Operational Update

17 Nov 2022 07:00

RNS Number : 7473G
Jadestone Energy PLC
17 November 2022
 

 

Operational Update

 

17 November 2022 - Singapore: Jadestone Energy plc ("Jadestone" or the "Company"), an independent oil and gas production company focused on the Asia-Pacific region, is pleased to provide the following operational update.

 

Montara Project

 

Since the Company's H1 2022 results announcement on 20 September 2022, a comprehensive programme of hull and tank inspection, repairs and maintenance has been underway on the Montara Venture FPSO. In particular, the following activities have been carried out in recent weeks:

 

· Oil cargo tank 2C: the site of the original hull defect which resulted in the small release of oil in June 2022 has been removed and a permanent repair has now been completed. Initial visual inspection of the tank confirms the overall condition to be good, with a small number of minor defects to be addressed.

· Ballast water tank 4S: the bulkhead location of the defect identified in August 2022 has been repaired. Several smaller defects identified as part of a wider inspection of tank 4S are currently being repaired.

 

While the Company remains unable to advise on a restart date for Montara, based on the tank inspection activity to date it reaffirms an intent to remain within the lower end of the production guidance range announced on 12 September 2022, which would see Jadestone's 2022 production average at least 11,000 boe/d. 

 

Separately, the independent reviewer described in NOPSEMA's general direction dated 12 September 2022 was appointed in October, with the contract awarded to DNV, the world's leading maritime classification society and an independent expert in risk management and assurance. The gap recognition review, which has the intent of assuring Jadestone's remediation plans and operational readiness prior to the restart of production operations, is progressing well. DNV's report on this will be considered by NOPSEMA prior to the restart of production through the FPSO.

 

The Company currently estimates the cost incurred in 2022 in respect of the additional inspection and repair activities on the FPSO to be US$4 million, consistent with the initial US$2-4 million estimate published on 12 August 2022.

 

A short presentation containing photos of recent tank work on the Montara Venture FPSO is available from the Company's website at https://www.jadestone-energy.com/assets/australia-portfolio/montara/.

 

Stag Infill Drilling Programme

 

At the Stag field, the two infill wells Stag-50H and 51H have been drilled successfully and initial results from well data are in line with pre-drill expectations. The final completions are currently being run on both wells by the Valaris-107 rig, prior to it moving off location later this month. A further update will be provided once the wells are brought into production.

 

Liftings Schedule

 

The Company will lift over one million barrels of crude in November and December 2022, with a lifting of ~160,000 barrels recently from Montara, removing all remaining oil onboard the FPSO to help accelerate the inspection process. A lifting of approximately 620,000 barrels, attributable to Jadestone's recently acquired interest in the North West Shelf Oil Project, is expected imminently. Additionally, the next Stag lifting of ~190,000 barrels is provisionally timed for early December at a US$21.88/bbl premium to Brent, while a further two liftings from the Peninsular Malaysia assets are also expected prior to year-end 2022.

 

Paul Blakeley, President and CEO commented:

 

"Significant work has been undertaken at Montara in recent weeks, with completion of repairs in tank 2C and the 4S ballast tank being key milestones. The ongoing inspection and repair programme will underpin operational readiness and a safe restart of production.

 

We are building a solid baseline survey on the FPSO's remaining tanks - a fundamental step towards a risk-based inspection regime going forward. This survey, and the physical work underway on the FPSO, should help to ensure the highest levels of safety, integrity and vessel uptime in future, and maximise the life and value of the Montara fields for all our stakeholders."

 

For further information, please contact:

 

Jadestone Energy plc

Paul Blakeley, President and CEO

+65 6324 0359 (Singapore)

Bert-Jaap Dijkstra, CFO

Phil Corbett, Investor Relations Manager

+44 7713 687467 (UK)

ir@jadestone-energy.com

 

Stifel Nicolaus Europe Limited (Nomad, Joint Broker)

+44 (0) 20 7710 7600 (UK)

Callum Stewart

Jason Grossman

Ashton Clanfield

 

Jefferies International Limited (Joint Broker)

+44 (0) 20 7029 8000 (UK)

Tony White

Will Soutar

 

Camarco (Public Relations Advisor)

+44 (0) 203 757 4980 (UK)

Billy Clegg

jse@camarco.co.uk

Georgia Edmonds

Elfie Kent

 

About Jadestone Energy

 

Jadestone Energy plc is an independent oil and gas company focused on the Asia-Pacific region. It has a balanced, low risk, full cycle portfolio of development, production and exploration assets in Australia, Malaysia, Indonesia and Vietnam.

 

The Company has a 100% operated working interest in the Stag oilfield and in the Montara project, both offshore Australia. Both the Stag and Montara assets include oil producing fields, with further development and exploration potential. The Company also has a 16.67% non-operated interest in the North West Shelf Oil Project offshore Western Australia, comprising four oil fields containing significant upside potential through potential infill drilling and life extension activities.

