RE: PMO TRADING & OPERATIONS UPDATE10 Jan 2020 11:51
smokin88 11:27
I have added the releases of timeline from the 2019 WINX announcements to give a heads up of where we are right now with Charlie 1. We can see that PTD was not given until Ice Road was at least 10 days into construction. Makes sense I think, because (AOGCC) wouldn't want a false start.
So, all good thus far, IMHO.
Highlights 6th January 2019
• Ice road construction commenced for Winx-1 exploration well
• Winx-1 Permit to Drill (PTD) submitted
• Spud schedule for mid-late February 2019
Highlights 17th January 2019
• Permit to Drill (PTD) Approved for Winx-1 exploration well
• Ice road construction progressing well
o Rig mobilisation planned for early February
• Spud remains on schedule for mid-late February 2019
Western Leases – Winx-1 Exploration Well
The Permit to Drill for the Winx-1 exploration well was approved by the Alaska Oil and Gas Conservation Commission (AOGCC) on the 16th January (AK time).
This is the final major permit required for commencement of drilling.
Construction of the ~11-mile ice road to the Winx-1 exploration well location is proceeding as planned. Once complete, the ice pad will be constructed, and the rig will be mobilised for drilling.
Rig mobilisation is expected to commence in early February.
keefy