RE: Prem30 Jun 2022 20:07
I liked the interview also, lots of information. I jotted some notes down for a fellow investor who couldn’t watch while at work. Pasted below.
Let’s see where we go from here, with the Chinese on his back and new hires coming maybe just maybe this is the time prem seriously delivers.
Happy to hear there will be 4 sorters also. These things are amazing bits of kit.
Notes:
Site work at Zulu commences 30 July
Contractors are already all at site
Plant construction timeline final delivery to site mid January
Most of plant onsite by end December, final component mid January
Power will be by generators but looking at Solar power
Water is at site from a dam, construction being looked at now, complete by December / jan
2 of the 4 sorters ready to ship from supplier (sensor based ore sorters)
Production by February and first shipment end of March
Road will be finished end of July
Updating markets on a monthly basis
Said he had suggested putting a camera up at Zulu to watch the progress
Nothing stops prem repaying the loan, in full at anytime early
At Zulu excess of 100 staff, construction, site prep and civil engineering. Survey for dam in progress. Internal team planned to grow, all before end of year. General manager hopefully next few months
Discount on li to investors as long as the dept is outstanding, wouldn’t give the amount of discount. A floor price has been set but wouldn’t say what that price was
Essay results, RUS. Says most of the testing has been re run and re checked due to anomalies. Says most of results are all in, soon to start releasing string of results
Drilling ongoing, will slow down at Zulu while building mine. Extension drilling could last 3-4 years