Less Ads, More Data, More Tools Register for FREE

Pin to quick picksJubilee Metals Regulatory News (JLP)

Share Price Information for Jubilee Metals (JLP)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 6.85
Bid: 6.80
Ask: 6.90
Change: -0.49 (-6.68%)
Spread: 0.10 (1.471%)
Open: 6.80
High: 6.85
Low: 6.60
Prev. Close: 7.34
JLP Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Platinum Projects update

18 Aug 2016 07:00

RNS Number : 4855H
Jubilee Platinum PLC
18 August 2016
 

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

 

 18 Aug 2016

 

Jubilee Platinum PLC

("Jubilee" or "Company")

 

Platinum Projects update

 

Mine-to-Metals specialist Jubilee Platinum plc (AIM: JLP, AltX: JBL) is pleased to provide, on behalf of its subsidiary, Jubilee Tailings Treatment Company Pty Ltd ("JTTC"), a performance, operational and financial update of its chrome recovery section of the Dilokong Chrome mine tailings project ("DCM Tailings" or "DCM Project") and a progress update on the Hernic PGM-bearing chrome tailings project ("Hernic Project").

Highlights

· Chromite concentrate production of the DCM Project up 29 % to 9 670 tons in the month of July 2016 compared with June 2016

· Project revenue from the sale of chromite concentrate for the month of July 2016 up 33% to GBP 0.692 million (ZAR 12.1 million) compared with the month of June 2016

· Chromite project earnings from chromite concentrate for the month of July 2016 up 46% to GBP 0.520 million (ZAR 9.075 million) compared with the month of June 2016

· Earnings attributable to Jubilee for the month of July 2016 from chromite concentrate production up 30% to GBP 0.293 million (ZAR 5.114 million) compared with the month of June 2016

· Since the start of the project in April 2016, project revenue of GBP 1.69 million (ZAR31.2 million) generated from chromite concentrate sales

· Since the start of the project in April 2016, project earnings of GBP 1.26 million (ZAR23.28 million) generated from chromite concentrate sales

· Upgraded platinum values in surface material after chromite removal continue to exceed design expectations further increasing expected saleable value of the contained platinum concentrate

· Jubilee is concluding the audit of the operational readiness at an existing platinum operation and is scheduling a full scale commercial trial, which forms part of the option study for toll processing as an alternative to building its own platinum plant at DCM. This option potentially offers significant project upside

· Construction at the Hernic Project of the 660 000 tons per annum platinum and chromite processing plant continues to progress to schedule targeting commencement of commissioning in December 2016

· Project Capital expenditure on the Hernic Project to date of GBP 6.2 million (ZAR 108.1 million) equivalent of 55% of total estimated Project Capital which is commensurate with the percentage project completion

Leon Coetzer, Chief Executive commented:

"Increased production month to month is very encouraging for the Company and endorses previous decisions to focus on chrome and platinum. The enriched platinum material stock pile continues to grow and we are progressing options to turn stockpile to cash.

I am pleased with the progress at Hernic where construction is on schedule and on budget. Looking back at the years' work and results I am encouraged by our team's commitment and skills and am looking forward to taking full advantage of the current position and the opportunities presented to us. "

Overview

The DCM Project has continued to outperform the original design numbers both in terms of revenue and earnings from chromite concentrate sales as well as operational performance. The month of July has shown further improvements in operational performance which has more than offset the slight drop in the saleable value per ton of chromite produced. The Company continues to process only current surface material at DCM and have not commenced with the processing of 3d party ore which offers the potential to significantly further enhance the operational performance numbers.

The enrichment of the platinum material which is produced by recovering chromite from the surface material and rejecting low value waste, continues to exceed our projections due to the high operational efficiencies maintained at DCM. The enriched platinum material continues to be stockpiled at DCM pending the outcome of the platinum processing option study.

The option study which focusses on toll processing as an alternative to building the Company's own platinum plant at DCM will be concluded shortly. At present the Company's engineers are completing an operational readiness audit of a target platinum recovery plant to establish final time lines and required working capital. A full scale commercial trial of the enriched platinum material as a final test to confirm modelled financial numbers are also being scheduled.

If the option study proves successful there will be no need to build a dedicated platinum plant and platinum revenues will be received at least one year earlier.

The Hernic project is in full execution mode with construction progress of the platinum and chromite recovery plants illustrated by continually updated project pictures on our website. The month of August and September 2016 will show accelerated visual progress on site, as the large platinum flotation units are being positioned onto the completed civil structures.

