RE: CONVICTION BUY - BARGAIN OF THE CENTURY !30 May 2021 00:31
OptimisticVic, yes production costs were up on Q1 but as Faramog has said this was due to 35 days lost production due to a planned 35 day maintenance shutdown. As can be seen below this significantly reduced production at Vametco in Q1.
However the company has to pay certain fixed costs, irrespective of production. If production is low (as it was) then unit cost of production will be higher. Hence the increased cost of production reported.
The good news is that they have reported production ramping up to normal levels since period end and looking forward are anticipating production costs back down to $20 to $21.30 per kgV.
So when you point out that Libero didn’t mention rising costs (actually they aren’t rising, they were higher in Q1 for reasons discussed above) in fairness you failed to mention the context, which I would argue could be very misleading.
Here are the relevant paragraphs from the Q1 Update. It’s all explained clearly:
“Q1 2021 production of 395 mtV was 40 per cent below Q1 2020 (Q1 2020: 660 mtV) and 44 per cent below Q4 2020 (Q4 2020: 703 mtV) due to lower production as a result of the planned 35-day maintenance shutdown during the quarter.
- A planned 35-day annual maintenance shutdown was undertaken during February and March 2021 to increase the reliability of critical segments of the plant. All work was completed on time and within budget.
Q1 2021 production cash cost of US$26.51/kgV was 37 per cent higher than Q1 2020 (Q1 2020: US$19.36/kgV) and 27 per cent higher than Q4 2020 (Q4 2020: US$20.90/kgV) due to lower volumes as a result of the planned maintenance shutdown and a stronger ZAR:USD exchange rate.
Vametco has not achieved consistent plant performance during the quarter. The 35-day maintenance shutdown is expected to improve the reliability and performance issues experienced in the past. However, various workstreams remain underway to enhance and maintain this stability, including maximizing safety and house-keeping initiatives, identifying and solving process system constraints and optimizing preventative maintenance programmes. Management continues to monitor plant performance and keep production guidance under review, however, it is currently anticipated that Vametco production will be towards the lower end of guidance of between 2,700 mtV and 2,850 mtV and the higher end of its production cash cost (C1) of between US$20.0/kgV and US$21.30/kgV (ZAR320/kgV and ZAR340/kg).”