RE: Irish Offshore Operators Associatio18 Apr 2019 21:34
Me, I'm heading out to one of Jupiter's moons. Lol.
Got in touch with Dccae today. They replied, very promptly, thus:
"Consents have to go through a series of assessments as follows
(1) 30 day public consultation published on website with associated environmental documents
(2)EIA screening/assessment of EIAR; decision by the Environment Advisory Unit
(3)AA screening/assessment of Stage IIAA; decision by the Environment Advisory Unit
(4) After all considerations under the EIA and Birds and Habitats are completed by out by the Environment Advisory Unit, the proposals are considered by the Minister of State who decides whether to grant the consent (with conditions attached), if it is considered appropriate."
So, given that 1 has now concluded, and assuming An Taisce have not whined (no mention of doing so on their website) I guess we are in stages 2&3. They must have done these last time round, so shouldn't be too arduous to recycle the paperwork one would hope, and now waiting on stage 4, when the Minister returns from his Easter hols.