 DCM OPERATIONAL AND FINANCIAL PERFORMANCE

Chromite concentrate tons produced

Project revenue (GBP'000)

Project revenue (ZAR'000)

Project earnings (GBP'000)

Project earnings (ZAR'000)

Jubilee attributable project earnings (GBP'000)

Jubilee attributable project earnings (ZAR'000)

July 2016

9 670

692

12 100

520

9 075

293

5 114

June 2016

7 480

519

9 905

356

6 793

226

4 315

% change month on month

29%

33%

22%

46%

34%

30%

19%

Q2 2016

(May, June 2016)

15 188

1,002

19,137

744

14,203

456

8,710

YTD

24 927

1 671

31 218

1 263

23 278

749

13 824

 

July 2016 production showed significant improvement from the stable production levels reached in June 2016 with an increase in production of saleable chromite concentrate of 29% reaching a new monthly high of 9 670 tons.

All chromite production to date at DCM is from the processing of platinum and chrome containing surface tailings alone. Stated Project earnings is net of operational cost and cost of chromite concentrate sales.

The saleable chromite concentrate price in ZAR terms reduced in July 2016 due to the strengthening of the ZAR against the US dollar and other major currencies. Jubilee was able to offset this drop in the ZAR chromite concentrate price by improved operational efficiencies as illustrated by the increased production rate for July 2016. The operational cost at DCM is incurred in ZAR.

 

Disposal of Middelburg operations

 

The Company announced in February 2016 an update on the final payment due to the Company regarding the disposal of 100% of the issued shares in Jubilee Smelting and Refining Proprietary Limited ("JSR"), and 70% of the issued shares in Power Alt Proprietary Limited ("PA") ("Disposal"), to Siyanda Resources Proprietary Limited ("Siyanda") through its newly named nominated special purpose vehicle Hornbill Investments Proprietary Limited ("SPV"). As stated previously 10% of the remaining 15% of the purchase consideration is held in escrow with an approximated amount of GBP0.510 million (ZAR8.9 million), net of closing adjustments including stock and supplier adjustments. This amount was due by the SPV to Jubilee following the expiry of the first warranty period on 31 December 2015 (90 days after the closing date of 30 September 2015). Payment has however not yet been made. Release of this escrow amount to the Company has been frustrated by an unsubstantiated warranty claim submitted by the SPV. The Company has informed the SPV that it rejects the legitimacy of such a claim and will take all necessary steps to ensure the release of the escrow amount due to the Company. We will continue to update shareholders on progress made.

 

Contacts

Jubilee Platinum plc

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0)1752 221937

JSE Sponsor

Sasfin Capital, a division of Sasfin Bank LimitedSharon OwensTel +27 (0)11 809 7500

Nominated Adviser

SPARK Advisory Partners LimitedSean Wyndham-Quin/Mark BradyTel: +44 (0)203 368 3555

Broker

Beaufort Securities LimitedJon BellissTel: +44 (0) 20 7382 8300

 

About ASA

Pollux Investment Holdings Pty Ltd ("Pollux"), a wholly owned subsidiary of Jubilee, holds the exclusive rights to beneficiate the platinum group metals ("PGM's") from the platinum-containing surface material at ASA Metals Proprietary Limited ("ASA") ("DCM Platinum Project, Processing Agreement").

 

The Company has targeted the construction of a New Processing Plant for the recovery of chrome and PGMs capable of processing up to 35 000 tons of surface material per month. The Company executed an addendum to the Processing Agreement ("Addendum"), whereby the Company is incentivised to accelerate the construction and commissioning of the New Processing Plant by targeting commencement of commissioning of the front end of the New Processing Plant early 2016. This target has been achieved. The Addendum significantly enhances and expedites the projected profitability of the project since both the chrome concentrate and platinum containing concentrate will now contribute to the overall profitability of the DCM Platinum Project. The Project is the first of the Company's Platinum Projects.

 

About the Hernic Project

Hernic Ferrochrome Proprietary Limited ("Hernic") is the world's 4th largest integrated ferrochrome producer with an estimated 3 million tons of platinum containing material at surface while Hernic continues to add further material to the surface stock.

The Company was selected as the exclusive party to beneficiate the chromite and PGMs contained in the Hernic Surface Material ("the Project") and address the project execution methodology as well as the operational and financial performance targets. The Project is the second of the Company's Two Projects.

The Hernic Surface Material has been independently fully drilled and assayed for chrome and PGM content. This has resulted in an independent resource statement of 1.7 million tons, of which approximately 90% of the resource is classified in the measured category under the internationally recognised SAMREC code. Hernic also has access to secondary surface stocks, which it has internally identified and could increase the surface stocks to in excess of 3 million tons through further drilling programmes. The total Project is estimated to contain PGM ounces in excess of 224 000 (3PGM + Au) oz.

