SOU´s potential funding gap and shareholder dilution in 202519 Jun 2025 13:24
Cash at the end of March (£3.1 million) will barely be enough to cover G&A expenses until first gas sales.
There is a potential funding gap, as a result of converting the LNG rental contract to an EPC one.
The operator agreed to pay Italfluid (see March 17th press release):
-US$ 18 million following a payment schedule in line with the actual work progress, with staged payments through gas processing plant commissioning,
-US$ 7 million paid once the plant is fully commissioned
SOU will be responsible for 20% of that amount (US$ 5 million net to SOU).
I don´t know if US$ 9.5 million of past payments already made to Itafluid will be deducted from the US$ 18 million (the press release is not clear about that). If that´s the case, SOU´s net exposure should be reduced to US$ 3.2 million.
I´m sure that part of that obligation was paid before the end of March (hence the reduction in SOU´s cash position since end last year). But, because payments to Italfluid should be aligned with “actual work progress”, I suspect there are substantial payments to be made yet (likely no less than US$ 10-12 million, including the US$ 7 million due after commissioning). That´s US$ 2-2.4 million net to SOU.
The lowering cash balance since last December is likely to have happened not only to pay Italfluid, but also to cancel trade payables outstanding at Dec.
I suspect the conversion of the LNG rental agreement into an EPC contract (with the obvious consequence of an increase in pre first gas cost, and risk of further shareholder dilution) was decided by Managem. SOU´s management could do nothing about that.
Graham set up the LNG rental agreement as a means to reduce funding requirements before first gas. Thas was now reverted by Managem (in order to achieve a greater NPV), without giving any consideration to SOU´s current liquidity situation.
What other activities related to phase 1 are still awaiting conclusion, that will require more funding from SOU? Managem only carries SOU in relation to phase 2 expenditures. SOU should still fund 20% of phase 1 costs.
In the March 17th press release, management talked about the following activities still awaiting execution:
-procurement and delivery to site of the gas gathering system equipment
-completion of the installation of the gas gathering system and connection to the wells
The 2024 Annual report informed that the following significant activities are scheduled for 2025:
1. Clean up operation of wells TE-6 and TE-7
2. Connecting the wells to the mLNG plant
3. Delivery, installation and connection of mLNG plant processing packages
4. Commissioning of the mLNG plant
The Afriquia loan has been substantially fully drawn down at Dec 31. So SOU can´t use that loan to pay Italfluid or other payment obligations related to phase 1.
In addition to that, 2% of annual interest of the secured bonds should be paid in cash this year (equivalent to US$ 0.6 million per year).