Successful completion of Mintails' Mogale Gold DFS30 Jun 2022 08:58
This is showing on part of the PAF news feeds, all good !
https://uk.finance.yahoo.com/news/pan-african-resources-plc-successful-060000388.html
https://www.moneyweb.co.za/mny_sens/pan-african-resources-plc-pan-african-successfully-concludes-mintails-mogale-gold-definitive-feasibility-study-dfs/
"Activity Estimated date
Completion and finalisation of DFS Completed
Engineering optimisation activities June – August 2022
Detailed engineering study September 2022 – March 2023
Likely project commencement date September 2022
Funding package finalised October/November 2022
Environmental approvals March 2023
Construction commences April 2023
Commissioning July 2024 – December 2024"
Pan African is pleased to announce that the Company has successfully completed a DFS on the Mogale Gold Proprietary Limited (“Mogale Gold”) Tailings Storage Facilities (“TSFs”) that forms part of the Mintails Mining SA (Proprietary) Limited (“Mintails SA”) assets, situated near Krugersdorp to the west of Johannesburg, South Africa (the “Project”). The DFS was prepared by DRA Projects SA (Pty) Ltd (“DRA”), with reliance on specialist input from third parties for Mineral Resource and Mineral Reserve estimation, dump re-mining, tailings pumping and disposal and metallurgical test work. The parties have provided their consent for the release of the information contained in this announcement as far as it pertains to the results of the DFS.
HIGHLIGHTS FROM DFS
Significant production impact:
The Project has the potential to increase the Group’s gold production profile over the coming years, with re-mining of the Mogale Gold TSFs expected to add approximately 50koz/yr of production over its 13-year life of mine (LOM)
Equivalent to an increase >25% on Group’s current production
Compelling project economics:
Pre-tax NPV (at 9.5% real discount rate) of ZAR1,006 million (US$64,9 million), real ungeared IRR of 20.1% at US$1,750/oz and US$/ZAR:15.50.
Forecast AISC of ~US$914/oz and operating cost of ~ZAR78/t (~US$5/t at US$/ZAR:15.50) over the initial 13-year LOM
Construction capex:
~R2.5billion (US$161.3 million at US$/ZAR:15.50)
Payback:
Construction capital payback estimated within 3.5 years, post commissioning
Targeting production within 18-24 months from commencement of construction
Mineral reserve:
The Mogale Gold TSFs, which comprise various individual dams, contain a Probable Mineral Reserve of 123.6Mt of re-mineable material at a head grade of 0.29g/t for an estimated content of 1.14Moz gold
Further production upside:
Addition of Mintails SA’s Soweto Cluster resource has potential to extend LOM from 13 years to 21 years and further increase annual gold production
Proven technology:
Low unit cost hydro mining with low project execution risk at 800ktpm (thousand tons per month) carbon in leach (“CIL”) plant, similar to Pan African’s Elikhulu operation (currently processing ~1.2Mt per month)
Project funding: