Implementation of Mine Plan at Molefe

31 Mar 2026 07:01

RNS Number : 7160Y
Jubilee Metals Group PLC
31 March 2026
 

Jubilee Metals Group PLCRegistration number: 4459850AIM share code: JLPAltx share code: JBLISIN: GB0031852162('Jubilee' or 'the Company' or 'the Group') 

Dissemination of a Regulatory Announcement that contains inside information according to UK Market Abuse Regulations. Not for release, publication or distribution in whole or in part in, into or from any jurisdiction where to do so would constitute a violation of the relevant laws or regulations of such jurisdiction.

 

Implementation of Mine Plan at Molefe to Support Stable Production and Growth

 

Jubilee, the integrated copper producer and resource developer in Zambia, is pleased to announce the updated near term mine plan of its Molefe Mine following the recent results from the Phase 1 drilling and trenching programme.

 

 

Key updates to the near term mine plan

 

· Connecting Pit 2 and 3 to form an enlarged open-pit mine allowing for an increased mining rate

· Investment into approximately 4 months' development work to further enlarge pit area and connect the two pits which includes the removal of approximately 400 000t of overburden material

· Once complete, the mining rate of the copper reef increases to 60 000t per quarter (from the current capacity of 15 000t per quarter) post completion of the combined Pit 2 and 3, at an average stripping ratio of 6:1 (bcm:bcm), equivalent to six bank cubic metres of waste per bank cubic metre of ore

· This is achieved by widening the targeted copper reef zone to deliver an average copper grade of approximate 1.4% TCu to surface, prior to applying targeted ROM sorting to classify the reef into high-grade and medium-grade stockpiles

· High-grade ore will be trucked to Sable refinery for direct leaching with the medium-grade stockpile targeted for on-site processing prior to refining at Sable refinery

· Phase 2 drilling programme, commencing soon will target the further definition of the eastern extension beyond the current Pit 1 based on the early results from the Phase 1 drilling programme, which confirmed the existence of a significant extended copper mineralisation

Statement from Leon Coetzer, Chief Executive Officer:

"This marks another important milestone in Jubilee's transition towards becoming a resource-backed copper producer, with the implementation of a structured mine plan at Molefe providing a clear pathway to sustainable and scalable production. Operations at Molefe Mine continue to perform well and expand whilst we have simultaneously prioritised resource development. This plan reflects a disciplined approach to balancing production with long-term value creation.

 

The integration of Pit 2 and 3, together with an accelerated stripping programme, positions the operation to deliver a stable and consistent feed to our Sable Refinery. By prioritising the direct processing of high-grade material while upgrading medium-grade ore on-site, we are accelerating cash generation and maximising value from the resource.

 

Importantly, our focus now extends to unlocking the full potential of the Molefe Project. Drilling of the eastern extension is the immediate focus of the Phase 2 programme, with the objective of progressing this area into construction and first production within the next 12 months. This represents a key step in expanding the scale of operations and extending the life of the project. We believe this phased development approach strengthens our ability to deliver reliable copper production while building a long-term, resource-driven growth platform in Zambia."

 

Overview

 

The mine plan follows a period of exploratory drilling and evaluation of in-pit sampling and trenching and is designed to support the delivery of a consistent supply of ore to the Sable refinery while advancing the long-term development of the project. Recent drilling results have supported the integration of Pit 2 and 3 into a single, larger open pit. This allows for an accelerated stripping and pushback programme, improving mining efficiencies and access to the targeted copper reef. The initial phase of the mine plan is focused on establishing a stable production profile, targeting ore delivery in excess of 15 000tpm to the Sable Refinery at a more consistent grade and at a sustainable unit cost per tonne. The updated mine plan has been optimised to target a broader reef package, enabling the extraction of increased copper volumes across both high and medium-grade material. This will be supported by the introduction of automated ore sorting on site allowing for the efficient classification of mined material. High-grade ore will be transported directly to the Sable refinery for immediate processing while medium-grade material will be treated on-site using an acid curing process to enhance copper solubility and overall recovery. This integrated strategy is designed to maximise resource utilisation, improve efficiencies and accelerate the conversion of mined material into revenue.

 

Importantly, the next phase of development which will commence with the Phase 2 drilling programme, is focused on the eastern extension of the resource with the objective of progressing this area into construction and thereafter production within the next 12 months. This supports the continued expansion of the resource base, with further drilling expected to extend mineralisation along strike and increase the overall mine life. The Company believes this phased approach balances near-term production delivery with longer-term growth, positioning Molefe Mine as a reliable and scalable source of copper feed to its Zambian processing operations.

 

Near term upgraded mine plan for Molefe Mine

 

 

 

 

Mine Plan implementation timeline

 

Month 1-3

Month 4-6

Month

7-9

Month

10-12

WASTE BCM (wet)

bcm*

352230

310014

236360

99377

ORE BCM (wet)

bcm

7791

50006

50000

50000

Total Cu Ore BCM (dry)

bcm

5843

37504

37500

37500

ORE Tonnes (dry)

tonnes

9349

60007

60000

60000

Total Cu Grade

%

0.9

1.3

1.4

1.6

Contained Cu mined

tonnes

88

758

842

944

STRIPPING RATIO (bcm:bcm)

bcm:bcm

6:1 average across period

 

 

*Bank Cubic Metres (in-situ volume) - reflects waste to ore movement

 

The technical information contained in this announcement has been reviewed, verified, and approved by Colin Bird, Chartered Engineer (CC.ENG), Fellow of The Institute of Materials, Minerals & Mining (FIMMM), South African and UK Certified Mine Manager with more than 40 years' experience primarily in underground and open cast mining. He has managed both base metal and gold operations on a global basis.

