RE: Rig movement12 Feb 2021 17:18
Not sure at all, unlike a rig move on a highway which can be tracked via Alaska511, hopefully we will see an Ops update in the next few days.
I look forward to that forward programme, snow road goes to Umiat.
"The Company is on schedule to spud the Merlin-1 well in late-February / early-March 2021, with drilling
and logging of the well anticipated to be completed by mid-March. Subject to positive results from the
Merlin-1 logging program, the Joint Venture expects to flow test the well for up to 10 days before
proceeding to the spudding of the Harrier-1 well in late March / early April 2021. It should be noted
that the drilling of the Harrier-1 well remains subject to scheduling, permitting and related government
approvals, as well as agreement between the Joint Venture parties on the forward programme, which
may be subject to change."