RE: GatewatchMedia interview with RP5 Apr 2026 10:54
Lots of familiar stuff but more insight into project timeline that was of interest. I don’t think this was particularly clear but this is what I got out of it.
- Rig 12 is getting re-tooled presently, preparing rig
- From 1st August equipment being moved to Montreal, ship is contracted for 30days and will leave Montreal on 12th September, sail to Nuuk, pickup other equipment, before onto beach disembarkation. There are two ships, not clear if they will leave together or separately.
- OPW-1 to be drilled in October
- 30 day drill, results around Oct/nov
- royalties paid to Greenland. Will pay Greenland 3.75% royalties when GLND reach 35% net profit, then up to maximum 15% royalties when GLND reach 55% net profit.
- Development drills will follow successful drill of OPW-1 (100’s of development drills will follow)
- Stampede, drill first two wells then review will take place.