Rigs etc24 May 2018 15:11
A80 already owned and recently upgraded. Ok for light interventions.
A100 on order locally and 2 months late on delivery according to the latest schedule. This will also be owned by Zen
Zj30-150 t under negotiation for hire, probably with crew to finish off z21, go back in z28 and maybe z3
Genesis-nemeses. Currently somewhat unproven, so far I cannot find anyone using them although there were 'good' reports onit somewhere. We are thankfully doing some kind of lease arrangement instead of diluting. It is due q4 and is earmarked for spudding new well once they have scratched their heads a bit longer, consulted the seismic and geology reports etc etc and come up with a promising target. The results of which are about 12m away from now. In any case, one can assume the 500 means 500t which is what is needed for deep drilling which again is a plus. Roxi/Casp have been arsing around since 2013 with inadequate equipment, I cannot wait 5 years for zen to get their act together for the same reasons and hope to you know who that this genesis machine will be up to the job in terms of reliability.
ZJ-30 needs to be super successfull very quickly. Hopefully 21 will not collapse and we will at least get an acceptable average out of it.
In the meantime a80 is dunking pumps in at revised depths and fingers crossed may set of a few fireworks downhole and re-perf some zones to up the flow rates.
A100 will also be available in another 6 weeks or so to start earning its keep.
6 months to treble production without buying a new asset... can't wait to see it. Anyone any good with a bowler hat, black stick with white bits on either end and a couple of rabbits..?
Back to the pool and the sun lounger for another day. Ohh well.