Pilot Phase Site Construction on Schedule

12 Jun 2024 07:00

RNS Number : 0852S
Sovereign Metals Limited
12 June 2024
 

NEWS RELEASE I 12 JUNE 2024

PILOT PHASE SITE CONSTRUCTION ON SCHEDULE

·

Kasiya's pilot mining and land rehabilitation program is progressing with site establishment on schedule

·

Mobile fleet is currently constructing the test pit, water storage pond and ore stockpile

·

Free-dig nature of soft saprolite ore confirms the ease of mining with no drilling or blasting required

·

Eight boreholes have been commissioned and are ready to supply the water storage pond

·

Key contractors and consultants across major disciplines have now been appointed

·

Empirical data generated from the Pilot Phase will assist in determining optimal project excavation, material handling, processing, backfilling and rehabilitation approaches

 

Classification 2.2: This announcement includes Inside Information

Figure 1: Pilot Phase site June 2024

Sovereign Metals Limited (ASX:SVM; AIM:SVML) (the Company or Sovereign) is pleased to announce that pilot site construction for the ongoing Pilot Mining and Land Rehabilitation Program (Pilot Phase) at the Kasiya Rutile-Graphite Project (Kasiya or Project) in Malawi is on schedule with groundworks underway.

Managing Director Frank Eagar commented: "This Pilot Phase is a step-change for Kasiya and demonstrates our ability to execute in Malawi. The early works are progressing as planned: on schedule and within budget. We are very pleased with the progress and specifically how the mobile fleet is performing in the soft saprolite ore, confirming our understanding of how simple mining, with no drilling or blasting required, will contribute to low operating costs."

The construction fleet is on-site with groundwork to excavate the water storage pond and construct the test areas currently underway. Site equipment is currently moving 5,000 cubic metres of earth daily. The fleet consists of four excavators, 20 trucks and a support fleet, including two bulldozers and a motor grader.

Figure 2: Dry mining stockpile area under construction

A perimeter fence around the 9.9-hectare pilot site has been erected to maintain the necessary health and safety standards. Sovereign's strategic investor, Rio Tinto, is assisting with establishing health and safety protocols and implementation on a day-to-day basis.

Eight water extraction boreholes have been commissioned and are delivering water to the site, with the filling of the water storage pond to follow. The temporary water storage pond is currently being excavated and will be sealed using natural clay from excavated material. This will minimise the use of conventional plastic lining at the pilot site in accordance with Sovereign's objectives for a sustainable operation at Kasiya.

 

Figure 3: Pilot Phase fleet and equipment excavating the water storage pond

Key contractors and consultants have been appointed across all major disciplines essential for the Pilot Phase.

· Multinational engineering and construction company Mota Engil Group has been appointed to perform all excavation required for site establishment, the water storage pond, the test pit, seven rehabilitation pits as per Figure 4, site closure and general rehabilitation of the site. Mota Engil Group operates in 21 countries with 54,000 employees and is ranked among the world's largest construction companies.

· South Africa-based consultancy Fraser Alexander (Pty) Ltd has been contracted to complete the hydraulic mining phase.

· Backfill, storage and tailings management will be assessed by South African residue management solutions consultancy Epoch Resources (Pty) Ltd, which has a 25-year track record, including working for Randgold Resources Plc, Xstrata Plc and Anglo American Platinum Limited.

· International engineering company DRA Global Limited has been appointed to oversee and provide engineering and design services required during the Pilot Phase.

The Pilot Phase is being undertaken on a 9.9-hectare site and will include the following activities:

1. Test Pit: A test pit of 120m by 110m will be excavated to a depth of 20m, allowing optimisation of hydraulic and dry mining excavation methods.

2. Stockpiles: The excavated material will be temporarily stored in 4 stockpiles, namely all dry mining material, wet slimes (in a pond) and two sizes of sand fractions from the hydraulic mining.

3. Backfilling and Grading: The material will be placed back into the pit, and all areas will be graded.

4. Rehabilitation Demonstration: Sovereign will construct eight small rehabilitation demonstration pits covering a combined area of 100m by 130m. These will be used for water storage, excavated material storage, and demonstration of multiple rehabilitation approaches.

5. Temporary Laydown Areas: Four areas will be used as temporary laydown areas, offices, and associated infrastructure.

6. Communication: The Pilot Phase will be an educational opportunity for Project stakeholders. Sovereign will undertake a series of stakeholder visits and consultations for this purpose.

Sovereign's objective is to restore land after mining to conditions that achieve the same or better agricultural yields than existing land uses and crop yields. The Pilot Phase will demonstrate to local communities the successful rehabilitation of land for agricultural use post-mining; land rehabilitation will form an integral component of the ongoing optimisation study. Results will also allow Sovereign to determine optimal excavation and backfill approaches, providing critical information for the upcoming Definitive Feasibility Study.

Kasiya is the world's largest natural rutile deposit and the second-largest flake graphite deposit. Sovereign aims to develop a low-CO2 footprint and sustainable operation to supply highly sought-after natural rutile and natural graphite to the global markets.

