Zambia Progress Update

13 Jul 2022 07:00

RNS Number : 2490S
Jubilee Metals Group PLC
13 July 2022
 

Jubilee Metals Group PLC

Registration number (4459850)

Altx share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company" or "the Group")

 

Dissemination of a Regulatory Announcement that contains inside information according to UK Market Abuse Regulations. Not for release, publication or distribution in whole or in part in, into or from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations of such jurisdiction.

 

 

Zambia Progress Update

Jubilee Metals Group PLC, a leader in metals processing with operations in Africa (AIM: JLP/Altx: JBL), is pleased to announce an update at its Zambian operations where the integration of the Sable Copper and Cobalt refinery with the newly constructed copper concentrator, Project Roan, continues as part of Jubilee's Southern Refining Strategy.

 

Highlights

 

- Cobalt refining circuit at the Sable Refinery entered the commissioning phase during June 2022 in line with original timing expectations, with first trial cobalt product produced per the expected commissioning and ramp up schedule:

Commercial production is targeted to commence during August 2022

The cobalt refining circuit at Sable is able to produce up to 1 200 tonnes of cobalt a year depending on the feed grade

- Commissioning and ramp up is progressing at the Project Roan concentrator reaching 65% of designed capacity with first filtered copper concentrate produced for refining at Sable as part of commissioning and ramp-up activities:

Ramp-up of the concentrator is expected to reach design capacities by the end of July 2022

At capacity, targets the processing of 830 tonnes of copper in concentrate per month for refining at Sable

Part of overall Southern Refining Strategy to reach 12 000 tonnes per annum of copper production capacity

Significant employment opportunities created, and local suppliers prioritised, to create a locally sustainable support infrastructure

 

 

Leon Coetzer, CEO, commented: "Reaching these significant milestones announced today put us in great stead for the financial year ahead, and beyond. It is testament to all the hard work by the Jubilee team that over the past 12 months have delivered on a bold implementation plan across both the PGM and chrome operations in South Africa and the copper and cobalt operations in Zambia.

 

"During this period in South Africa we delivered a new and upgraded Inyoni PGM facility to reach 45 000 PGM ounces per annum which includes a newly constructed and fully integrated 80 000 tonnes per month chrome beneficiation circuit. The circuit was further complimented with the inclusion of Jubilee's renowned ultra-fine chrome circuit earlier this year.

 

"In Zambia we have reached a key deliverable in the implementation of our copper and cobalt strategy as we announce the commissioning of the cobalt refining circuit at the Sable Refinery while ensuring that it is operationally ready to refine the copper concentrate from our newly commissioned Roan copper concentrator. The Roan concentrator, with the ability to produce an additional 10 000 tonnes of copper units annually for refining at Sable, continues to ramp-up its throughput in line with the commissioning schedule, reaching 65% of its design capacity to date and is expected to reach its full design capacity during July 2022.

 

"The Roan copper concentrator completes the implementation of Jubilee's Southern Refining Strategy targeted to deliver up to 12 000 tonnes of copper units per annum. This progress of the Southern Refining Strategy paves the way for the acceleration of our Northern Refining Strategy as we continue our expansion in Zambia and I look forward to reporting in future on the potential step-up in Jubilee's earnings on the back of this, and other, successful projects."

 

 

Further Details

 

Jubilee's copper strategy in Zambia includes, as its first phase, the implementation of its Southern Refining Strategy which targets to produce up to 12 000 tonnes of copper units per annum including a cobalt by-product from certain cobalt containing feed streams.

 

The strategy integrates the upgraded Sable Refinery with Project Roan, a new copper concentrator processing both Run-Of-Mine copper ore as well as tailings to produce copper concentrates for refining at Sable (10 000 tonnes per annum), which complements the existing supply of third-party feed to Sable refinery (2 000 tonnes per annum). The integrated Southern Refining Strategy's capital allocation is c. £ 19 million (ZAR 378 million).

 

Jubilee's project execution team broke ground for the construction of the new copper concentrator, Project Roan, in June 2021 and despite the challenges caused by the COVID 19 pandemic and its effect on supply chains the team was able to commence testing of certain equipment within seven months and completed all construction activity within 11 months which remains a remarkable achievement. Project Roan has reached a production throughput level pf 65% of design capacity and is expected to complete the ramp-up of the operation, which targets 830 tonnes of copper per month, during July 2022.

 

In addition to the copper refining capacity at Sable, Jubilee approved the implementation of a cobalt refining circuit at Sable able to produce up to 1 200 tonnes of cobalt per annum depending on the feed grade to the circuit. The new cobalt circuit commenced commissioning during June 2022 with the first test product produced as part of the commission of the circuit targeting to commence commercial production during August 2022.

 

Crucially, and in line with Jubilee's goals to promote sustained, inclusive economic growth, the Southern Refining Strategy has resulted in significant job creation, with total jobs filled in Zambia reaching over 700 during the last 12 months. Jubilee has prioritised sourcing of skills and services from its local communities and has in many instances partnered with local firms to assist in their growth and development to offer a sustained service to its projects.

