RE: EIA timetable16 Apr 2021 20:12
SAVs only mistake was to take the 1st answered questions as given (i.e. not expecting a second roudn of questions) and sang like a canary about 20 days for APA to respond. Firstly, it was just hitting Xmas and pandemic went up a notch in Portugal so no way were they turnign that around in 20 days......then they asked more questions. SAV is not in control of this, to suggest otherwise is folly. Then to answer questions they proabbly had to do new studies or change the location of the processing plant for example, you can't fire a quick email back with the answers. And I would rather SAV pour over each question and answer it within an inch of its life to ensure to is accepted than a 'nay we'll sort that, nowt to worry about' flippant response. After they have submitted then the Portuguese in full lockdown ain't going to turn it around in 20 days, on top of this there are many things going on in the shadows in Portugal and EU regards the grand battery plan that this is all an intergral part of.
So yeah i'm ****sssed it has taken this long but not a SAV time issue that can be pinned on them. This EIA conformity is an enormous step.....at one time we didn't even need to do one, 3 years later and a load of work later we are here.....all because of ESG requirements changing. If we get the DIA in August we are home anmd dry, regardless of the days required for Environmental Title. Get past the public and this is a home run, Portugal needs it to be and I hope the hard work in getting it 'public friendly' has been done up front by APA and SAV.