Positive Wind Farm Project Update

27 Oct 2014 07:00

RNS Number : 2875V
Rame Energy PLC
27 October 2014
 



Click on, or paste, the following link into your web browser to view the associated PDF which includes photographs of the project:

 http://www.rns-pdf.londonstockexchange.com/rns/2875V_-2014-10-24.pdf

27 October 2014

Rame Energy / Index: Aim / Epic: Rame / ISIN: JE00BBD8GG53 / Sector: Energy

Rame Energy Plc ("Rame" or the '"Company")

Operational Update: Construction of Raki / Huajache Wind Farm Project Continues to Make Good Progress

Rame Energy Plc, the international power generator and engineering company, is pleased to announce an update on the construction of its fully funded 15MW Raki / Huajache Project ("the Project"), the Company's first equity participation in wind assets in Chile. This update is in line with Rame's strategy to become a niche independent power producer ('IPP'). Raki and Huajache are the first two of six wind farms with a combined capacity of 133MW currently under development by the Company's On-Grid Power Generation division.

 

A number of significant milestones have been achieved at the Project:

· Access roads, laydown areas and crane positions have been prepared

· Gravel piling beneath turbine foundations has been completed

· The first turbine foundation comprising of over 1,300 tonnes of concrete and 50 tonnes of steel reinforcement has been completed with the second foundation ready to be cast and work progressing well on the remaining three

· The trenches for inter array electrical cabling between the wind turbine generators have been completed

· The cabling between the onsite substation and the overhead export line has been completed

· Substation ground works have been completed and above ground works are underway

· All turbine components including blades, hubs, nacelles and tower sections have been delivered to Puerto Coronel and Puerto Liquen for final transportation to and assembly at the site

 

The completion stages of the Project; the erection and commissioning of the turbines, are due to start at the beginning of December 2014. Following commissioning of the Project, the power will be sold to EKA Chile S.A, a joint venture between AkZoNobel and Celulosa Arauco y Constitucion S.A for a period of 10 years. The Project's equity was funded under a joint venture with Santander, in which Rame has a 20% equity participation, and the debt has been provided by Chilean bank Banco BICE.

 

CEO Tim Adams said "Completing power projects on time and budget involves effective, proactive management and strong alignment between the project stakeholders and the contractors and suppliers performing the works. Rame is playing a critical role in this process and the successful achievement of the key stages of the Project outlined above is testament to the effectiveness of our project team and the strong working relationships we enjoy with our partners. With turbine erection now clearly in sight, we look forward to reporting on the completion phases of these first projects."

  

**ENDS**

 

 

 

For further information, please call one of the contacts below or visit the Company's website, www.rame-energy.com.

 

Rame Energy plc

Tel: +44 (0) 1752 565638

Tim Adams (Chief Executive)

Jan Gawel (Finance Director)

Northland Capital Partners Limited

Tel: +44 (0) 20 7382 1100

Nominated Adviser and Broker

Matthew Johnson / Lauren Kettle

(Corporate Finance)

John Howes / Alice Lane

(Corporate Broking)

St Brides Media & Finance Ltd

Tel: +44 (0) 20 7236 1177

Elisabeth Cowell / Frank Buhagiar

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPGGWAUUPCGCC
12
Date   Source Headline
30th Dec 201611:34 amRNSResignation of Nominated Adviser and Broker
26th Sep 20165:48 pmRNSAdministration process update
5th Sep 20168:42 amRNSAdministration process update
5th Aug 20167:06 amRNSAppointment of Administrators
28th Jul 20167:00 amRNSDirectorate Change
1st Jul 20167:30 amRNSSuspension - Rame Energy plc
1st Jul 20167:30 amRNSStatement Regarding Suspension
28th Apr 20167:00 amRNSPrivate Placement
25th Apr 20167:00 amRNSRame Secures US$4m InterEnergy Development Loan
20th Apr 20169:11 amRNSContract with Goldcorp in Argentina
18th Mar 20167:00 amRNSUpdate on Cerro Coihue Project
14th Mar 20167:00 amRNSCommercial Contract and Project Agreements
6th Jan 20167:00 amRNSSale of 15MW Raki and Huajache Wind Projects
1st Oct 20154:30 pmRNSRame Profiled by The Telegraph Business Club
29th Sep 20157:00 amRNSInterim Results
3rd Aug 20157:00 amRNSCommencement of Commercial Operations in Chile
20th Jul 20154:50 pmRNSResult of AGM
13th Jul 20157:00 amRNSChange of Adviser
10th Jul 20157:00 amRNSLaunch of UK Solar Generating Subsidiary
2nd Jul 20155:40 pmRNSNotice of Annual General Meeting
30th Jun 20155:40 pmRNSPosting of Report & Accounts
30th Jun 20157:00 amRNSFinal Results
27th May 20157:00 amRNSChilean On-Grid Wind Projects Update
20th May 20153:53 pmRNSHolding(s) in Company
20th May 20157:00 amRNSUpdate on Cerro Coihue Wind Power Project, Chile
24th Mar 20157:00 amRNSExpansion of Santander Agreement
13th Mar 20157:00 amRNSCerro Bayo Project Update
9th Mar 20157:00 amRNSUpdate on Chilean Wind Power Project
5th Feb 20157:00 amRNSUpdate on Raki/Huajache Wind Power Project, Chile
22nd Jan 20157:00 amRNSBoard Changes
19th Dec 20147:00 amRNSUpdate on Chilean Solar Projects
16th Dec 20147:00 amRNSUpdate on Raki / Huajache Wind Power Project
27th Oct 20147:00 amRNSPositive Wind Farm Project Update
17th Oct 20147:00 amRNSPPA to provide power to Cerro Bayo mine, Chile
3rd Oct 20147:00 amRNSDirectorate Change
2nd Oct 20147:00 amRNSLegislation Opens Up Domestic Chilean Solar Market
30th Sep 20147:00 amRNSInterim Results
5th Sep 20147:00 amRNSSecures Loan for £300,000
1st Sep 20147:00 amRNSTotal Voting Rights
28th Aug 20147:00 amRNSPlacing to Advance Wind Farms, Chile
18th Aug 20147:00 amRNSOperational Update
8th Aug 20147:00 amRNSEngineering Services Wins Contract with Barrick
6th Aug 20147:00 amRNSChange of Principle Place of Business Address
31st Jul 20147:00 amRNSNew Engineering Premises in Plymouth
28th Jul 201412:05 pmRNSResult of AGM
11th Jul 20144:10 pmRNSUpdate on Notice of AGM
8th Jul 20147:00 amRNSDirectorate Change
1st Jul 20147:00 amRNSMOU to provide power to Cerro Bayo mine, Chile
30th Jun 20144:38 pmRNSFinal Results for the Year Ended 31 December 2013
18th Jun 20147:00 amRNSAcquisition of Solar Energy Company
12

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.