 

 

United Kingdom

13 July 2022

 

 

For further information visit www.jubileemetalsgroup.com or contact:

Jubilee Metals Group PLC

Leon Coetzer

Tel: +44 (0) 20 7584 2155 / Tel: +27 (0) 11 465 1913

 

Nominated Adviser - SPARK Advisory Partners Limited

Andrew Emmott/James Keeshan

Tel: +44 (0) 20 3368 3555

 

PR & IR Adviser - Tavistock

Jos Simson/ Gareth Tredway/Charles Vivian

Tel: +44 (0) 207 920 3150

 

Joint Broker - Berenberg

Matthew Armitt/Jennifer Lee/Detlir Elezi

Tel: +44 (0) 20 3207 7800

 

Broker - Shard Capital Partners LLP

Damon Heath/Erik Woolgar

Tel: +44 (0) 20 7186 9900

 

Joint Broker - WHIreland

Harry Ansell/Katy Mitchell

Tel: +44 (0) 20 7220 1670/+44 (0) 113 394 6618

 

JSE Sponsor - Questco Corporate Advisory Proprietary Limited

Sharon Owens

Tel: +27 (11) 011 9212

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBKBBPKBKBQOD
Date   Source Headline
29th May 20267:00 amRNSNotice of General Meeting
28th May 20262:10 pmRNSStrategic Investment to Support Copper Growth
6th May 20267:00 amRNSOperational and Production Update 9m FY2026
29th Apr 20267:00 amRNSCapital Reduction Court Approval
20th Apr 20264:05 pmRNSHolding(s) in Company
8th Apr 20262:57 pmRNSResults of GM & Proposed Capital Reduction
31st Mar 20267:01 amRNSImplementation of Mine Plan at Molefe
31st Mar 20267:00 amRNSFinancial report for 6 months to end-December 2025
25th Mar 20267:05 amRNSMolefe Mine Phase 1 Drilling Results
24th Mar 20267:00 amRNSMolefe Mine Phase 1 Drilling Results delayed
23rd Mar 202610:05 amRNSReduction of Share Premium Account & Notice of GM
23rd Mar 20267:00 amRNSReduction of Share Premium Account & Notice of GM
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
27th Feb 20267:00 amRNSShareholder update and Dealing in securities
19th Feb 20267:00 amRNSOperational and Projects update H1 FY2026
23rd Jan 20267:00 amRNSChanges to the Board
14th Jan 20262:19 pmRNSResults of Annual General Meeting
6th Jan 20267:00 amRNSReceipt of US$10 million in funds from SA sale
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
17th Dec 20257:00 amRNSAudited Results for FY2025 & Notice of AGM
28th Nov 20257:00 amRNSMolefe Mine Co-Operation and Development Agreement
21st Nov 20257:00 amRNSOperational Update Zambia Q1 FY2026
17th Nov 20257:00 amRNSCompetition Tribunal Approval
17th Oct 20257:00 amRNSOperational Update South Africa Q1 FY2026
6th Oct 20256:06 pmRNSTR-1: notification of major holdings
6th Oct 20257:00 amRNSZambia Copper Strategy and SA Disposal Update
8th Sep 20257:00 amRNSDealing in securities
28th Aug 20252:05 pmRNSResults of General Meeting
12th Aug 20257:00 amRNSPosting of Circular & Notice of General Meeting
6th Aug 20257:00 amRNSZambia Copper and SA Business Proposed Sale Update
21st Jul 20257:00 amRNSQ4 Operational Update - South Africa
10th Jul 20257:00 amRNSChange of Broker and Proposed Disposal Update
19th Jun 20257:00 amRNSDirectorate Change
5th Jun 20257:00 amRNSProposed Disposal of Chrome and PGM Operations
28th May 20257:02 amRNSZambia Projects Update & Issue of equity
30th Apr 20257:40 amRNSZambia Progress Update
16th Apr 20257:00 amRNSOperational Update Q3 FY2025
14th Apr 20257:00 amRNSDirectorate Change
9th Apr 20257:00 amRNSTransaction on Surplus PGM Feed Material
3rd Apr 20257:00 amRNSJubilee Transaction on Large Waste Project
31st Mar 20257:00 amRNSInterim Financial Report 6 Months to December 2024
14th Feb 20257:00 amRNSRoan Commences High Grade Copper Production
6th Feb 20257:00 amRNSZambia Projects Update
21st Jan 20257:00 amRNSAdditional power supply secured for Roan re-start
13th Jan 20257:00 amRNSOperational Update H1 FY2025
24th Dec 20247:00 amRNSHolding(s) in Company
16th Dec 20247:00 amRNSZambia Operations Update and Exercise of Options
21st Nov 20247:00 amRNSTR-1: notification of major holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.