The Project will be the largest PGM beneficiation plant of surface chrome tailings in South Africa and is capable of producing annual revenues of GBP 18.2 million (ZAR 400 million) at an average metal basket price of USD 906 per (3PGM + Au) oz. The financial and operational risks of the Project are significantly mitigated since the material is already at surface and requires neither the cost nor the risk associated with mining.

An extensive prefeasibility study has been concluded on the Project, which included both pilot scale and full commercial scale trials to confirm the design and operational parameters.

The Project is to be undertaken in four phases over an 11 month period; namely

1. Phase one - Bankable Feasibility Study and Engineering Design. -- Completed.

2. Phase two - Construction of the chrome and platinum processing plant ("Processing Plant"). --On-going

3. Phase three - Commissioning and Ramp up of Processing Plant to design capacity of 55 000 tons per month.

4. Phase Four - Stable operation of the Processing Plant.

The Company has targeted a combined processing of platinum containing surface material over the two projects in excess of 900 000 tons per annum.

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFERTEIDLIR
Date   Source Headline
18th Apr 20247:00 amRNSOperational Update Q3 FY2024
28th Mar 20247:00 amRNSProjects Update
6th Mar 20243:00 pmRNSExercise of Options
6th Mar 20247:00 amRNSChanges to the Board & New Dedicated Exec Boards
29th Feb 20247:00 amRNSInterim Results 2023 Presentation
28th Feb 20249:31 amRNSInterim Results 2023 Presentation Re-scheduled
26th Feb 20247:00 amRNSInterim Financial Report 6 months to December 2023
8th Feb 20247:00 amRNSZambia Copper Expansion Update
23rd Jan 20247:00 amRNSOperational and Projects Update Q2 FY2024
4th Jan 20243:00 pmRNSTR-1: Notification of major holdings
3rd Jan 202412:00 pmRNSResults of General Meeting
15th Dec 20231:53 pmRNSResults of Placing and Notice of General Meeting
15th Dec 20237:00 amRNSProposed Placing
13th Dec 20232:30 pmRNSReply to Shareholder Correspondence Regarding a GM
12th Dec 20237:00 amRNSInvestment in Historical Waste Rock Dump in Zambia
21st Nov 20233:30 pmRNSInvestor Webcast
17th Nov 20237:00 amRNSNew Corporate Presentation
3rd Nov 20231:30 pmRNSResult of AGM
1st Nov 20237:05 amRNSQ1 Operational Report to 30 September 2023
17th Oct 20237:00 amRNSAward of New Slag Project with Mopani Copper Mines
11th Oct 20237:00 amRNSFinal Results and Notice of AGM
5th Oct 20237:00 amRNSNotice of Results
21st Aug 20237:00 amRNSSouth Africa and Zambia Project Expansion Update
14th Aug 20237:00 amRNSAppointment of CFO and Head of Energy Metals
20th Jul 20237:00 amRNSOperational Update for full year to 30 June 2023
6th Jun 20237:00 amRNSEXPANSION OF CHROME AND PGM FOOTPRINT
4th May 20233:29 pmRNSExercise of Options
24th Apr 20237:00 amRNSCompany Update
23rd Mar 20234:35 pmRNSPrice Monitoring Extension
20th Mar 20237:00 amRNSHalf-Yearly Financial Report to 31 December 2022
17th Mar 20237:00 amRNSNotice of Results
17th Feb 20231:00 pmRNSDirector/PDMR Shareholding
17th Feb 20237:00 amRNSDirector/PDMR Shareholding
16th Feb 20237:00 amRNSInvestor Presentation
15th Feb 20239:05 amRNSSecond Price Monitoring Extn
15th Feb 20239:00 amRNSPrice Monitoring Extension
15th Feb 20237:00 amRNSOperations Update 6 months to 31 December 2022
24th Jan 202312:11 pmRNSTR-1: Notification of major holdings
23rd Jan 20238:00 amRNSExercise of Warrants
18th Jan 20233:48 pmRNSExercise of Warrants - Correction
18th Jan 20238:00 amRNSIssue of Equity
13th Jan 20232:05 pmRNSSecond Price Monitoring Extn
13th Jan 20232:00 pmRNSPrice Monitoring Extension
12th Jan 20234:40 pmRNSSecond Price Monitoring Extn
12th Jan 20234:35 pmRNSPrice Monitoring Extension
19th Dec 20227:00 amRNSZambia Update, Corporate Update & Warrant Exercise
24th Nov 20227:30 amRNSExercise of Warrants
22nd Nov 20228:51 amRNSCopper and Cobalt Operations Update
18th Nov 202212:00 pmRNSExercise of Warrants
16th Nov 20223:48 pmRNSResult of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.