MT DFS progress1 Oct 2022 06:11
Is there anything to take from the change in wording from “submission in 2022” to “completion by the end of 2022” for the MT DFS?
I’m sure they’d previously mentioned something about November 2022 but I can’t find it at the minute.
1 Sept 2021; The Monchetundra Definitive Feasibility Study (DFS), contracted to CKE and EMR (both defined below), is in the final stages of its development further to the successful completion of geotechnical and other studies performed by Gipronickel (an engineering arm of Norilsk Nickel) as well as an audit by Wardell Armstrong International.
29 June 2022; Definitive Feasibility study on schedule for submission in 2022.
30 Sept 2022; Monchetundra Definitive Feasibility Study being progressed for completion by the end of 2022.