Project Update

31 Mar 2015 07:00

RNS Number : 9119I
Ncondezi Energy Limited
31 March 2015
 

News Release

 

 

Project Update

 

31 March 2015: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to provide shareholders with an update in relation to its 300MW power plant project ("Ncondezi Project" or the "Project"), located near Tete in northern Mozambique.

 

Extension of Commercial Deal with EdM

 

On 15 December 2014 the Company announced that it was in the process of seeking an extension from Electricity de Mozambique ("EdM") to the period in which certain conditions precedent that relate to the conditional commercial deal signed between the parties in September 2014 are required to be satisfied. Following further discussions with EdM and progress made on the power project, EdM has formally agreed to extend the deadline for the conditions precedent.

 

The extension has been granted with the longstop date of September 30th, 2015, and is subject to the following conditions precedent:

 

· Reaching a binding agreement with a strategic investor acceptable to EdM, to be the key responsible party for the development, construction and operation of 300MW the power project.

 

· Bankable EPC and O&M agreements for the power plant, mine and common infrastructure.

 

· An agreed timetable with EdM, the strategic investor and Ncondezi to finalise the key commercial agreements, namely the Power Purchase Agreement, Power Concession Agreement and the Coal Supply Agreement.

 

The agreed commercial deal includes the range for the starting electricity tariff to be paid by EdM, which will then be subject to adjustments during the 25 year operational life of the Project. The starting tariff range is based on a number of assumptions including indexation, financing costs, coal costs, operator & maintenance costs and the technical parameters and capital costs contained in the binding Power Plant EPC bids. Based on a target project capital structure of 70% debt and 30% equity, the Company believes that the conditional commercial deal supports the economics of the Ncondezi Power Plant and provides a regionally competitive US$ based project equity IRR.

 

Transmission Line ESIA Approval

 

During March 2015, the Company received official notification from the Ministry for Coordination of Environmental Action ("MICOA") regarding the approval of the Environmental Social Impact Assessment ("ESIA") for the 92km transmission line that will connect the Project to the Mozambican national grid. This follows ESIA approvals that have already been granted on both the mine and power plant.

 

Current Cash Position

 

Following a detailed review of the Company's budget and the implementation of cost saving initiatives, management are comfortable that the Company has sufficient cash to support ongoing operations until Q1 2016. As of 28 February, 2015, the Company had US$3.7 million cash on its balance sheet.

 

Appointment of Chris Schutte as Chief Operating Officer

 

The Company is pleased to announce that Mr Chris Schutte has agreed to become the Chief Operating Officer of Ncondezi and will now sit on the Board as an Executive Director. Mr Schutte was appointed a Non-Executive Director of Ncondezi in February 2013 and led the Company's power plant EPC selection and binding bid process during 2014. Mr Schutte has worked in the power sector for more than 20 years and was previously Senior General Manager of the Group Technology Division and responsible for all the engineering functions at Eskom, including design accountability for new power stations, transmission lines and distribution development. Prior to this, he was Senior General Manger of Eskom's Generation Division, managing five power stations with over 18,000MW total installed capacity. He holds a degree in mechanical engineering.

 

 

 

 

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+44 (0) 20 7183 5402

Liberum Capital Limited:NOMAD & Broker

Richard Crawley / Christopher Britton

+44 (0) 20 3100 2000

finnCap:

Joint Broker

Christopher Raggett / Joanna Weaving

+44 (0) 20 7220 0500

Bell Pottinger:

Daniel Thöle/ Marianna Bowes

+44 (0) 20 7861 3232

 

Ncondezi Energy owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW.The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSDIFMSFISEFD
Date   Source Headline
13th Sep 20127:00 amRNSPositive DFS Results for Power Plant Project
12th Sep 20124:56 pmRNSHolding(s) in Company
6th Sep 201211:39 amRNSHolding(s) in Company
4th Sep 20127:00 amRNSInterim Results
20th Aug 20127:00 amRNSOperational Update
14th Aug 20124:23 pmRNSHolding(s) in Company
1st Aug 20127:00 amRNSAppointment of Joint Broker
27th Jul 20123:41 pmRNSResult of AGM
17th Jul 20122:54 pmRNSPress Speculation
29th Jun 20122:35 pmRNSHolding(s) in Company
21st Jun 201212:48 pmRNSCorrection: Directors Dealings
21st Jun 20127:00 amRNSDirectors Dealings
18th Jun 20127:00 amRNSProject Update
31st May 20124:37 pmRNSDirector/PDMR Shareholding
22nd May 20127:00 amRNSManagement Restructure
18th May 20127:00 amRNSFramework Agreement Signed
14th May 20127:00 amRNSChange of Adviser
26th Apr 20127:00 amRNSNcondezi Initiates Strategic Partner Search
23rd Apr 20127:00 amRNSFinal results for the year ended 31 December 2011
20th Mar 20127:53 amRNSNcondezi Project Coal Resource Upgrade
18th Jan 20127:00 amRNSNcondezi Infrastructure Agreement
21st Dec 20117:00 amRNSNcondezi Project South Block Resource Update
7th Dec 20117:00 amRNSAppointment of Joint Broker
6th Dec 20117:00 amRNSResult of Power Generation Studies
21st Nov 20117:00 amRNSCompany Update to Shareholders
30th Sep 20117:00 amRNSInterim Results
26th Jul 20112:45 pmRNSHolding(s) in Company
30th Jun 20112:15 pmRNSNotice of AGM
24th Jun 20117:00 amRNSFinal Results for the year ended 31 December 2010
10th Jun 20114:51 pmRNSReplacement Issue of Shares and Total Voting Right
10th Jun 20114:30 pmRNSIssue of Shares and Total Voting Rights
9th Jun 20117:00 amRNSIssue of shares and Total Voting Rights
27th May 20117:00 amRNSINITIAL COAL QUALITY RESULTS AND OPS UPDATE
3rd Mar 20117:00 amRNSDFS WORK PROGRAMME UPDATE
28th Jan 20117:00 amRNSSettlement of Placing Shares
20th Jan 201110:30 amRNSBuy-back of Shares
13th Jan 20113:15 pmRNSResult of Placing
13th Jan 20117:00 amRNSProposed cash placing
17th Dec 201010:48 amRNSAllotment of Shares
16th Dec 20102:50 pmRNSHolding(s) in Company
15th Dec 20107:00 amRNSNCONDEZI COMPLETES 2010 DRILL PROGRAMME
28th Sep 20103:45 pmRNSInterim Results
23rd Sep 20107:00 amRNSNcondezi commences core drilling
1st Sep 20107:00 amRNSCommencement of DFS Work Programme
15th Jul 201010:18 amRNSChange of Address, Agent and Company Secretary
11th Jun 201011:03 amRNSHolding(s) in Company
10th Jun 20107:00 amRNSAdmission to Trading on AIM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.