Hamilton...it was supposed to start 2 weeks after the compressor arrived on site. It isn't on site yet but was due to be last month. Currently being worked on. I can't see production starting this year TBH
PJ ...all deliveries of PSA unit on site ... no mention yet of it fully installed ... I assume that is ongoing.
They are waiting on the compressor ... when that has arrived it's two weeks to production.
3 to 4 wells will be hpoked up ...awaiting workover rig for 4th well to test second formation. That will take a week or so then ot will be taken down and connected for production.
5th well yet to be started. Posdible offtake agreements soon.
It was DM who kept mentioning summer where as Bo said early to mid fall.
Never the less it is another slip but that's the way it goes.
I have time to wait a few more months which isn't huge it just means they won't achieve the start of company to producer im the 18 months (this month) that they were pushing for.