 

The Company has interests in four oil producing licences offshore Peninsula Malaysia; two operated and two non-operated positions. Further, the Company has a 100% operated working interest in two gas development blocks in Southwest Vietnam, and an operated 100% interest (assuming completion of the Hexindo stake acquisition, as announced in November 2021) in the Lemang PSC, onshore Sumatra, Indonesia, which includes the Akatara gas field development, where first production is expected in the first half of 2024.

 

Led by an experienced management team with a track record of delivery, who were core to the successful growth of Talisman's business in Asia, the Company is pursuing an acquisition strategy focused on growth and creating value through identifying, acquiring, developing and operating assets in the Asia-Pacific region.

 

Jadestone Energy plc (LEI: 21380076GWJ8XDYKVQ37) is listed on the AIM market of the London Stock Exchange (AIM: JSE). The Company is headquartered in Singapore. For further information on the Company please visit www.jadestone-energy.com.

 

The information contained within this announcement is considered to be inside information prior to its release, as defined in Article 7 of the Market Abuse Regulation No. 596/2014 which is part of UK law by virtue of the European Union (Withdrawal) Act 2018.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEAKFXFLDAFEA
Date   Source Headline
3rd Jun 20257:00 amRNS-RPublication of 2024 Sustainability Report
2nd Jun 20257:00 amRNSAppointment of CEO
23rd May 20257:00 amRNSAward of Restricted Shares
20th May 20257:01 amRNSAnnual Report and Notice of AGM
20th May 20257:00 amRNS2024 Full-Year Results
6th May 20257:00 amRNSNotice of full-year 2024 results
24th Apr 20257:00 amRNSLiquidity Enhancement and Resilient Operations
16th Apr 20257:00 amRNSPortfolio Focus and Optimization – Sinphuhorm Sale
31st Mar 20257:00 amRNSSkua-11 Operations and Group Production Update
25th Mar 20257:00 amRNSDirector Share Dealing
20th Mar 20257:00 amRNSDirector and PCA Share Dealings
18th Mar 20257:00 amRNSSubmission of Vietnam Field Development Plan
25th Feb 20257:01 amRNSBlock Listing Six Monthly Return
25th Feb 20257:00 amRNS2024 Trading Update, Reserves and 2025 Guidance
11th Feb 20257:00 amRNSNotice of 2025 Guidance Release
10th Feb 20257:00 amRNSPCA Share Dealing Notification
20th Jan 20257:00 amRNSRecord 2024 exit rate and annual production
16th Jan 20257:00 amRNSBoard Changes
30th Dec 20247:00 amRNS-R2024 Executive Chairman Letter to JSE Shareholders
9th Dec 20247:00 amRNSCompletion of Akatara Performance Test
6th Dec 20247:00 amRNSVesting and Awards of Restricted Shares
5th Dec 20247:00 amRNSBoard Changes and Corporate Update
13th Nov 20247:00 amRNSDirector Share Dealing
11th Nov 20247:00 amRNSOperational Update
8th Nov 20247:00 amRNSVesting of Share Awards
29th Oct 20247:00 amRNSAppointment of CFO
17th Oct 202412:49 pmRNSSubstantial Shareholding Notification
3rd Oct 20247:00 amRNSDirector Share Dealing
17th Sep 20247:01 amRNS2024 Half Year Results
3rd Sep 20247:00 amRNSAkatara Facility Export Compressors Commissioned
3rd Sep 20247:00 amRNSNotice of H1 2024 Results
23rd Aug 20247:00 amRNSBlock Listing Six Monthly Return
19th Aug 20247:00 amRNSAkatara Update
31st Jul 20248:04 amRNSCommencement of Akatara Contractual Gas Sales
29th Jul 20247:11 amRNSTrading update for half-year ended 30 June 2024
26th Jul 20247:00 amRNSAward of SFA Cluster PSC Offshore Malaysia
17th Jul 20247:00 amRNSHolding(s) in Company
3rd Jul 20247:00 amRNSDirectorate Change
24th Jun 20247:00 amRNSIntroduction of First Gas at Akatara
13th Jun 202410:59 amRNSResults of AGM
13th Jun 20247:00 amRNSCorporate Update
6th Jun 20247:00 amRNSAkatara Update
24th May 20247:00 amRNSPublication of Sustainability Report
10th May 20247:00 amRNSNotice of AGM
9th May 20247:00 amRNSAppointment of Independent Non-Executive Director
29th Apr 20247:01 amRNSMailing of Annual Report
29th Apr 20247:00 amRNS2023 Full Year Results
26th Apr 20241:59 pmRNSSuccessful RBL Redetermination
17th Apr 20247:00 amRNSAdmission of Shares to Trading on AIM
11th Apr 202410:30 amRNSRestoration - Jadestone Energy plc

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.