RE: Worst case scenario14 Feb 2020 11:37
"On the routine fix at HH-2z. Anyone have any thoughts on timescale for this?"
Once the rig starts to turn up - 3 days to rig up, one day to clean up the well (i.e run in and run out) 1.5 days for the PLT (it has to be run slowly to get accurate data) - results available immediately.
Hopefully they will have a range of kit on site to cover the most likely solutions.
So another day to rig up a packer, run in place & test (1 day), flow the well to ensure there is no water - 2 days . Spot Cement the end of the hole 1 day. Run the pump and test 2 days...... rig down 2 days
13 days minimum - probably 2 weeks....... after the rig appears