Projects Status Update

7 Jun 2018 07:00

RNS Number : 5732Q
Jubilee Metals Group PLC
07 June 2018
Β 

Jubilee Metals Group PLC

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company")

Β 

Projects Status Update

Β 

Projects Highlights

Β 

Β· Hernic project achieves record production of 2 101 PGM* ounces for the month of May with Q2 2018 already touching 4Β 000 PGM ounces in the first two months

Β· First PGM material from PlatCro targeted for delivery to Northam in June 2018

Β· Construction of Kabwe project underway with initial focus on the zinc leach circuit

Β· Implementation of the fine chrome recovery circuit at DCM underway

* 6 Element Platinum Group Metals

Β 

Leon Coetzer, Chief Executive Officer, says: "

Β 

I am particularly pleased with the performance of our Hernic operation. The Hernic operation continues to set new benchmarks quarter on quarter with May setting a new record high delivering an impressive 2101 PGM ounces. At the current production rates we are expecting to increase the production of PGM ounces by more than 20% during Q2 2018 compared with Q1 2018.

Β 

We have awarded the transport contract to commence with the delivery of ourPlatCro PGM material to Northam Platinum for the recovery of the PGM's..

The construction of our Kabwe project is underway following the reinstatement of the mining licence by the Zambian authorities. Our initial focus is on the implementation of the zinc recovery circuit. I will provide further details and clarity on the project following my presentation to the Zambian Mining Department later this month.

Β 

At DCM we have commenced with the implementation of the hydro-mining circuit to replace the mechanical reclamation of the tailings material. This switch-over forms part of the installation of the integrated fine chrome recovery circuit which is the pre-cursor to the platinum recovery circuit at DCM."

Β 

Β 

Β 

Β 

Hernic Platinum and Chrome Operation (South Africa)

Β 

The production rate during the first two months of Q2 2018 continues to show a significant increase in PGM ounces compared with the previous quarter. Production during May 2018 has set a new record high for the operation of 2 101 ounces, an increase of 12% on the previous reported high. The ounces produced to date for Q2 2018 equals 3Β 972 with a target being set of 6Β 000 ounces for the full quarter (equates to a targeted growth of 22.5% quarter-on-quarter). The corresponding financial numbers for the quarter-to-date is yet to be finalised.

Β 

Production performance of the Hernic project for Q1 2018 and Q2 2018 month-to-date as follows:

Β 

Β 

Tailings processed Tonnes

PGM Ounces delivered*

Β 

Β 

Β 

Jan-18

26 073

1284

Feb-18

38 052

1755

Mar-18

46 284

1858

Q1 2018

110 409

4897

Apr-18

39 458

1871

May-18

39 734

2101

Jun-18

-

-

Β Q2 2018**

79 192

3 972

Β 

Β 

Β 

Project to date

497 745

16305

*Ounces calculated based on assays received to date and subject to final metal accounting.

**Quarter 2 2018 numbers include only the months of April and May 2018.

Β 

PlatCro Platinum Project (South Africa)

Β 

Jubilee executed a processing agreement with Northam Platinum's Eland Platinum operation to process the PlatCro PGM material as announced in April 2018. The project targets the processing of 60Β 000 tonnes of PGM material per month equating to the production of approximately 2Β 800 PGM ounces per month. Jubilee has awarded the transport contract for the delivery of the PGM material and the first delivery to Northam is expected to commence during June 2018.

Β 

Kabwe Zinc, Lead and Vanadium Project (Zambia)

Β 

Our Jubilee and BMR teams are hard at work with the construction of the Kabwe project in Zambia. The initial construction focus is on the zinc primary leach recovery circuit.

Β 

The lead and vanadium project schedule will be concluded following completion of the circuit optimisation work currently undertaken by Jubilee.Β The circuit optimisation test work by Jubilee's research and development team includes work to evaluate the optimal product purity specifications. Further detail relating to the project's implementation schedule and design specifications will be provided following the presentation to the Zambian Mining Authorities during June 2018.

Β 

Clarification note on settlement of historical creditors by BMR Group PLC ("BMR")

Β 

Jubilee wishes to clarify the conditions under which Jubilee has agreed to allow BMR to allocate a portion of its existing holding of Jubilee shares to settle certain approved BMR creditors.