 

 

 

31 March 2026

 

For more information contact:

 

Jubilee Metals Group PLC

Leon Coetzer (CEO)/Jonathan Morley-Kirk (FD)

Tel: +27 (0) 11 465 1913 / Tel: +44 (0) 7797 775546

 

Nominated Adviser - SPARK Advisory Partners Limited

Andrew Emmott/James Keeshan

Tel: +44 (0) 20 3368 3555

 

PR & IR Adviser - Tavistock

Jos Simson/Gareth Tredway

Tel: +44 (0) 207 920 3150

 

Joint Broker - Zeus Capital

Harry Ansell/Katy Mitchell 

Tel: +44 (0) 20 7220 1670/+44 (0) 113 394 6618

 

Joint Broker - Shard Capital Partners LLP

Erik Woolgar/Gareth Burchell

Tel +44 (0) 207 1869900

 

JSE Sponsor - Questco Corporate Advisory Proprietary Limited

Alison McLaren

Tel: +27 63 482 3802

 

About Jubilee Metals Group

 

Jubilee Metals, listed on AIM and the Altx of the JSE, is a copper producer focused on building a world-class integrated copper business in Zambia. The Company aims to reach 25 000 tonnes per annum of copper production by integrating exploration, mining, concentrating and refining through its three-pillar strategy, combining the Roan concentrator, the Sable refinery and regional mining assets and the Large Waste Rock Project. Led by an experienced team, Jubilee applies innovative technologies to transform previously underutilised materials into value while supporting circular resource use and strong environmental stewardship.

 

For more information, please visit www.jubileemetalsgroup.com and follow Jubilee on X at @Jubilee_Metals

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDWPUUAWUPQPUU
Date   Source Headline
29th May 20267:00 amRNSNotice of General Meeting
28th May 20262:10 pmRNSStrategic Investment to Support Copper Growth
6th May 20267:00 amRNSOperational and Production Update 9m FY2026
29th Apr 20267:00 amRNSCapital Reduction Court Approval
20th Apr 20264:05 pmRNSHolding(s) in Company
8th Apr 20262:57 pmRNSResults of GM & Proposed Capital Reduction
31st Mar 20267:01 amRNSImplementation of Mine Plan at Molefe
31st Mar 20267:00 amRNSFinancial report for 6 months to end-December 2025
25th Mar 20267:05 amRNSMolefe Mine Phase 1 Drilling Results
24th Mar 20267:00 amRNSMolefe Mine Phase 1 Drilling Results delayed
23rd Mar 202610:05 amRNSReduction of Share Premium Account & Notice of GM
23rd Mar 20267:00 amRNSReduction of Share Premium Account & Notice of GM
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
12th Mar 20267:00 amRNSHigh-Grade Feed Secured & Large Waste Rock Update
27th Feb 20267:00 amRNSShareholder update and Dealing in securities
19th Feb 20267:00 amRNSOperational and Projects update H1 FY2026
23rd Jan 20267:00 amRNSChanges to the Board
14th Jan 20262:19 pmRNSResults of Annual General Meeting
6th Jan 20267:00 amRNSReceipt of US$10 million in funds from SA sale
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
2nd Jan 20267:00 amRNSClosing of Sale of South African Operations
17th Dec 20257:00 amRNSAudited Results for FY2025 & Notice of AGM
28th Nov 20257:00 amRNSMolefe Mine Co-Operation and Development Agreement
21st Nov 20257:00 amRNSOperational Update Zambia Q1 FY2026
17th Nov 20257:00 amRNSCompetition Tribunal Approval
17th Oct 20257:00 amRNSOperational Update South Africa Q1 FY2026
6th Oct 20256:06 pmRNSTR-1: notification of major holdings
6th Oct 20257:00 amRNSZambia Copper Strategy and SA Disposal Update
8th Sep 20257:00 amRNSDealing in securities
28th Aug 20252:05 pmRNSResults of General Meeting
12th Aug 20257:00 amRNSPosting of Circular & Notice of General Meeting
6th Aug 20257:00 amRNSZambia Copper and SA Business Proposed Sale Update
21st Jul 20257:00 amRNSQ4 Operational Update - South Africa
10th Jul 20257:00 amRNSChange of Broker and Proposed Disposal Update
19th Jun 20257:00 amRNSDirectorate Change
5th Jun 20257:00 amRNSProposed Disposal of Chrome and PGM Operations
28th May 20257:02 amRNSZambia Projects Update & Issue of equity
30th Apr 20257:40 amRNSZambia Progress Update
16th Apr 20257:00 amRNSOperational Update Q3 FY2025
14th Apr 20257:00 amRNSDirectorate Change
9th Apr 20257:00 amRNSTransaction on Surplus PGM Feed Material
3rd Apr 20257:00 amRNSJubilee Transaction on Large Waste Project
31st Mar 20257:00 amRNSInterim Financial Report 6 Months to December 2024
14th Feb 20257:00 amRNSRoan Commences High Grade Copper Production
6th Feb 20257:00 amRNSZambia Projects Update
21st Jan 20257:00 amRNSAdditional power supply secured for Roan re-start
13th Jan 20257:00 amRNSOperational Update H1 FY2025
24th Dec 20247:00 amRNSHolding(s) in Company
16th Dec 20247:00 amRNSZambia Operations Update and Exercise of Options
21st Nov 20247:00 amRNSTR-1: notification of major holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.