Leigh Creek Copper Mine Work Programme Commenced

13 Jun 2018 07:00

RNS Number : 1709R
Strategic Minerals PLC
13 June 2018
 

Market Abuse Regulation (MAR) Disclosure

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

 

13 June 2018

 

Strategic Minerals plc

("Strategic Minerals", "SML" or the "Company")

Leigh Creek Copper Mine Work Programme Commenced

Strategic Minerals plc (AIM: SML; USOTC: SMCDY), a producing mineral company actively developing projects prospective for battery materials, is pleased to inform the market that it has commenced the technical assessment of the Leigh Creek Copper Mine ("LCCM") with the formation of a highly experienced study team. The proposed work programme is expected to lead to the commencement of copper production around mid-2019.

 

Highlights

· Formation of highly experienced technical team with extensive experience in South Australian copper projects

· Drilling of existing heap leach pads due to commence in second half of June

· Drilling of Paltridge North, Lynda and Lorna Doone deposits for metallurgical samples due to commence in July

· Exploration drilling for potential resource extension between the Lynda and Lorna Doone deposits due to commence in July

 

Commenting, John Peters, Managing Director of Strategic Minerals, said:

"The SML Board is thrilled with the highly skilled and experienced technical team that has been assembled to progress this exciting copper project. The team has over 100 years' combined experience, much of which is in South Australian copper geology and processing. The quality of the team provides a superb foundation from which to review potential development and processing options and settle on a work programme that will minimise risk and maximise shareholder returns.

"The SML Management and Board are closely following the progress at LCCM and have established reporting arrangements and management policies to closely monitor developments and to ensure delivery of sustainable operations mid-2019.

"The work programme and the development of LCCM are both expected to be fully funded from the Company's existing cash flows, and we look forward to updating the market on the progress of the work programme during the September quarter."

 

LCCM Work Programme

As announced by SML on 26 April 2018, a work programme was committed to by the Company to assess low risk processing options for the Mountain of Light and Lyndhurst projects, which collectively form the LCCM project, as well as looking for opportunities to increase the existing resource base.

This work programme is aimed to commence sustainable production from existing heap leach pads in mid-2019.

Initial work activities include:

· Drill testing and assaying of the existing heap leach pads

· Volume determination of existing heap leach pads

· Diamond drilling of Paltridge North, Lynda and Lorna Doone deposits for subsequent metallurgical testwork to determine the most appropriate metallurgical process to increase recoveries

· Exploration drilling to test for possible copper oxide deposit extensions between the Lynda and Lorna Doone deposits

 

LCCM Project Team

The work programme at LCCM has commenced with the formation of a world class technical team in project management, geology and metallurgy which has a combined experience of over 100 years, with much of it in South Australian copper deposits.

Jonathon Trewartha, Project Manager

Jonathon is a highly experienced Mining Engineer and Project Manager with over 28 years' experience in South Australian copper and international base metal projects. This includes project management with Golder Associates, Terramin and on the Olympic Dam copper-gold project. Jonathon was the Managing Director of Resilience Mining Australia Ltd., the previous owners of the LCCM project, and has formed a strong foundation for the project to move forward into production.

Jonathon is also a guest lecturer at the University of Adelaide.

David Larsen, Geology Manager

David has over 35 years' experience as a geologist working in the mining and exploration industries throughout Australia, the Pacific and Mongolia. He has worked across a wide variety of commodities including gold, base metals and iron ore, and has done so in both open pit and underground operations. His areas of expertise include near-mine exploration, feasibility studies, JORC and NI43-101 compliant resource estimation and reporting, operations establishment, due diligence and quality improvement.

Arthur Hunt, Metallurgical Manager

Arthur is a metallurgist and operations manager with 34 years' experience in metallurgy, project and operations management. Arthur is well regarded in the industry having held key roles in South Australia including: Uranium One - Mine Manager; CuDeco Ltd - Technical Manager; OZ Minerals - Processing and Maintenance Manager - Prominent Hill and WMC Olympic Dam - General Manager Smelter.

 

For further information, please contact:

 

Strategic Minerals plc

 

 

+61 (0) 414 727 965

John Peters

Managing Director

www.strategicminerals.net

Follow Strategic Minerals on:

Vox Markets:

https://www.voxmarkets.co.uk/company/SML/

Twitter:

@SML_Minerals

LinkedIn:

https://www.linkedin.com/company/strategic-minerals-plc

SP Angel Corporate Finance LLP

+44 (0)20 3470 0470

Nominated Adviser and Broker

Ewan Leggat

Laura Harrison

Yellow Jersey PR

+44 (0)20 3735 8825 

Financial PR

Charles Goodwin

+44 (0)7747 788 221

Joe Burgess

+44 (0)7769 325 254

Henry Wilkinson

+44 (0)7951 402 336

 

 

Notes to Editors

Strategic Minerals Plc is an AIM-quoted, operating minerals company actively developing projects prospective for battery materials. It has an operation in the United States of America and development projects in the UK and Australia. The Company is focused on utilising its operating cash flows, along with capital raisings, to develop high quality projects aimed at supplying the metals and minerals being sought in the burgeoning electric vehicle/battery market.