Β 

Under the agreement reached with BMR, such number of Jubilee shares as required to settle the approved creditors will be placed into a Jubilee nominated broker account ("transferred shares"). The transferred shares will be now be under Jubilee's control for onward placing to ensure orderly market conditions.

Β 

Β 

United Kingdom

7 June 2018

Β Contacts

Jubilee Metals Group PLC

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0) 1752 221937

Nominated Adviser

SPARK Advisory Partners LimitedMark Brady/Andrew EmmottTel: +44 (0) 203 368 3555

Broker

Shard Capital Partners LLPDamon Heath/Erik WoolgarTel +44 (0) 20 7 186 9900

JSE Sponsor

Sasfin Capital (a member of the Sasfin group)

Sharon OwensTel +27 (0) 11 809 7500

Β 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
Β 
END
Β 
Β 
DRLFKADKCBKDAAK
Date   Source Headline
9th Oct 20098:41 amRNSNotification of Major Interests in Shares
7th Oct 20094:30 pmRNSResults of General Meeting
30th Sep 20091:00 pmRNSIssue Of Ordinary Shares For Cash
29th Sep 20091:49 pmRNSPreliminary Audited Results and Notice of AGM
25th Sep 20095:00 pmRNSTrading Statement
22nd Sep 200912:00 pmRNSIssue of Equity
14th Sep 200912:31 pmRNSPosting of Circular
14th Sep 200912:30 pmRNSOffer for Braemore Resources plc update
14th Sep 200912:30 pmRNSUpdate on offer by Jubilee Platinum
7th Aug 200911:00 amRNS?13.25m placing for cash
6th Aug 200912:00 pmRNSAdditional Listing
31st Jul 200912:00 pmRNSPreference Share Subscription
21st Jul 20094:00 pmRNSAdditional Listing
15th Jul 20093:00 pmRNSIssue of shares
3rd Jul 200910:30 amRNSOffer for Braemore
3rd Jul 200910:30 amRNSOffer by Jubilee Platinum plc
3rd Jul 200910:30 amRNSProposed Acquisition of Braemore Resources Plc
29th Jun 20094:30 pmRNSCorrection - Cautionary announcement
29th Jun 20093:00 pmRNSCautionary announcement
4th Jun 200910:30 amRNSTjate resource statement
2nd Jun 200911:02 amRNSResults of General Meeting
26th May 20097:00 amRNSIssue of Equity
21st May 20097:00 amRNSDirectors Dealings
19th May 20099:30 amRNSProduction and Smelting Agreement
19th May 20099:30 amRNSProduction and smelting agreement
6th May 200911:00 amRNSDeferred Share Agreement
23rd Apr 20092:00 pmRNSIssue of Equity
26th Mar 20094:04 pmRNSInterim Results
9th Mar 20099:00 amRNSChange of Advisers
18th Feb 20099:00 amRNSCompletion of Drilling Programme at Tjate
6th Feb 20092:30 pmRNSMadagascar update
26th Nov 200811:30 amRNSResult of AGM
4th Nov 200811:30 amRNSJoint Venture
22nd Oct 20083:00 pmRNSDirectors Dealings
8th Oct 20082:15 pmRNSDirectors Dealings
8th Oct 20081:30 pmRNSDirectors Dealings
11th Aug 20087:00 amRNSDrilling Update at Tjate
26th Jun 20087:00 amRNSDirectors Dealings
25th Jun 20083:00 pmRNSDirectors Dealings
19th Jun 20088:30 amRNSIncreases interest in the Tja
9th Jun 20087:00 amRNSDrilling Update at Tjate
3rd Jun 200812:30 pmRNSDirectors Dealings
2nd Jun 200810:30 amRNSDirectors Dealings
16th Apr 20087:00 amRNSIssue of Shares
8th Apr 20087:00 amRNSMadagascar Drilling Update
2nd Apr 20087:01 amRNSShare Acquisition in NewPlats
25th Mar 20087:01 amRNSShare Acquisition in NewPlats
13th Mar 20087:00 amRNSInterim Results
5th Mar 20087:00 amRNSDrilling Update - Madagascar
21st Feb 20087:00 amRNSAmbodilafa Drilling Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.