RE: Please, please, please....30 Nov 2022 22:30
Stock piled ore for WK was up to interim date 30th of June will be interesting to know the full year quantity with Platinum price now over $1000 oz since end of Sept results at $850?
DFS completion pending
Monchetundra Definitive Feasibility Study being progressed for completion by the end of 2022.
· Metallurgical testwork reports now available for compilation into the larger DFS report. New metallurgical study by SGS, Mekhanobr-St Petersburg, LIMS and Gipronickel (Norilsk Nickel's engineering arm) suggests grades, recoveries and flowsheet unchanged from the 2016 feasibility study.
· Rock mechanics studies and Hydro/Geotech drilling now complete for West Nittis and Loipishnune open pits.
· Recalculation of Monchetundra project resources and pit outlines, reflecting metal price movement since the feasibility study, for submission as a necessary component of the DFS.
· Work continues on assessment of the NKT Project, contained within Eurasia's 80% Flanks exploration license adjacent the Monchetundra (West Nittis and Loipishnune) mining license, as a standalone project or as a project combined with Monchetundra deposits.