In September 2011, Strategic Minerals acquired the Cobre magnetite tailings dam project in New Mexico, USA, a cash-generating asset, which it brought into production in 2012 and which continues to provide a revenue stream for the Company. This operating revenue stream is utilised to cover company overheads and invest in development projects orientated to supplying the burgeoning electric vehicle/battery market.

In January 2016, the portfolio was expanded with the acquisition of shares in Central Australian Rare Earths Pty Ltd, which holds tenements in Western Australia and the Northern Territory that are prospective for cobalt, gold, nickel sulphides and rare earth elements. The Company has since acquired all shares in Central Australian Rare Earths Pty Ltd.

In May 2016, an additional exploration asset was acquired when the Company entered into an agreement with New Age Exploration Limited to acquire up to 50% of the Redmoor Tin/Tungsten project in Cornwall, UK. This 50% acquisition was completed in February 2017 and a drilling programme completed in 2017 resulted in a significant upgrade of the resource.

In March 2018, the Company completed the acquisition of the Leigh Creek Copper Mine situated in the copper rich belt of South Australia and is currently working to bring this into operation in 2019.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLFMGMVKZNGRZM
Date   Source Headline
25th Apr 20167:29 amRNSUpdated Website
21st Apr 20167:00 amRNSPermit of Works application lodged for Hanns Camp
12th Apr 201611:57 amRNSChange of Registered Office
3rd Mar 20167:00 amRNSUpdate for the three months to 31 December 2015
1st Feb 20167:00 amRNSUpdate on Tatu Coal Mine Project
1st Feb 20167:00 amRNSTenement position in nickel sulphide area secured
22nd Dec 20158:27 amRNSConfirmation of Extension for Cobre Operations
16th Nov 20154:40 pmRNSSecond Price Monitoring Extn
16th Nov 20154:35 pmRNSPrice Monitoring Extension
16th Nov 20157:00 amRNSCommencement of Extraction of Bulk Sample
9th Nov 20157:00 amRNSUpdate for the quarter to 30 September 2015
27th Oct 20157:00 amRNSAppointment of Acting Mine Manager for Tatu
22nd Oct 201512:30 pmRNSHolding in Company
30th Sep 20157:01 amRNSInterim Results
4th Sep 201511:17 amRNSHolding in Company
3rd Sep 201511:30 amRNSHolding in Company
24th Aug 20157:00 amRNSTatu Coal Project Update
20th Jul 201510:10 amRNSDirector Shareholding
16th Jul 20159:37 amRNSApproval for Change of Control of Tatu Licence
14th Jul 20154:01 pmRNSTotal Voting Rights
6th Jul 20158:47 amRNSDirector/PDMR Shareholding
2nd Jul 20153:22 pmRNSResult of AGM
2nd Jul 20157:00 amRNSAGM Statement
1st Jul 20157:00 amRNSTotal Voting Rights
30th Jun 20157:00 amRNSDirectorate Changes
18th Jun 20157:00 amRNSMaiden Tatu Project JORC Resource Estimate
10th Jun 20159:41 amRNSFinal Results
8th Jun 20151:06 pmRNSIssue of Equity, Appointment of Joint Broker & AGM
1st May 20157:00 amRNSCorporate Update
10th Apr 201512:45 pmRNSGrant of Options
8th Apr 201511:53 amRNSDirector/PDMR Shareholding
31st Mar 20151:41 pmRNSAgreement to acquire Tatu Coal Mine
30th Mar 20153:24 pmRNSStatement re share price
26th Mar 20158:45 amRNSHolding in Company
26th Feb 20159:43 amRNSHoldings in Company
21st Jan 201511:02 amRNSDirectorate changes
9th Jan 201511:46 amRNSHolding(s) in Company
22nd Dec 201412:10 pmRNSEnd of Year Update
22nd Dec 20147:00 amRNSHolding(s) in Company
11th Dec 20149:36 amRNSHolding in Company
10th Dec 20149:36 amRNSHolding in Company
21st Nov 201410:11 amRNSDirector Dealing
19th Nov 20147:00 amRNSResignation of Director
31st Oct 20147:00 amRNSPositive HDM test work and corporate update
20th Oct 20147:00 amRNSNotification of major interest in shares
30th Sep 20148:57 amRNSInterim results for six months ended 30 June 2014
15th Sep 20147:00 amRNSHeavy Dense Media test work on Cobre material
1st Aug 20147:00 amRNSChange of Broker
28th Jul 20147:00 amRNSOperational and Corporate Update
27th Jun 201412:53 pmRNSResults of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.