RE: AGM Date4 Jun 2021 09:51
Negatives
Smellyben still here posting even though his predictions of imminent doom shown to be rubbish.
New mining contractor possibly slowed things down by a week or two
Positives
New mining contractor better deal.
“for full Project launch after the Company's Annual General Meeting, which is expected to be convened in due course for 30 June 2021. The Company remains on track to commence Project commissioning in late 2022 and to reach full production by mid-2023, in line with previous guidance.”
“updated detailed Project development and production plan. Whilst final approval of this updated plan is awaited as a condition precedent of the Project financing, TKGM has exchanged formal confirmations with the licencing authority regarding TKGM's commitment to honour the already outlined Project timetable;” would have to re jig it due to new mining contractor but commitment to honour timetable suggest any delay was minimal.
“procurement any time from July 2021;” suggests deal done after AGM”
“early works programme with principal process design and construction contractor, Lycopodium Limited, has commenced this month”
“Responses are up to date in respect of the senior lenders' due diligence requirements for credit approval. The timetable for Project finance remains for execution of detailed documentation as soon as possible after the KEFI AGM on 30 June 2021,”
“· 150 local personnel have been employed to prepare new host lands. TKGM have commenced compensation procedures”
“starter homes have been fabricated and are being delivered to site for assembly.”