RE: Is the total greater than the sum of the parts..?8 Jun 2023 11:58
That to me is the interesting bit contractually. How does noble cover that in the contract? At what point does HE1 have to release the drill? When it's done? By a specific data or after a number of days - even if it isn't finished?
So 6 weeks to transport to border
2 weeks to off boat, get rig to location, build and make it drill ready and then spud (seems optimistic to me)
2 weeks to drill if there are no issues at all - also optimistic
I don't see any room for error for noble. Considering HE1 is first we might expect more comms - at least an operational update.