RE: Ntorya to Madimba Gas Pipeline7 Jul 2025 11:18
EE I would agree with you but need to point out that "construction has actually started" could well, yet, be quite some time. Originally as I understand it and, when the pipeline construction was due to complete in Q1 this year, the expectation was for NT2 to start to coincide with pipeline completion; the BoD not wanting to set up NT2 for production only then to have to wait months to be able to connect it to the pipeline. Now, we are told, pipeline completion not expected for 12 months! So does that mean that NT2 "workover" will not be started until pipeline completion is within touching distance? Similarly we know that NT1 workover is expected to follow CH1 as both projects will utilise the same rig. So the question is, will all three projects be executed in sequence or will NT2 be done in parallel with either CH1 or, more likely, NT1.
So if completion of the pipeline is not expected until 07.26 we could still be waiting until the turn of the year before operational activity starts.