RE: News.......2 Feb 2022 07:58
Suggins,
I think we both pick up on the same things! ;-) "WAS"
A couple of other bits, without posting too much text, but more in there.
"WAS boosted to a run rate of 1,000oz by the end of December 2021."
2nd Ball mill IS being refurbished to increase to 1,500oz pm :-)
"To boost production from the current level will require the mill to be shut down for six weeks to install a second ball mill which is currently being refurbished in Nairobi. During this period, mining would not be stopped as ROM would be stockpiled, waiting for the processing plant to recommence operations having been upgraded to produce
1,500oz per month or 18,000oz per annum."
2022 estimate "This results in a profit for the year of £5.341 million and earnings per share of 0.286p."