Vanchem Expansion5 Feb 2021 11:39
1/2
Morning everyone,
Here's a little theory I have, which I thought was best suited to the BMN BB. Mainly shared for fun and not absolutely critical to the investment case but if analysis here holds up, then perhaps I'll share outside of here.
Vanchem in 2020 ; "12M 2020 production of 990 mtV, in line with 2020 guidance of 960 mtV to 1,100 mtV."
Thats what Vanchem is on 1 kiln, without further expansion, no more no less.
From yesterdays update ;
"2021 production guidance and capital expenditure
Production guidance of between 1,400 mtV and 1,500 mtV 2021, an increase of between 41 per cent and 52 per cent relative to 2020 production."
From the 30th Nov 2020 Orion finance update ;
"Refurbishment of the third kiln for modular production increase leading to 2,600mtv per annum."
Firstly, lets assume that the emphasis was placed on kiln 1 meeting its 1,100 mtV upper limitations, meaning that it is purely the 3rd kiln that delivers the additional c. 1,500 mtV of production (because kiln 1 refurb wan't mentioned at that time, as those 'critical works,' have always been described as regulatory in their necessity and not designed to add production).
We know that kiln 3 will be commissioned in H2 2021 and that process runs as follows ;
"Kiln-3 is expected to be commissioned in H2 2021, resulting in a modular production increase, subsequent to which, kiln-1 will be taken offline for refurbishment. Scoping of the refurbishment of other areas of the plant to cater for the kiln-3 refurbishment is in progress."
If kiln 1 is planned to run at normal output up until at least the end of H1, then Vanchem at that advertised rate (1,100 mtV FY), at maximum rate, produces 550 mtV in H1.
Thus leaving 950 mtV for H2.
To hit that 950 mtV fig, knowing that kiln 3 has a maximum output of 125 mtV per month (1,500/12 =), then both kilns have to complete the year in production.
That's because Kiln 3 at 6 x 125mtV = 750 mtV + 550 mtV = (just) 1,300 mtV.
Lets now go further down the rabbit hole.
A completion of the commissioning of kiln 3 by close of August and a 1 month shutdown on kiln 1, would deliver the following.
H1 = 550 mtV
Kiln 1 H2 = 5 x 92 mtV (1,100/12 =) = 458 mtV
Kiln 3 H2 full output from Sept = 4 x 125 mtV = 500 mtV
Total = 1,508 mtV
Almost bang on upper guidance.
For kiln 3 to replace kiln 1, it has to deliver full capacity or they fall short of that 1,500 mtV. Simple as that.
If kiln 1 is off line longer than 1 month, then they fall short of 1,500 mtV.
If kiln 3 comes on line later than end of August, then they fall short of 1,500 mtV.
Yes there is a guidance range but I would suspect this is more associated with standard production fluctuations on kiln 1 and not dates moving on kiln 3.
If the theory holds water, then what that says is that the plan is that kiln 3 hits the ground running in Sept at full capacity and that both kilns are back on line shortly afterwards.