Guercif biogenic gas development & timing8 Feb 2026 04:24
This is my opinion as to the timing of events that will lead to a closer accord between underlying value and market price. I will comment solely on the biogenic gas resource to the north and west of Guercif, extending down to about 1000m, which is the current focus of activity leading to commercialisation. The underlying value will only be acknowledged by the market once an Exploitation Concession is under way. What has to be done, and what is the time frame?
Four things need to be included in the application
* A definition of the resource under consideration – this will be in the ITR due for release by the end of the month.
* Proof that the resource is recoverable – MOU-6 results, I will deal with timing later.
* An agreed Field Development Plan – what work is necessary to get the gas out of the ground, process it and distribute it. This needs to be timed and costed. - currently under discussion with two parties for CNG and / or LNG. We believe the parties to be Afriquia Gaz and Vivo Energy respectively. Details of a finalised agreement may be released alongside the ITR, maybe later.
* How the FDP is to be executed and financed, and assurances on reliability of the sources of the necessary finance and expertise – the companies named, working most likely with Italfluid providing Flow Assurance and engineering, will not have any problems in meeting the necessary criteria.
Terms had been agreed with ONHYM for the exploration licence to be extended until 05/11/2026, the application has been submitted, and approval from the Ministries of Energy and Finance is awaited – RNS 17/12/25. PRD has a contractual, legal right, to this extension now that terms have been agreed. It may already have been granted – previously we have not been informed on similar approvals until well after the fact.
Timing of the Exploitation Concession. "Applications for concessions must be filed with the Ministry of Energy no later than three months prior to the expiry of the period of validity of the exploration permit pursuant to which the application is submitted." Source is the Hydrocarbon Code, S.22 of Decree 2-93-786, 03/11/93, amended by 2-99-210, 16/03/00, & Law 21-90 01/04/92, amended by 27-99, 15/02/00. This means all the above points must be included in a submission no later than 05 August 2026.
Therefore drilling + testing of MOU-6, which could take 10 days + 15 days, must start at the latest in early July. Agreement on the whole project, including financing the drilling and testing of MOU-6, must be earlier than that to ensure that all necessary materials are procured and on site. We know that some long lead time items are already on order.
The two key timing issues are the spud of MOU-6 in less than five months, and finalisation of a CNG and/or LNG agreement prior to that. Some of us have been more patient, and for a lot longer, than others, but I'm sure we all look forward to a return on our investment.