To look forward to1 Sep 2023 10:44
While the shareprice is in the doldrums. Until Horizonte announce otherwise, it is on plan and on budget and this is what we've got coming up:
End of Q3 (1 month from now): many construction items complete. Namely (from the August presentation, which is unlikely to be out of date): Manufacturing, Water Dam, Civil Works, 230kv Power LIne, 230kv Main Substation, Resettlement.
Q4 (1-4 months): Araguaia 2 DFS is published. With or without financing plan.
End of Q4 (4 months from now): Construction is complete: Environment, Construction, EM Erection, Water Pipeline.
So a roughly 2 year build window draws to a close in the next 1-4 months and in parallel we get a plan, with detailed numbers, for the next stage of mine development (Araguaia 2).
Lots to be positive about and all this in a relatively short timeframe now. GLA