RE: For the naysayers4 Jun 2019 14:44
Shaddam, the 60million is what BA suggested... from a budgetary 15million for the DMS plant and the remainder to cover the other cost associated with getting into production. I cant comment on how wide of the mark that might be but budgetary in my game can be +/-50%.
I also cant comment on whether equipment lead times are 6 months.... 12months or more..... but why would I accept your assessment over what has been previously stated by the company, when you are pretty much always negative? Also.... I could see support being provided to design/size long lead items and procurement progressed up to purchase..... I just think actual purchases will require the permit and PFS first.... but maybe I am wrong and the supply chain would be willing to "take a punt".