RE: Back to Basics15 Jan 2023 12:01
@legalWold & ID78 Thanks for the Feedback ... but ID78 nailed it with ... "Back to basics. Mine ore, produce gold and sell it. 1000oz a month. Report honestly and keep us informed." So putting this together ...
(my post 13-Jan-22)
1) Solid dependable Admin and Quarterly reporting ... on time, every time
2) Stick to 500oz/month and get EXISTING plant 1+2+3 & mine up to 1koz/month ASAP ... weeks not months
3) Get updated Kilimapesa MRE out NOW ... lets not wait any longer as 6 months drilling without news is more than enough & it will always be a work in progress
4) Confirm Philoro $3m funding position ... provide some clarity good or bad lets hear it please
5) CLN position ... what is the plan EXACTLY
IMHO as comms have been so poor we do not know what plant is currently operational or what mine output is available to feed it as we have had no operational update since 30-Jun-22. So putting this together attainable Production Targets & how GCAT could do it:
> Target minimum 500oz/month: NO upgrades needed just feed existing plant 1 and/or plant 1&2!
A1) Plant 1 CIL only = 10kt *2.5g/t *80%/31.1 = 643oz ... as CIL = 80% recovery assuming Plant 2 offline
A2) Plant 1 & 2 = 10kt *2.5g/t *91%/31.1 = 732oz ... current 500tpd mill = 10kt @Q1 @80% CIL & 50% Tailings recovery
> Target minimum 1,000oz/month: NO upgrades needed !
B1) Plant 3 HL only = 35kt *1.72g/t *53%/31.1 = 1,025oz ... assuming 1 month cook cycle & Q2 @53% pilot plant recovery
B2) Plant 1 and Plant 3 = A1+B1 = 1,668oz
B3) Plant 1, 2 and Plant 3 = A2+B1 = 1,757oz
> Target minimum 2,000oz/month ... using original Plant 1&2 capacity, New Plant 4 & Q1/2 grades and %recoveries:
Plant 1 & 2 = 10kt *2.5g/t *91%/31.1 = 732oz ... 500tpd mill over 20 days= 10kt @Q1 @80% CIL & 50% Tailings recovery
Plant 3 HL = 35kt *1.72g/t *53%/31.1 = 342oz ... assuming 3 month cook cycle & Q2 @53% pilot plant recovery
Plant 4 HL = 120kt/3 *1.72g/t *53%/31.1 = 1,172oz ... assuming 3 month cook cycle & Q2 @53% pilot plant recovery
Summary = 2,246oz/month using non-upgraded plant capacity & Q1/2'22 %recovery data
> Target minimum 2,000oz/month ... UPGRADED Plant 1&2 capacity, New Plant 4 & Q1/2 grades and %recoveries:
Plant 1 & 2 = 20kt *2.5g/t *91%/31.1 = 1,464oz ... 1ktpd mill over 20 days= 20kt @Q1 @80% CIL & 50% Tailings recovery
Plant 3 HL = 35kt *1.72g/t *53%/31.1 = 342oz ... assuming 3 month cook cycle & Q2 @53% pilot plant recovery
Plant 4 HL = 120kt/3 *1.72g/t *53%/31.1 = 1,172oz ... assuming 3 month cook cycle & Q2 @53% pilot plant recovery
Summary = 2,978oz/month using upgraded plant capacity & Q1/2'22 %recovery data
To be clear IMHO 1koz/month can be achieved without upgrades but GCAT just need to chose to do so. GCAT do have options and need to make some quick choices & go Back To Basics.
Once funding has been secured & banked then Plant 1 & 2 can be upgraded and Plant 4 construction completed so 2koz/month can be targeted.
ATB APR