RE: At last30 Nov 2021 15:54
Yanis, I agree... it is somewhat of a relief to FINALLY get some sort of an update. However...
Looking at today's update, it's clear that ANGS has known for some time that things have slipped way beyond their most recently announced schedule - as can be seen from:-
a) the significantly revised dates of all that equipment which was meant to be onsite from October, and
b) the fact that they are only now just (!!!) tendering for the necessary groundworks... HUH?
Why oh why didn't they release this information sooner??? I mean, it was obvious from the random Twitter pix released a week or so back that no groundworks had taken place? So how come they only inform the market now?
The least surprising news in the RNS (as anyone with half a braincell had worked out) is that they're not going to start drilling the sidetrack on Jan 4th, despite the company having insisted it would only a month ago.
Well... if this latest much-revised schedule doesn't slip yet again, now that they've given up on the utterly unachievable sidetrack schedule, they might squeak first gas just within Q1 if nothing else goes wrong. Mid Feb is out of the question though, IMO.
(You know, it just shouldn't be that companies leave it till the very last minute to correct information that they themselves have recently issued, especially when everyone's already long worked out that their last update was over-optimistic nonsense. Still...)