Financial Highlights:
· Loss for Period €527,985 (30 June 2022: loss of €448,652 and December 2022: loss of €792,263)
· Basic and diluted loss per share 0.0001 cent (30 June 2022: 0.0001 cent and 31 December 2022: €0.0002 cent)
· Net assets at 30 June 2023: €8,845,494 (30 June 2022: €9,191,466 and 31 December 2022: €8,618,024)
· Cash balances at 30 June 2023: €410,661 (30 June 2022: €1,158,053 and 31 December 2022: €145,197)
· Placing of new shares during Period raised €913,242 before expenses
Operational Highlights:
· Special Use Permit granted to Western Milling joint venture by Mineral County Commissioners
· Diamond core hole at OMCO Mine confirms extension to the OMCO vein
· Status of copper prospects upgraded by intensive field work and mapping
Post Period End:
· Western Milling Joint Venture: concrete laid and production due to start this year
· Placing of new shares raised €581,139 before expenses
· Signing of Western Milling Operating Agreement and Declaration of Earn-In
· Rhyolite Dome (Olympic Gold project) identified as potential gold-silver play
My Summary:
>GWMO now has circa Euro935k or £810k (assumes 10% finance cost E58k) (Cash E410k +E581k-E58K costs)
> Cash burn was E528k to Jun-23 or £460k including remaining JV costs, management and exploration
> Months available cash = circa 21 months from 1-Jul-23
> JV costs likely accounted for in Dec-23 period cash burn "December 2022: loss of €792,263" as E300k above normal burn rate
> Tailing access road has been built and available to dig out JORC "ore" for JV processing
>JV plant mill build well underway and RNS states "We are expecting to commence production of gold and silver concentrates during the second half, using the significant volumes of material on our claims and, in due course, material from third parties."
>OMCO tailings MRE "Inferred Resource 31,000 t at 1.6 g/t Au and 3.0 g/t Ag" or circa 1,600oz gold equivalent contained metal implying 820oz recoverable metal via gravity separation at stated 50% recovery rate. At $1,900 gold this implies $1.5m revenue or £1.3m revenue before JV processing costs
Looking good BH just need to ...
>Complete JV plant install & commissioning
>Secure licence to operate JV mill & plant
>Dig out some "ore" ready for JV processing
>Feedback on 2023 exploration programme drilling at OMCO and M2 copper prospect