Capex Kraken page 27229 Oct 2018 22:29
Hi E121
The capex payments I refered to in prospect is found on page 272/273
Guess the subsea work is paid later but drilling rig daily payment
EnQuest Heather has also entered into a separate contract with Technip in respect of drill
centre 4, with an original contract price of £30,310,986. Such contract price has already
increased due to variations and is now £32,526,326. Under the arrangements, the
payment of EnQuest’s equity share (70.5 per cent.) of all invoices will be deferred and a rate
of 7 per cent. per annum applied on such deferred amounts. The deferred amounts shall be
paid in six monthly instalments, with the first such payment being due on the date falling
nine months after completion of the work, with such completion expected to occur around
15 September 2018.
(vii) Contract for the provision of Transocean Leader
EnQuest Heather is party to a contract dated 29 September 2014 with Transocean Drilling
U.K. Limited (“Transocean”) in relation to the provision of the Transocean Leader drilling
unit. The contract has since been amended by amendment agreement to reduce the term of
the contract and the applicable suite of operating rates (see paragraph 18.4(c) of this Part 11
(“Additional Information”) for details of the amendment agreements). The remaining scope
of work under the contract comprises the workover of three wells at Alma and drilling and
completion of four wells at Kraken. The remuneration to be paid to Transocean includes an
operating rate of $135,000 per day payable by EnQuest Heather in respect of the Alma
workovers and $160,000 per day in respect of Kraken drilling (together with a bonus-malus
scheme based on rig performance). This daily operating rate is payable if the drilling unit is,
among other things, anchored on location and ready to start the work. Lower rates apply in
certain circumstances, including where Transocean is unable to proceed with the work
because of adverse sea or weather conditions or force majeure.
See also paragraph 18.4(c) of this Part 11 (“Additional Information”) on the deferral
arrangement around the consideration payable to Transocean.