Figure 4: Planned site layout

 

ENQUIRIES

Frank Eagar (South Africa/Malawi)Managing Director

+61(8) 9322 6322

Sam Cordin (Perth)+61(8) 9322 6322

Sapan Ghai (London)+44 207 478 3900

 

Nominated Adviser on AIM and Joint Broker

 

SP Angel Corporate Finance LLP

+44 20 3470 0470

Ewan Leggat

Charlie Bouverat

 

 

Joint Brokers

 

Stifel

+44 20 7710 7600

Varun Talwar

 

Ashton Clanfield

 

 

 

Berenberg

+44 20 3207 7800

Matthew Armitt

 

Jennifer Lee

 

 

 

Buchanan

+ 44 20 7466 5000

Forward Looking Statement

This release may include forward-looking statements, which may be identified by words such as "expects", "anticipates", "believes", "projects", "plans", and similar expressions. These forward-looking statements are based on Sovereign's expectations and beliefs concerning future events. Forward looking statements are necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Sovereign, which could cause actual results to differ materially from such statements. There can be no assurance that forward-looking statements will prove to be correct. Sovereign makes no undertaking to subsequently update or revise the forward-looking statements made in this release, to reflect the circumstances or events after the date of that release.

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ('MAR'). Upon the publication of this announcement via Regulatory Information Service ('RIS'), this inside information is now considered to be in the public domain.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCUUSARSNUNARR
Date   Source Headline
1st Feb 20247:00 amRNSExtensions To Rutile & Graphite Mineralisation
31st Jan 20247:00 amRNSDecember 2023 Quarterly Report
23rd Jan 20247:00 amRNSExperienced Social Specialist Firm Appointed
27th Nov 20237:00 amRNSCompany Presentation
24th Nov 20237:00 amRNSResult of AGM
2nd Nov 20237:00 amRNSLithium-Ion Battery Graphite Program Upscaled
31st Oct 20237:00 amRNSSeptember 2023 Quarterly Report
20th Oct 20237:00 amRNSInitial Director’s Interest Notice
18th Oct 20237:00 amRNSNotice of AGM
16th Oct 20237:00 amRNSKey Mgmt Appointments for Development at Kasiya
11th Oct 20237:00 amRNSKasiya Pre-Feasibility Study Results Presentation
29th Sep 20237:00 amRNSAnnual Report 2023
29th Sep 20237:00 amRNSIssue of Shares and AGM Date
28th Sep 20237:00 amRNSKasiya Pre-Feasibility Study Results
25th Aug 20237:00 amRNSIssue of Shares
23rd Aug 20237:00 amRNSResults of Meeting
16th Aug 20238:24 amRNSNotice of Change of Interest of Substantial Holder
28th Jul 202310:49 amRNSNotice of Change of Interest of Substantial Holder
28th Jul 20237:00 amRNSJune 2023 Quarterly Report
25th Jul 202311:01 amRNSNotice of Substantial Holder
21st Jul 20237:00 amRNSNotice of GM
17th Jul 20237:00 amRNSRio to Invest $40.4m to Become Strategic Investor
21st Jun 20237:00 amRNSChange of AIM Nominated Adviser
20th Jun 20237:00 amRNSGraphite Bulk Sample Operations Commenced
8th Jun 20237:00 amRNSKasiya Graphite for use in Lithium ion Batteries
6th Jun 20237:00 amRNSLapse of Performance Rights
16th May 20237:00 amRNSExpiry of Unlisted Options
28th Apr 20237:00 amRNSMarch 2023 Quarterly Report
5th Apr 20237:00 amRNSKasiya Indicated Resource Increased By Over 80%
20th Mar 20237:00 amRNSDemerger Timetable
17th Mar 20237:00 amRNSResult of Meeting
15th Mar 20237:00 amRNSKasiya's Graphite Warming Potential Amongst Lowest
14th Mar 20237:00 amRNSHalf-year Report
15th Feb 20237:00 amRNSNotice of General Meeting
6th Feb 20237:00 amRNSCompany Presentation
31st Jan 20237:00 amRNSDecember 2022 Quarterly Report
30th Jan 20238:07 amRNSKasiya Resource Infill Drilling Results
30th Jan 20238:01 amRNSASX Trading Halt Update
27th Jan 20239:18 amRNSASX Trading Halt
13th Jan 20237:00 amRNSIssue of Unlisted Performance Rights
7th Dec 20227:00 amRNSSovereign to Demerge Standalone Graphite Projects
23rd Nov 20227:00 amRNSChange of Director’s Interest Notice x4
21st Nov 20224:40 pmRNSSecond Price Monitoring Extn
21st Nov 20224:36 pmRNSPrice Monitoring Extension
18th Nov 20227:00 amRNSResult of AGM
17th Nov 20227:00 amRNSTZMI Congress Presentation
2nd Nov 20227:00 amRNSRutile Offtake MoU with Chemours
31st Oct 20227:00 amRNSSeptember 2022 Quarterly Report
26th Oct 20227:00 amRNSAC Drilling Confirms Pit Expansion at Depth
30th Sep 20227:12 amRNSNotice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.