSUis Financing & Lithium Ridge Drilling Complete
8th May 20269:45 amRNSNotification of Major Holdings
5th May 20267:00 amRNSSecond Batch of Lithium Ridge Drill Results
29th Apr 20268:31 amRNSNotification of Major Holdings
29th Apr 20267:00 amRNSAmendment of Convertible Loan Notes
24th Apr 20262:09 pmRNSNotification of Major Holdings
23rd Apr 20267:08 amRNS-RUpdate: Investor Presentation via IMC
20th Apr 20267:00 amRNSStrategic Equity Placement To Accelerate Growth
13th Apr 20267:00 amRNSPositive Tungsten Test Results At Brandberg West
26th Mar 20267:00 amRNSBusiness Update For Period Ended 28 February 2026
3rd Mar 20264:03 pmRNSEmployee Incentive Scheme Update
24th Feb 20267:00 amRNSThaisarco Strengthens Relationship with Andrada
10th Feb 20262:40 pmRNSEIB Partnership for Uis Mine Feasibility Study
9th Feb 20267:00 amRNSHigh-grade initial drill results at Lithium Ridge
4th Feb 20267:00 amRNSACAM Transaction Update
26th Jan 20267:00 amRNSLithium Ridge Exploration Update
21st Jan 20267:00 amRNSPartnership with ACAM to develop Brandberg West
19th Jan 202611:00 amRNSOrange Trust Loan Conversion to Equity
17th Dec 20257:00 amRNSQ3 Operational Update For Period End 30 Nov 2025
1st Dec 202510:35 amRNSNotification of Major Holdings
27th Nov 20257:00 amRNSInterim Results for Six Months Ended 31 Aug 2025
7th Nov 20257:00 amRNS-RPublication of 2025 Sustainability Report
24th Oct 20255:26 pmRNSNotification of Major Holdings
24th Oct 20255:25 pmRNSNotification of Major Holdings
30th Sep 20252:00 pmRNSResults of the Annual General Meeting
29th Sep 20257:00 amRNSBoard Changes
15th Sep 20257:00 amRNSQ2 Operational Update For Period Ended 31 Aug 2025
3rd Sep 20257:00 amRNSExploration Drilling Commences at Lithium Ridge
29th Aug 20257:00 amRNSAudited Financial Results For Year End 28 Feb 2025
21st Aug 20257:00 amRNSAndrada accelerates growth of its tin production
15th Aug 20257:00 amRNSIssuance of Shares & Total Voting Rights
27th Jun 20257:00 amRNSResults of strategic Subscription & Placing
26th Jun 20257:00 amRNSProposed Strategic Subscription and Placing
19th Jun 20252:00 pmRNSNotification of Major Holdings
17th Jun 20257:00 amRNSAndrada Secures High-Grade Tin Feedstock
6th Jun 20257:00 amRNSOperational Update For Period Ended 31 May 2025
22nd May 202511:28 amRNSChange of Registered Address
10th Apr 20257:00 amRNSUis Exploration Drilling Results
31st Mar 20257:00 amRNSFY Operational Update For Period Ended 28 Feb 2025
11th Mar 202512:59 pmRNSNotification of Major Holdings
7th Mar 202512:41 pmRNSNotification of Major Holdings
4th Mar 20254:51 pmRNSDirector/PDMR Shareholding
28th Feb 20257:00 amRNSSQM earn-in agreement receives NaCC Approval
21st Feb 20252:17 pmRNSEmployee Incentive Scheme Update & Issue of Shares
14th Feb 202512:20 pmRNSNotification of Major Holdings
12th Feb 20257:00 amRNSOrange Trust Funding
6th Feb 20257:00 amRNSMineral Resource Update at Uis
20th Dec 20247:00 amRNSQ3 Operational Update for Period Ended 30 Nov 24
28th Nov 20247:00 amRNSUnaudited Interim Results 6 Months Ended 31/08/24
20th Nov 20247:00 amRNSPublication of 2024 Sustainability Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.