Clean up = Increased Production11 Sep 2019 13:38
Reading back on this update from Edison's latest report:
"Supportive Lancaster EPS start-up performance: The two producing Lancaster wells, 205/21a-6 and 205/21a-7Z, have benefited from longer clean-up periods and are producing at higher rates than seen during drill stem testing (DST), with improved reservoir characteristics. This performance uplift has resulted in Hurricane increasing its target production guidance envelope to an upper target of 20kbd from 2020, with the base case remaining at 17kbd (net of operational downtime). A minimum period of production of six to 12 months is now required to prove long-term production performance.
If we look at current DST with Lincoln is it reasonable to assume they may be spending more time on clean up here looking for similar outcomes or just bad guesswork on my part?