RE: Matrix Observer30 Oct 2019 18:00
Hey adrianz
Just seen your message... I did translate the emissions agreement from yesterday, not much new info, below is a couple of bits...
---
2500 meters depth is planned in 2019-2022 years (the duration of the construction 120 days):
2019 - design wells E-151, E-154, E-155 and E-200 (transition 2020 year: 60 days in 2019, 60 days in 2020);
2020 g - the well design E-150, E-152, E-153, E-156 and E-157; 2021 g - the well design E-158, E-160, E-201, E-202 and E-203; 2022 - design of the well E-159, E-161, E-204 and E-205.
• Drilling will be carried out on schedule drilling rig ZJ-40 or
analog development wells will be machine UPA 60/80 or equivalent.
--
Structure of wells is...
Direction 508.0 0 20m - -
Conductor 339.7 0 400m - -
Technical column 244.5 0 1800m - -
Operational "Shank " 168.3 1700m 2500m - -
Other observations...
It does appear we are using the Mobile rig purchased (UPA 60/80) to set-up the 6xMJF wells for drilling down in winter.
Must admit, am focused a little deeper at the mo ;-} about another 2000m, come on CASP, make our Halloween..